Measurment as per DPR Estimate 129+275 MNBR Measurment as per Revised Drawing 129+275 MNBR

Excess/
Breadth Breadth
Sl. No. Description Unit No. Length (m) Depth (m) Quantity Description Unit No. Length (m) Depth (m) Quantity Saving
(m) (m)
Qty.

Clearing and grubbing at site which includes Clearing and grubbing at site which includes
cleaning and removal of vegetation growth from cleaning and removal of vegetation growth from 1 75.000 26.000
1.01 Sqm 1 69.56 26.00 1808.56 Sqm 1950.00 141.44
structures, channel and protective works as per structures, channel and protective works as per
direction of Engineer as per Tech.Spec. Cl. 201 direction of Engineer as per Tech.Spec. Cl. 201

Dismantle existing cross drainage structure Dismantle existing cross drainage structure
Including disposal of resulting material and salvage Including disposal of resulting material and salvage
1.02 Cu.m. Cu.m.
reusable materials complete as per Tech.Spec.Cl. reusable materials complete as per Tech.Spec.Cl.
202 202
a) Brick / Stone/RCC structure 564.91 a) Brick / Stone/RCC structure 564.91 0.00
RCC Abutment 2 8.20 5.80 1.20 114.14 RCC Abutment 2 8.20 5.80 1.20 114.14
RCC Pier 6 8.20 5.80 1.20 342.43 RCC Pier 6 8.20 5.80 1.20 342.43
Returnwall 4 4.79 5.80 0.60 66.65 Returnwall 4 4.79 5.80 0.60 66.65
Returnwall (in between spans) 0 7.00 1.70 4.00 0.00 Returnwall (in between spans) 0 7.00 1.70 4.00 0.00
Parapet 2 57.90 0.60 0.60 41.69 Parapet 2 57.90 0.60 0.60 41.69

b) PCC in Substructure Cu.m. 119.65 b) PCC in Substructure Cu.m. 119.65


Abutment 2 8.50 6.10 0.15 15.56 Abutment 2 8.50 6.10 0.15 15.56
Pier 6 8.50 6.10 0.15 46.67 Pier 6 8.50 6.10 0.15 46.67
Returnwall 4 5.09 6.10 0.15 18.62 Returnwall 4 5.09 6.10 0.15 18.62
Arch 0 7.50 12.00 0.70 0.00 Arch 0 7.50 12.00 0.70 0.00
Parapet 2 53.90 0.60 0.60 38.81 Parapet 2 53.90 0.60 0.60 38.81

c) RCC in Superstructure Cu.m. 370.80 c) RCC in Superstructure Cu.m. 370.80 0.00


Girders 0 8.20 7.70 1.10 0.00 Girders 0 8.20 7.70 1.10 0.00
Slab 7 8.20 7.70 0.80 353.58 Slab 7 8.20 7.70 0.80 353.58
Approach slab 2 8.20 3.50 0.30 17.22 Approach slab 2 8.20 3.50 0.30 17.22
Railings 0 63.14 0.50 1.20 0.00 Railings 0 63.14 0.50 1.20 0.00

d) Stone Slabs in super structure Sq.m 0 7.50 2.00 0.00 d) Stone Slabs in super structure Sq.m 0 7.50 2.00 0.00
e) Steel I beams MT 0 7.00 0.04 0.50 0.00 e) Steel I beams MT 0 7.00 0.04 0.50 0.00
f) HP ( > 300 dia) m 0 10.00 0.00 f) HP ( > 300 dia) m 0 10.00 0.00
g) Wearing coat sqm 1 63.14 7.20 454.61 g) Wearing coat sqm 1 63.14 7.20 454.61 0.00

