The document outlines 16 points to discuss regarding a construction project. These points include issues like gas purification equipment location, electrical room design, cable trench plans, foundation beam plans, embedded parts depths, bolt sizes and loads, block masonry heights, air path room thinning, air path clarification, embedded part depths, cooling water routing, and baffle and foundation designs. It also provides a schedule for starting steel engineering and manufacturing, gas pipeline engineering, electrical substation work, pipe gallery engineering and installation, and embedded parts work within the next 2 months.
The document outlines 16 points to discuss regarding a construction project. These points include issues like gas purification equipment location, electrical room design, cable trench plans, foundation beam plans, embedded parts depths, bolt sizes and loads, block masonry heights, air path room thinning, air path clarification, embedded part depths, cooling water routing, and baffle and foundation designs. It also provides a schedule for starting steel engineering and manufacturing, gas pipeline engineering, electrical substation work, pipe gallery engineering and installation, and embedded parts work within the next 2 months.
The document outlines 16 points to discuss regarding a construction project. These points include issues like gas purification equipment location, electrical room design, cable trench plans, foundation beam plans, embedded parts depths, bolt sizes and loads, block masonry heights, air path room thinning, air path clarification, embedded part depths, cooling water routing, and baffle and foundation designs. It also provides a schedule for starting steel engineering and manufacturing, gas pipeline engineering, electrical substation work, pipe gallery engineering and installation, and embedded parts work within the next 2 months.
The document outlines 16 points to discuss regarding a construction project. These points include issues like gas purification equipment location, electrical room design, cable trench plans, foundation beam plans, embedded parts depths, bolt sizes and loads, block masonry heights, air path room thinning, air path clarification, embedded part depths, cooling water routing, and baffle and foundation designs. It also provides a schedule for starting steel engineering and manufacturing, gas pipeline engineering, electrical substation work, pipe gallery engineering and installation, and embedded parts work within the next 2 months.
1. Gas purification and bag house shifting to right side.
2. Low voltage room Missing 3. Cable trench construction Plan 4. Plinth beam plan 5. Embedded parts up to 4.8m 6. Size and type of bolts WRT to load given. 7. Block masonry (Up to Roof)?? 8. Thinning of PB of air path and Air path room. 9. Air path sections clarification 10. 4.8m Bottom embedded parts 11. 4.8m Top Embedded parts 12. Cooling water path from 4.8m floor 13. Front screen foundation 14. Baffle addition 15. Round Wheels Foundation 16. Small Ground wheel Foundation 17. C Cal ci um Car bi de1. 1. 3 钢结构工程 Steel work Engineering 174 21- Dec- 22 12- J un- 23 o 25 o 钢结构制作 Steel work Cal ci um Car bi de1. 1. 3. 1 85 21- Dec- 22 15- Mar - 23 li 26 manufacturing n g water lines under or over ground.
As per schedule following tasks can be started within next 2 Months.
1. Steel work Engineering from 21 December 2022 to 12 June 2023.
2. Steel work manufacturing from 21 December 2022 to 15 March 2023. 3. General gas pipeline Engineering 01 December 2022 to 30 December 2022. 4. General electrical utilities work a. 10KV substation project from 01 December 2022 to 19 April 2023. 5. Pipe gallery and bridge engineering from 01 December to 12 March 2023. a. Pipe gallery foundation engineering from 01 December 2022 to 30 December 2022. b. Pipe gallery production and installation works 01 December 2022 to 29 January 2023. c. Cable laying works 30 January 2023 to 12 March 2023. d. Clean furnace gas pipeline engineering 30 January 2023 to 28 February 2023.