Professional Documents
Culture Documents
Assessment of The Overall Equipment Effectiveness in A Sack Manufacturing Company in Kano, Nigeria
Assessment of The Overall Equipment Effectiveness in A Sack Manufacturing Company in Kano, Nigeria
Assessment of The Overall Equipment Effectiveness in A Sack Manufacturing Company in Kano, Nigeria
machines are only value adding machines, and so their OEEs (1) Shift Length: 11 h.
were not considered. (2) Breaks: 1.5 h.
As there were 3 nos. tapeline machines, 60 nos. loom (3) Total Units Processed (TUP), Rejected Units (RU) and
machines and 6 nos. cutting & sewing machines on the Good Units (GU) presented in Table 3.
production floor of the company, the following assumptions (4) Downtime (DT) presented in Table 4.
were made: (5) Ideal Run Rate (IRR) presented in Table 5.
(1) All the machines in the same category are of the same
make Table 3: Total units processed (TUP), rejected units (RU)
(2) All the machines in the same category have the same and good units (GU) for the machines
operating conditions Machine Category TUP RU 𝑮𝑼 = 𝑻𝑼𝑷 − 𝑹𝑼
(3) All the machines in the same category receive equal Tapeline Machine 2012 Kg 40 Kg 1972 Kg
treatments by their operators who have the same Loom Machine 704 m 20 m 684 m
training and skills Cutting and Sewing 12207 pcs 251 pcs 11956 pcs
(4) All the machines in the same category will require the
same OEE improvement measures
Table 4: Downtime for the machines
Given the above assumptions, only the OEE of one Machine Category DT (hours)
representative machine from each category was assessed. Data Tapeline Machine 0.33
were obtained by consulting the production manager, the Loom Machine 2.23
production engineer, the machine operating manual, and by Cutting and Sewing Machine 2.4
direct observation during the morning shift of 21st January
2020, at the time of production of a certain order received
from XCB Company. The order had the following Table 5: Ideal Run Rate for the machines
specifications: Machine Category IRR
Sack size: 70 x 110 cm Tapeline Machine 250 Kg/h
Lamination: none Loom Machine 120 metres/h
No. of sacks required: 150,000 Cutting and Sewing Machine 1800 pieces/h
The data obtained were:
(1) Shift Length
Having obtained the OEE data above, the following
(2) Breaks (time duration)
calculations were performed:
(3) Total Units Processed (TUP), Rejected Units (RU) and
1. Planned Production Time (PPT) calculated in
Good Units (GU) for each machine
accordance with Muhammad et al. (2012)
(4) Downtime for each machine during the examined
𝑃𝑃𝑇 = 𝑠ℎ𝑖𝑓𝑡 𝑙𝑒𝑛𝑡ℎ − 𝑏𝑟𝑒𝑎𝑘𝑠 (5)
period
𝑃𝑃𝑇 = 11 − 1.5 = 9.5ℎ𝑜𝑢𝑟𝑠
(5) Ideal run rate for each machine
2. Operating Time (OT) calculated in accordance with
The availability metric (Muhammad et al., 2012),
Muhammad et al. (2012) is presented in Table 6.
performance and quality metrics (Soniya et al., 2012), for
3. Availability (A) calculated according to equation (1) is
each machine were calculated according to the following
presented in Table 7.
equations:
𝑂𝑝𝑒𝑟𝑎𝑡𝑖𝑛𝑔 𝑡𝑖𝑚𝑒 4. Performance (P) calculated according to equation (2)
𝐴𝑣𝑎𝑖𝑙𝑎𝑏𝑖𝑙𝑖𝑡𝑦 (𝐴) = (1) is presented in Table 8.
𝑃𝑙𝑎𝑛𝑛𝑒𝑑 𝑝𝑟𝑜𝑑𝑢𝑐𝑡𝑖𝑜𝑛 𝑡𝑖𝑚𝑒
𝑇𝑜𝑡𝑎𝑙 𝑢𝑛𝑖𝑡𝑠 𝑝𝑟𝑜𝑑𝑢𝑐𝑒𝑑
⁄𝑜𝑝𝑒𝑟𝑎𝑡𝑖𝑛𝑔 𝑡𝑖𝑚𝑒 5. Quality (Q) calculated according equation (3) is
𝑃𝑒𝑟𝑓𝑜𝑟𝑚𝑎𝑛𝑐𝑒 (𝑃) = (2) presented in Table 9.
𝐼𝑑𝑒𝑎𝑙 𝑟𝑢𝑛 𝑟𝑎𝑡𝑒
𝐺𝑜𝑜𝑑 𝑢𝑛𝑖𝑡𝑠 6. Availability (A), Performance (P), Quality (Q) and
𝑄𝑢𝑎𝑙𝑖𝑡𝑦 (𝑄) = (3)
𝑇𝑜𝑡𝑎𝑙 𝑢𝑛𝑖𝑡𝑠 𝑝𝑟𝑜𝑐𝑒𝑠𝑠𝑒𝑑 Overall Equipment Effectiveness (OEE). OEE was
The OEE of each machine was determined according to the calculated according equation (4). These are presented
following equation (Davis, 1995): in Table 10.