Earthwork in excavation of foundation for structures Earthwork in excavation of foundation for structures
1.03 in all types of soil including lead and lifts complete Cu.m. 1182.61 in all types of soil including lead and lifts complete Cu.m. 3281.33 2098.7
as per Tech. Spec. Cl. 304 as per Tech. Spec. Cl. 304
a) ordinary soil a) ordinary soil
Abutment AL 1 19.92 8.53 1.50 254.69 Abutment (A1) RL (186.772-12=174.772) 1 17.100 8.300 2.000 283.860
Abutment AR 1 19.92 8.53 1.50 254.69 Pier (P1) RL (183.221-10=173.221) 1 8.300 5.300 2.000 87.980
Pier - 1 1 15.86 7.21 1.50 171.43 Pier (P2) RL (183.986-10=173.986) 1 8.300 5.300 2.000 87.980
Pier - 2 1 15.86 7.21 1.50 171.43 Abutment (A2) RL (186.772-12=174.772) 1 17.100 8.300 2.000 283.860
Pier - 3 0 15.86 7.21 0.00 0.00 RetainingWall A1 side 2 50.000 5.800 2.000 1160.000
Independent Returnwall on AL side 2 10.60 4.32 1.00 91.48 RetainingWall A2 side 2 50.000 5.800 2.000 1160.000
Independent Returnwall on AR side 2 10.60 3.58 1.00 75.90 Toe wall A1 side 2 17.75 1.70 1.90 114.64
Toe wall on side slopes AL 2 12.98 2.10 1.65 89.98 Toe wall A2 side 2 15.95 1.70 1.90 103.01
AR Side 2 10.53 2.10 1.65 73.00

b) in soft/weathered rock 1213.65 b) in soft/weathered rock 140.20 -1073.5


AL 1 19.92 8.53 1.65 280.16 Abutment (A1) 15 3.142x0.5x0.5x4.25=3.338 50.070
AR 1 19.92 8.53 1.65 280.16 Pier (P1) 6 3.142x0.5x0.5x4.25=3.338 20.028
Pier - 1 1 15.86 7.21 1.65 188.57 Pier (P2) 6 3.142x0.5x0.5x4.25=3.338 20.028
Pier - 2 1 15.86 7.21 1.65 188.57 Abutment (A2) 15 3.142x0.5x0.5x4.25=3.338 50.070
Pier - 3 0 15.86 7.21 0.00 0.00
Independent Returnwall on AL side 2 10.60 4.32 1.65 150.95
Independent Returnwall on AR side 2 10.60 3.58 1.65 125.24

c) in Hard Rock 0.00 c) in Hard Rock 140.20


Abutment - A1 1 19.92 8.53 0.00 0.00 Abutment (A1) 15 3.142x0.5x0.5x4.25=3.338 50.070
Abutment - A2 1 19.92 8.53 0.00 0.00 Pier (P1) 6 3.142x0.5x0.5x4.25=3.338 20.028
Pier - 1 1 15.86 7.21 0.00 0.00 Pier (P2) 6 3.142x0.5x0.5x4.25=3.338 20.028
Pier - 2 1 15.86 7.21 0.00 0.00 Abutment (A2) 15 3.142x0.5x0.5x4.25=3.338 50.070

1
Excess/
Breadth Breadth
Sl. No. Description Unit No. Length (m) Depth (m) Quantity Description Unit No. Length (m) Depth (m) Quantity Saving
(m) (m)
Qty.
Pier - 3 0 15.86 7.21 0.00 0.00

