SERVICE BULLETIN #35

FRAMO MARINE CARGO PUMPING SYSTEM


Oil monitoring and inspection

Oil Monitoring and Inspection Program (OMP) includes:


Oil sampling – Oil analysis – Filter condition – Annual Inspection – Pre-Docking Inspection
Service Bulletin #35
Oil Monitoring and Inspection Program for Framo Cargo Pumping System

The Oil Monitoring and Annual Inspections and Pre- • Perform trend analysis of
Inspection Program Docking Inspections. The the different tests and send
has proven to be a cost program will be managed the Framo Oil Monitoring
effective condition based by one of the Framo service Report to ship and
maintenance system. stations and dedicated customer.
personnel will follow up each • Perform scheduled
By monitoring the condition ship.
of the cargo pumping system, inspection and highlight
this will give an improved recommended action /
lifetime of the components in We will: spare parts, if any.
the system. • Supply Framo sample • Available information
With the Oil Monitoring and bottle kit annually, with related to oil analysis,
Inspection Program (OMP), instruction for sampling performed inspections and
Framo offer assistance for and labels for shipping. consumption statistics,
cost control and optimal might be discussed
• Provide recommended during meetings with our
operation. sampling and attendance customer.
The Oil Monitoring and schedule.
Inspection Program
includes Oil Monitoring,

Framo test laboratory

2
The program comprise E-1064. Recommended Filter condition:
the following: limit is below 300 PPM. As we all know, the
The program includes a total Microscopic analysis will be cleanliness of the oil, as well
of 4-four oil samples annually, carried out if higher amount as the general oil condition, is
in which there are 3-three of particles are observed very important for the lifetime
Level 1 analysis and 1-one during automatic counting. of the Framo Cargo Pumping
Level 2 analysis. A separate Tailor made comments and System. In this respect, please
sampling valve is a standard recommendations will be keep in mind that:
installation by Framo. given in each Framo Oil • Our systems are equipped
Please study our Monitoring Report. with full flow filters,
recommended oil sampling securing that all circulated
procedure, 1400-0063-4, oil is filtrated.
Oil Monitoring - Level 2:
carefully prior oil sampling.
• 1-one full analysis will • Particle counting,
be done annually, and combined with pressure
Oil Monitoring - Level 1: will in addition to particle drop measurements
counting and water over the filter is the only
• Particle counting and water
content, comprise the safe indicator on when
content test, quarterly. The
following: to change the filter
oil sample will be analysed
element(s).
at a Framo test laboratory - Viscosity test at 40°C
and observed results • Framo is using a depth
reported according to ISO - Total acid number, filter, which means that
4406-1999 (TAN). these are not cleanable at
- Phosphor, ppm. (P) all.
- Number and size of
particles. Recommended - Zinc, ppm. (Zn) Please make sure that you use
limit is ISO -/16/12 only genuine Framo filters.
- Calcium, ppm. (Ca)
- Water content will be
reported according to
Karl Fisher ASTM

The Framo main filter is a so called depth filter. Glass fiber and metal are the materials used. Depth filters cannot be
cleaned and are regarded as disposeable elements.

3
Service Bulletin #35
Oil Monitoring and Inspection Program for Framo Cargo Pumping System

Annual Inspection: • Control of Framo toolbox


Framo will provide skilled incl. special tools and
engineers to attend your ship the pressure testing kit /
worldwide in order to perform manometer set.
a visual inspection on board • Inspection and evaluation
your vessel, together with of spare part inventory as
representatives from the vessels well as stock location.
crew. • Evaluation of planned
The inspection will comprise maintenance records.
the following: • Following the survey, a
• Visual inspection of detailed inspection report Genuine spare-parts
hydraulic power unit. including recommended
• If possible, perform a visual action / spare parts, will
inspection of manual wear be sent to the customer.
• Purge cofferdam on all
indicators. cargo pumps (depending
• Check for air in the system Pre-Docking Inspection: on type of cargo).
and de-aerate if necessary. Framo will provide skilled • If possible, test each
• Inspect the system for engineers to attend your hydraulic power pack.
leakages, abnormal noise ship worldwide in order to • If possible, test the
etc. evaluate the condition of the hydraulic control system,
• Visual inspection and entire Framo cargo pumping alarm and shutdown
evaluation of hydraulic deck system, prior to docking. functions.
piping and valves, including The Pre-Docking Inspection
is preferably carried • Visual inspection and
quick coupling stations for evaluation of hydraulic
the portable pump. out prior to a discharge
operation, if possible. The deck piping and valves,
• Visual inspection of cargo Pre-Docking Inspection can including coupling stations
pumps top plates, including also be replaced with an for the portable pump.
FCV / STC valves. On-board Training session. • Inspection and test of
• Evaluation of purging For that, a short voyage is portable pump, if possible.
routines of the cargo pumps recommended.
• If possible, test-run the
cofferdam. The inspection will comprise ballast pumps and tank
• Visual inspection of Framo the following: cleaning pumps.
portable pump with • If possible, test all cargo • Inspection of spare part
accessories. pumps against closed inventory and Framo
• Visual inspection of cargo valve in order to toolbox incl. special tools
standard pumps and other evaluate condition of the and the pressure testing kit
Framo delivered equipment. pumps and control valves / manometer set.
(depending port authority
and type of cargo).