𝑂𝐸𝐸 = 𝐴 × 𝑃 × 𝑄 (4)
The world class standard values of the Availability, Table 6: Operating time for the machines
Performance and Quality are presented in Table 2 Machine Category DT 𝑶𝑻 = 𝑷𝑷𝑻 − 𝑫𝑻
Tapeline Machine 0.33 9.17 h
Table 2: World class OEE standard metrics Loom Machine 2.23 h 7.27 h
OEE Metrics World Class Value Cutting and Sewing Machine 2.4 h 7.1 h
Availability 90%
Performance 95% Table 7: Availability for the machines
Quality 99%
Machine Category 𝑨 = 𝑶𝑻⁄𝑷𝑷𝑻
Source: (Smith & Hawkins, 2004)
Tapeline Machine 97%
Loom Machine 81%
For manufacturing industry, the World Class OEE Standard is Cutting and Sewing Machine 75%
85% (Smith & Hawkins, 2004). Thus, comparison was made
with the company calculated values. The losses hindering the Table 8: Performance for the machines
OEE were identified, and suggestions were made for 𝑻𝑼𝑷⁄
Machine Category 𝑷= 𝑶𝑻
improvement. 𝑰𝑹𝑹
Tapeline Machine 88%
Result and Discussion Loom Machine 81%
The following data were as provided by the production Cutting and Sewing Machine 96%
manager at XYZ Company and as observed by the authors,
with the necessary computations performed.
Table 9: Quality for the machines Fig. 1: Comparison of calculated OEEs and world class
𝑮𝑼 OEE standard
Machine Category 𝑸=
𝑻𝑼𝑷
Tapeline Machine 98%
Loom Machine 97% The tapeline machine
Cutting and Sewing Machine 98% As seen in Table 10 and Fig. 1, for the tapeline machine,
availabilty was 97%, performance was 88%, quality was 98%
and OEE was 84%. In comparison with the world class
Table 10: OEE and its metrics standard values, only the availability metric is satisfactory.
Availab Perfor. Qual. 𝑶𝑬𝑬 = The OEE is below world class standard. The below world
Machine category
(A) (P) (Q) 𝑨 × 𝑷 × 𝑸 class standard OEE value obtained is found in similar studies
Tapeline Machine 97% 88% 98% 84% conducted by Sayuti (2019), Disha et al. (2013), Muhammad
Loom Machine 81% 81% 97% 64% et al. (2012), and Khairun et al. (2012).
Cutting and Sewing Machine 75% 96% 98% 71% After careful observation, discussion and interview with the
maintenance staff, operators and management, factors
responsible for the OEE losses were discovered. The factors
were time losses and are shown in Table 11.
Loom machine
As seen in Table 10 and Fig. 1, for the loom machine,
availability was 81%, performance was 81%, quality was 97%
and OEE was 64%. In comparison with the world class
standard values, all the metrics are not satisfactory. The OEE
is much below the world class standard. The below world
class standard OEE value obtained is found in similar studies
conducted by Sayuti (2019), Disha et al. (2013), Muhammad
et al. (2012), and Khairun et al. (2012).
After careful observation, discussion and interview with the
maintenance staff, operators and management, factors
responsible for the OEE losses were discovered. The factors
were time losses and are shown in Table 12.
Cutting and sewing machine an insulation line in a cable manufacturing unit. Int. J.
As seen in Table 10 and Fig. 1, for the cutting and sewing Innovative Res. Sci. Engr. & Tech., 2: 1629-1634.
machine, availabilty was 75%, performance was 96%, quality Davis RK 1995. Productivity Improvement through TPM.
was 98%, and OEE was 71%. In comparison with the world Prentice Hall : London
class standard values, only the quality metric is satisfactory. Khairun N, Mohibul I, Mostafizur R & Mosharraf H 2012.
The OEE is below the world class standard. The below world Evaluation of OEE for implementing Total Productive
class standard OEE value obtained is found in similar studies Maintenance (TPM) in sewing machine of a knit factory.
conducted by Sayuti ( 2019), Disha et al. (2013), Muhammad Proc. Glo. Engr. Sci. & Tech. Conf., Dhaka, Bangladesh,
et al. (2012), and Khairun et al. (2012). 28-29 December 2012.
After careful observation, discussion and interview with the Muhammad AS Muhammed RH & Asrafuzzaman MD 2012.
maintenance staff, operators and management, factors Analysis of performance by overall equipment
responsible for the OEE losses were discovered. The factors effectiveness of the CNC cutting section of a shipyard.
were time losses and are shown in Table 13. ARPN J. Sci. & Tech., 2(11): 1091-1096.
Nakajima S 1988. Introduction to Total Productive
Conclusion Maintenance. Productivity Press, Cambridge, MA, pp. 1-
In this study, the Overall Equipment Effectiveness (OEE) of 129.
key machines on the production floor of XYZ Company was Peter M & Liliane P 2008. Performance measurement using
assessed. Thus, the OEEs of the tapeline machine, the loom overall equipment effectiveness (OEE): literature review
machine and the cutting and sewing machines were and practical application discussion. Int. J. Prod. Res.,
respectively evaluated to be 84%, 64% and 71%. Comparison DOI : 10.1080/00207540601142645
of these OEE values was made with the world class standard Smith R & Hawkins B 2004. Lean Maintenance: Reduce
value for manufacturing industries which stands at 85%. Costs, Improve Quality, and Increase Market
Therefore, all the OEEs evaluated for tapeline machine, the Share. Elsevier, Oxford, UK, pp. 55-56
loom machine, and cutting and sewing machine, are below the Soniya P, Sanjay J & Lokesh B 2012. Calculation of OEE for
world class standard values. For each of the three machines, an assembly process. Int. J. Res. in Mech. Engr. & Tech.,
reasons for the OEE losses were identified and suggestions 2(2): 25-29.
made in order to improve equipment effectiveness. Sayuti M 2019. Analysis of the overall equipment
effectiveness (OEE) to minimize Six Big Losses of
Conflict of Interest pulp machine: A case study in pulp and paper industries.
The authors declare that there is no conflict of interest related Int. Conf. Scie. & Innovative Engr. doi:10.1088/1757-
to this work. 899X/536/1/012061.
References
Disha MN, Vijaya KM N, Sreenivasulu NG & Veena S 2013.
Evaluation of OEE in a continuous process industry on