Back filling behind abutments, wing walls, return Back filling behind abutments, wing walls, return
walls and foundation trenches with selected granular walls and foundation trenches with selected granular
1.04 material of approved quality complete with all leads Cu.m. 1198.00 material of approved quality complete with all leads Cu.m. 1071.94 -126.1
as per Tech. Spec. Cl.710.1.4 of IRC:78and lifts as per Tech. Spec. Cl.710.1.4 of IRC:78and lifts
complete complete
Abutment - AL 1 19.92 0.60 1.20 14.34 Behind return wall (A1) 2 2.350 3.859 7.717 139.947
Abutment - AR 1 19.92 0.60 1.20 14.34 Behind return wall (A2) 2 2.350 3.859 7.717 139.947
Pier - 1 1 15.86 0.60 1.00 9.52 Behind abutment A1 1 13.300 3.859 7.717 396.021
Pier - 2 1 15.86 0.60 1.00 9.52 Behind abutment A2 1 13.300 3.859 7.717 396.021
Pier - 3 0 15.86 0.60 1.00 0.00 0.00
Independent Returnwall on AL side 2 10.60 0.60 0.80 10.18 0.00
Independent Returnwall on AR side 2 10.60 0.60 0.80 10.18 0.00
Abutment - AL 1 19.92 7.21 1.95 279.84 0.00
Abutment - AR 1 19.92 7.21 1.95 279.84 0.00
Pier - 1 1 15.86 6.11 2.15 208.20 0.00
Pier - 2 1 15.86 6.11 2.15 208.20 0.00
Pier - 3 0 15.86 6.11 -1.00 0.00 0.00
Pier - 1 1 2.00 1.10 2.15 4.73 0.00
Pier - 2 1 2.00 1.10 2.15 4.73 0.00
Pier - 3 0 2.00 6.11 -1.00 0.00 0.00
Independent Returnwall on AL side 2 10.60 3.72 0.20 15.75 0.00
Independent Returnwall on AR side 2 10.60 3.72 0.20 15.75 0.00
Toe wall AL side 2 12.98 0.60 0.30 4.67 0.00
2 12.98 1.85 1.20 57.65 0.00
AR side 2 10.53 0.60 0.30 3.79 0.00
2 10.53 1.85 1.20 46.77 0.00

Cement Concrete/Reinforced Cement Concrete in Cement Concrete/Reinforced Cement Concrete in


open foundation / leveling course including open foundation / leveling course including
1.05 centering and shuttering but excluding Cu.m. centering and shuttering but excluding Cu.m.
reinforcement all complete as per Tech. Spec.Cl. reinforcement all complete as per Tech. Spec.Cl.
1500, 1700 & 2100 1500, 1700 & 2100
a) M15 Grade - Levelling Course 115.56 a) M15 Grade - Levelling Course 216.70 101.1
Abutment - AL 1 19.62 8.23 0.15 24.20 RL (186.222- 1 16.300 7.600 0.150 18.582
Pile cap levelling course A1
Abutment - AR 1 19.62 8.23 0.15 24.20 1.65=184.572) -15 3.142x0.5x0.5=0.7855 0.150 -1.767
Pier - 1 1 15.56 6.91 0.15 16.12 RL (182.721- 1 7.600 4.600 0.150 5.244
Pile cap levelling course P1
Pier - 2 1 15.56 6.91 0.15 16.12 1.65=181.071) -6 3.142x0.5x0.5=0.7855 0.150 -0.707
Pier - 3 0 15.56 6.91 0.15 0.00 RL (183.446- 1 7.600 4.600 0.150 5.244
Pile cap levelling course P2 1.65=181.796)
Independent Returnwall on A1 side 2 10.30 4.02 0.15 12.41 -6 3.142x0.5x0.5=0.7855 0.150 -0.707
Independent Returnwall on A2 side 2 10.30 3.28 0.15 10.14 RL (186.019- 1 16.300 7.600 0.150 18.582
Pile cap levelling course A2
Toe wall 2 12.68 1.80 0.15 6.85 1.65=184.369) -15 3.142x0.5x0.5=0.7855 0.150 -1.767
2 10.23 1.80 0.15 5.53 A1 Side levelling course 2 50.000 5.800 0.150 87.000
A2 Side levelling course 2 50.000 5.800 0.150 87.000
c) M15 Grade - Below Approach Slab c) M15 Grade - Below Approach Slab
Below Approach slab 2 16.00 3.65 0.15 17.52 Below Approach slab 2 16.30 5.00 0.15 24.45 6.9

Cement concrete grade M20 in sub-structures and Cement concrete grade M20 in sub-structures and
1.06 40.71 40.71 0.0
Foundation as per Tech. Spec. Cl. 1700. Foundation as per Tech. Spec. Cl. 1700.
Toe wall Toe wall
AL AL
Base Slab 2 12.38 1.50 0.30 11.15 Base Slab 2 12.38 1.50 0.30 11.15
Stem wall 2 12.38 0.25 1.80 11.15 Stem wall 2 12.38 0.25 1.80 11.15
AR AR
Base Slab 2 10.23 1.50 0.30 9.21 Base Slab 2 10.23 1.50 0.30 9.21
Stem wall 2 10.23 0.25 1.80 9.21 Stem wall 2 10.23 0.25 1.80 9.21