4
• Following the survey, a Framo service station for
a detailed inspection further analysis. Shipping
report with repair costs will be at customer`s
recommendations, account. Our target is to
followed by our quotation collect 1-one oil sample
for recommended spare during the Annual / Pre-
parts, will be sent to the Docking Inspections.
customer. This will help • Contact us prior to
the ship’s superintendent attendance in ports
in preparing the docking where we are located,
activities on the Framo if your vessel is due for
system and at the same inspections. We will act
time keep the maintenance accordingly, as long as we
cost down. have available capacity.
• In the year when Pre- We are also able to attend
Docking Inspection is vessels in other ports.
carried out, it is not More info below.
deemed necessary to
also carry out an Annual
Inspection. Port attendance:
• Pre-Docking Inspection Please note that the costs of
can also be combined with inspection included in the Oil
On Board Training. Monitoring and Inspection
Program are based on the
You will get: inspection being carried out
in ports where Framo have an
• Secured optimal office (Rotterdam, Houston,
performance of your Singapore, Bergen, Shanghai,
Framo cargo pumping Busan, Tokyo, Rio de Janeiro -
system. City Harbor and Dubai area).
• Reduced maintenance
costs.
For attendance outside
• Increased lifetime of the Framo ports:
hydraulic components.
Tickets, hotel, subsistence
• Better possibility to plan allowance, travelling expenses
the maintenance and and driving pre-paid by us
to have an indication of will be charged at cost face
required spare parts. value.
• Documentation of the For traveling and waiting
system condition. time we will charge the actual
hours, limited to a maximum
amount pr. calendar day.
In order to secure smooth
cooperation from both
parties, your vessel (s) will For any further information
have to: regarding our services, please
• Collect 3-three oil samples do not hesitate to contact any
per year and send same to of the Framo service stations.

5
Service Bulletin #35
Oil Monitoring and Inspection Program for Framo Cargo Pumping System

_________________________________________________
_________________________________________________
_________________________________________________
_________________________________________________
_________________________________________________
_________________________________________________
_________________________________________________
_________________________________________________
_________________________________________________
_________________________________________________
_________________________________________________
_________________________________________________
_________________________________________________
_________________________________________________
_________________________________________________
_________________________________________________
_________________________________________________
_________________________________________________
_________________________________________________
_________________________________________________
_________________________________________________
_________________________________________________
_________________________________________________
6
_________________________________________________
_________________________________________________
_________________________________________________
_________________________________________________
_________________________________________________
_________________________________________________
_________________________________________________
_________________________________________________
_________________________________________________
_________________________________________________
_________________________________________________
_________________________________________________
_________________________________________________
_________________________________________________
_________________________________________________
_________________________________________________
_________________________________________________
_________________________________________________
_________________________________________________
_________________________________________________
_________________________________________________
_________________________________________________
_________________________________________________
7
FRAMO Services AS
P.O. Box 44 framo.com
NO-5329 Florvåg, Norway
Phone: + 47 55 99 92 00
service@framo.no

FRAMO AS FRAMO Brasil


P.O. Box 23, NO-5329 Florvåg, Av. Presidente Vargas, 463
Norway /19° andar, Rio de Janeiro CEP
Phone: + 47 55 99 90 00 20071-003, Brazil
Telefax: + 47 55 99 93 80 Phone: + 55 21 2507 7898
framobr@framobr.com.br
E-mail: marine@framo.no
FRAMO Middle East
FRAMO Nederland
Al Quoz Industrial Area
Edisonweg 18​
P.O. Box 21467
P.O. Box 305
Dubai, United Arab Emirates
NL-3200 AH Spijkenisse
Phone: +971 4 886 1313,
The Netherlands
dubai@framo.no
Phone: + 31 181 619311
nederland@framo.no
FRAMO Fusa AS
Venjaneset
FRAMO USA
NO-5641 Fusa, Norway
3002 East 13th Street
Phone: + 47 55 99 96 00
La Porte, Texas 77571, USA
marine@framo.no
Phone: + 1 281 884 4800
houston@framo.no
FRAMO Holsnøy AS
Rosslandsvegen 933
FRAMO Singapore
NO-5918 Frekhaug, Norway
17 Tuas View Circuit
Phone: + 47 55 99 75 00
Singapore 637575
piping.marine@framo.no
Republic of Singapore
Phone: + 65 6210 2400
FRAMO Flatøy AS
singapore@framo.no
Flatøyvegen 24
NO-5918 Frekhaug, Norway
FRAMO Japan
Phone: + 47 55 99 94 00
Kotsu Building 5F, 15-5
oil&gas@framo.no
Shinbashi, 5-chome
Minato-ku
Tokyo 105-0004, Japan Phone:
+ 81 3 5776 2405
tokyo@framo.no

FRAMO Korea
Rm 608, Centum Sh Valley
35, Centum Dong – Ro
Haeundae – Gu, Busan
Korea, 612-020
Phone: + 82 51 743 6942/3
busan@framo.no

FRAMO Shanghai
Building No.5, 123
Lane 1165, Jin Du Road
Min Hang District, Shanghai
China 201108
Phone: + 86 21 6115 5000
shanghai@framo.no