Cement concrete grade M30 in sub-structures and Cement concrete grade M30 in sub-structures and
1.07 Cu.m. 33.60 Cu.m. 1180.49 1146.9
Foundation as per Tech. Spec. Cl. 1700. Foundation as per Tech. Spec. Cl. 1700.
Approach Slab Approach Slab
2 16.00 3.50 0.30 33.60 2 16.00 5.00 0.30 48.00
2 50.000 4.800 0.300 144.000
2 50.000 1/2x0.2x1.6=0.16 16.000
Raft
Retaining Wall A1 Side
2
Excess/
Breadth Breadth
Sl. No. Description Unit No. Length (m) Depth (m) Quantity Description Unit No. Length (m) Depth (m) Quantity Saving
(m) (m)
Raft Qty.
2 50.000 0.800 0.200 16.000
Retaining Wall A1 Side
2 50.000 1/2x2.4x0.2=0.24 24.000
2 50.000 1/2x6.5x0.5=1.625 162.500
Wall
2 50.000 0.300 6.500 195.000
2 50.000 4.800 0.300 144.000
2 50.000 1/2x0.2x1.6=0.16 16.000
Raft
2 50.000 0.800 0.200 16.000
Retaining Wall A2 Side
2 50.000 1/2x2.4x0.2=0.24 24.000
2 50.000 1/2x6.5x0.5=1.625 162.500
Wall
2 50.000 0.300 6.500 195.000
Pedestrian Kerb 2 58.300 0.500 0.300 17.490

Cement concrete grade M35 in Foundations as per Cement concrete grade M35 in Foundations as per
1.08 Cu.m. 676.16 Cu.m. 377.04 -299.1
Tech. Spec. Cl. 1700. Tech. Spec. Cl. 1700.

Independent Returnwall on AL side (Foundation) 2 10.00 3.72 0.80 59.44 A1 pile group 15 3.142x0.5x0.5=0.7855 12.000 141.390
Independent Returnwall on AR side (Foundation) 2 10.00 2.98 0.80 47.68 P1 Pile group 6 3.142x0.5x0.5=0.7855 10.000 47.130
Abutment base - AL 1 19.32 7.93 1.20 183.71 P2 Pile group 6 3.142x0.5x0.5=0.7855 10.000 47.130
Abutment base - AR 1 19.32 7.93 1.20 183.71 A2 pile group 15 3.142x0.5x0.5=0.7855 12.000 141.390
Foundation 1 15.26 6.61 1.00 100.81 0.00
Foundation 1 15.26 6.61 1.00 100.81 0.00
Foundation 0 15.26 6.61 1.00 0.00 0.00

Cement concrete grade M35 in sub-structuresas per Cement concrete grade M35 in sub-structuresas per
1.09 Cu.m. 539.37 Cu.m. 1181.65 642.3
Tech. Spec. Cl. 1700. Tech. Spec. Cl. 1700.
Return wall
Independent Returnwall on AL side wall 2 10.00 0.50 5.39 53.92 A1 pile cap RL (186.222-184.572) 1 16.100 7.300 1.500 176.295
2 10.00 0.20 5.39 10.78 P1 Pile cap RL (182.721-181.071) 1 7.300 4.300 1.500 47.085
Independent Returnwall on AR side 2 10.00 0.50 4.17 41.67 P2 Pile cap RL (183.446-181.796) 1 7.300 4.300 1.500 47.085
2 10.00 0.20 4.17 8.33 A2 pile cap RL (186.019-184.369) 1 16.100 7.300 1.500 176.295
Abutments
Abutment - AL (Shaft) 1 19.32 0.75 1.48 21.40 A1 shaft 1 16.000 1.400 8.197 183.613
Hunch RL (195.019- 2 1/2x0.45x0.45=0.10125 10.968 2.221
1 19.32 0.57 1.48 8.13 1.4=186.222)
2 4.41 0.88 1.48 11.46 Return Wall 2 2.950 0.750 10.968 48.533
Abutment Cap AL 1 19.32 0.75 0.60 8.69 1 4.9 1.1 10.898 58.740
P1 shaft RL (193.619-182.721)
Triangle portion 2 19.32 0.45 0.60 5.22 1 3.142x0.55x0.55=0.951 10.898 10.364
1 19.32 1.70 0.90 29.55 1 4.9 1.1 10.173 54.832
P2 shaft RL (193.619-183.446)
Dirt wall 1 19.32 0.30 1.95 11.30 1 3.142x0.55x0.55=0.951 10.173 9.675
Projection 1 19.32 0.30 0.30 1.74 A2 shaft 1 16.000 1.400 8.40 188.160
Triangle portion 1 19.32 0.30 0.30 0.87 Hunch RL (194.419-186.019) 2 1/2x0.45x0.45=0.10125 8.40 1.701
Abutment - AR (Shaft) 1 19.32 0.75 0.25 3.65 Return Wall 2 2.950 0.750 11.17 49.432
1 19.32 0.57 0.25 1.39 0.00
2 4.41 0.88 0.25 1.96 A1 cap 1 13.700 1.400 0.600 11.508
RL (187.896-188.496)
Abutment Cap AR 1 19.32 0.75 0.60 8.69 A1 Return Wall 2 1.350 0.500 0.600 0.810
Triangle portion 2 19.32 0.45 0.60 5.22 1 13.700 2.100 0.700 20.139
1 19.32 1.70 0.90 29.55 P1 cap RL (187.141-188.541) 2 1/2x(3.15+0.55)x0.7=1.295 2.100 5.439
Dirt wall 1 19.32 0.30 1.95 11.30 1 6.300 2.100 0.700 9.261
Projection 1 19.32 0.30 0.30 1.74 1 13.700 2.100 0.700 20.139
Triangle portion 1 19.32 0.30 0.30 0.87 P2 cap RL(187.188-188.588 2 1/2x(3.15+0.55)x0.7=1.295 2.100 5.439
Piers 1 6.300 2.100 0.700 9.261
Pier-1 A2 cap 1 13.700 1.400 0.600 11.508
RL (188.032-188.632)
1 13.26 1.10 5.23 76.24 A2 Return Wall 2 1.350 0.500 0.600 0.810
Top cap 1 13.26 2.80 0.50 18.57 0.00
1 17.68 2.80 0.70 34.66 Dirt Wall 1 16.000 0.300 1.871 8.981
1 4.42 2.80 0.50 3.09 1 16.000 0.600 0.300 2.880
1 16.000 0.300
1/2x0.3x 0.300 1.440
Pier-2 1 16.000 0.3=0.04 0.720
1 13.26 1.10 5.01 73.07 Return Wall 2 1.350 5
0.500 1.571 2.121
1/2x0.3x
Top cap 1 13.26 2.80 0.50 18.57 -2 0.300 0.3=0.04 -0.027
1 17.68 2.80 0.70 34.66 2 0.750 5
0.500 0.300 0.225

3
Excess/
Breadth Breadth
Sl. No. Description Unit No. Length (m) Depth (m) Quantity Description Unit No. Length (m) Depth (m) Quantity Saving
(m) (m)
Qty.
1 4.42 2.80 0.50 3.09 2 1.050 0.500 0.300 0.315
Dirt Wall 1 16.000 0.300 1.871 8.981
Pier-3 1 16.000 0.600 0.300 2.880
0 13.26 1.10 -3.02 0.00 1 16.000 0.300
1/2x0.3x 0.300 1.440
Top cap 0 17.26 2.80 0.50 0.00 1 16.000 0.3=0.04 0.720
0 17.26 2.80 0.50 0.00 2 1.350 5
0.500 1.571 2.121
-2 0.300 1/2x0.3x0.3=0.045 -0.027
Return Wall
2 0.750 0.500 0.300 0.225
2 1.050 0.500 0.300 0.315

Cement concrete grade M40 in super structures as Cement concrete grade M40 in super structures as
1.10 Cu.m. 484.74 Cu.m. 441.64 -43.1
per Tech. Spec. Cl. 1700. per Tech. Spec. Cl. 1700.
Pedestrals Pedestrals
42 0.80 0.80 0.25 6.72 A1 Pedestal 5 0.800 0.800 0.363 1.162
P1 pedestal 10 0.800 0.800 0.363 2.323
Diaphgram 6 19.32 0.40 0.95 44.04 P2 pedestal 10 0.800 0.800 0.363 2.323
RC Deck slab 3 17.65 16.52 0.20 174.95 A2 pedestal 5 0.800 0.800 0.363 1.162

b) in RC Girder RCC Girder


End Block 21 4.00 Area = 0.87 73.08 2 2.28 0.625 1.2 3.420
Tapering 21 2.40 Area = 0.78 39.31 2 1.2 0.4575 0.65 0.714
Mid Section 21 10.12 Area = 0.69 146.64 1 7.68 0.29 0.65 1.448
1 14.64 0.59 0.15 1.296
1 14.64 0.625 0.25 2.288
1 14.64 0.4575 0.15 1.005
For 1 girder 10.17
For 15 girder 10.17 x 15 152.54
Diaphgram 6 13.225 0.4 1.2 38.088
Cross Girder 3 13.225 0.3 0.95 11.307
Deck slab 3 15.000 16.000 0.295 212.400

Providing, cutting, bending and fixing in position of Providing, cutting, bending and fixing in position of
TMT bar reinforcement in reinforced cement TMT bar reinforcement in reinforced cement
1.11 T 189.06 T 307.12 118.1
concrete structures complete as per Tech. Spec. Cl concrete structures complete as per Tech. Spec. Cl
1600 1600
Toe wall 1 wt = 2.85 2.85
Abutment & Dirt wall 1 wt = 16.27 16.27 ABUTMENT 1 & 2 PILE 59.56
Piers 1 wt = 26.19 26.19 ABUTMENT 1 & 2 PILE CAP WITH PIER 74.01
Return Wall 1 wt = 10.32 10.32 ABUTMENT CAP 1 & 2 5.27
RC Girder 1 wt = 38.85 38.85 ABUTMENT 1 & 2 RETURN WALL 42.29
RC slab 1 wt = 20.99 20.99 PIER PILE 9.08
pedestals 1 wt = 0.67 0.67 PILE CAP 1&2 WITH PIER 23.43
Diapharam 1 wt = 5.28 5.28 PIER CAP 9.11
Foundations 1 wt = 67.62 67.62 GIRDER 1 TO 2 SPAN-2 36.32
DECK SLAB SPAN 1 TO 2 27.601
MISCELLANEOS ITEM 18.628
DIPHARM 1.815

Filter media with stone crushed aggregates Filter media with stone crushed aggregates
1.12 abutments/return walls as per clause 2504.2.2 and Cu.m. 95.16 abutments/return walls as per clause 2504.2.2 and Cu.m. 410.52 315.4
Tech. Spec. Cl.710.1.4 of IRC:78 Tech. Spec. Cl.710.1.4 of IRC:78
(3.142x5.892x7.081)/
Behind Abutment - AL 1 16.00 0.60 2.68 25.70 A1 end (both corner) (Below boulder) 2 4=32.772 0.150 9.832
(3.142x3.9975x4.804)/
Behind Abutment - AR 1 16.00 0.60 1.45 13.94 A2 end (both corner) (Below boulder) 2 4=15.085 0.150 4.526
Independent Returnwall on AL side 2 10.00 0.60 2.68 32.12 A1 Return Wall Cu.m. 2 2.35 0.60 10.23 28.835
Independent Returnwall on AR side 2 9.70 0.60 1.45 16.90 A2 Return Wall Cu.m. 2 2.35 0.60 9.08 25.600
Below pitching 4 21.64 0.15 6.49 A1 Abutment Cu.m. 1 14.50 0.60 10.23 88.957
A2 Abutment Cu.m. 1 14.50 0.60 9.08 78.979
A1 Approach Cu.m. 1 30.00 0.15 20.46 92.070
A2 Approach Cu.m. 1 30.00 0.15 18.16 81.720

4
Excess/
Breadth Breadth
Sl. No. Description Unit No. Length (m) Depth (m) Quantity Description Unit No. Length (m) Depth (m) Quantity Saving
(m) (m)
Qty.

Providing weep holes in abutments, returnwalls, Providing weep holes in abutments, returnwalls,
1.13 with 100mm dia AC pipes complete as per drawing no's 150.00 with 100mm dia AC pipes complete as per drawing no's 418.00 268.0
and Tech. Spec. Cl. 2706 and Tech. Spec. Cl. 2706
Abutment - AL 1 16.00 2.68 1.00 43.00 Abutment - A1 1 16.00 10.00 160.00
Abutment - AR 1 16.00 1.45 1.00 24.00 Abutment - A2 1 16.00 9.00 144.00
Independent Returnwall on AL side 2 10.00 2.68 1.00 54.00 A1 Return Wall 2 3.00 10.00 60.00
Independent Returnwall on AR side 2 9.70 1.45 1.00 29.00 A2 Return Wall 2 3.00 9.00 54.00

1.14 Providing and fixing Expansion joint Providing and fixing Expansion joint
Bitumin Plug joint Rmtr 2 17.65 35.31 Bitumin Plug joint Rmtr 2 17.65 35.31 0.0
Strip seal expansion joint Rmtr 4 17.65 70.62 Strip seal expansion joint Rmtr 6 17.65 105.92 35.3

Providing and fixing Tar paper bearing complete as Providing and fixing Tar paper bearing complete as
1.15 10.59 10.59 0.0
per drawing and IRC:SP:13-1973. per drawing and IRC:SP:13-1973.
in Approach slab Sq.m 2 17.65 0.30 10.59 in Approach slab Sq.m 2 17.65 0.30 10.59

Supply, fitting and fixing in position true to line and Supply, fitting and fixing in position true to line and
1.16 level POT-PTFE Bearings complete as per Tech. 42 level POT-PTFE Bearings complete as per Tech. 30.000 -12.0
Spec. Cl. 2000 Spec. Cl. 2000
Pot-PTFE Bearing - 200 MT No's 3 3 Pot-PTFE Bearing - 161.5 MT No's 0.000
Guided Pot-PTFE Bearing - 200 MT No's 36 36 Free bearing 12 12
Free Pot-PTFE Bearing - 200 MT No's 3 3 Long guide bearing 8 8
Transverse bearing 6 6
Fixed Pot Bearing - 250 MT No's 0 0 Fix bearing 4 4
Guided Pot-PTFE Bearing - 250 MT No's 0 0 0
Free Pot-PTFE Bearing - 250 MT No's 0 0 0

Fixed Pot Bearing - 300 MT No's 0 0 0


Guided Pot-PTFE Bearing - 300 MT No's 0 0 0
Free Pot-PTFE Bearing - 300 MT No's 0 0 0

Fixed Pot Bearing - 350 MT No's 0 0 0


Guided Pot-PTFE Bearing - 350 MT No's 0 0 0
Free Pot-PTFE Bearing - 350 MT No's 0 0 0

Proving and fixing Drainage spouts complete as per Proving and fixing Drainage spouts complete as per
1.17 Each 22 22.00 Each 22 22.00 0.0
Tech. Spec. Cl. 2705 Tech. Spec. Cl. 2705

Providing and filling joint sealing compound as per Providing and filling joint sealing compound as per
drawings with coarse sand and 6 percent bitumen by drawings with coarse sand and 6 percent bitumen by
weight (0.083 kg/m bitumen) including cost and weight (0.083 kg/m bitumen) including cost and
1.18 Rmtr 4 17.65 70.62 Rmtr 4 17.65 70.62 0.0
conveyance of all materials, labour, fixing in conveyance of all materials, labour, fixing in
position, etc., complete as per drawing and Tech. position, etc., complete as per drawing and Tech.
Spec. Cl Spec. Cl

Providing and laying wearing course on top of deck Providing and laying wearing course on top of deck
1.19 complete as per Tech.Spec.Cl.515 & 2702 65mm Sq.m 1 56.56 12.14 686.48 complete as per Tech.Spec.Cl.515 & 2702 65mm Sq.m 1 56.56 12.14 686.48 0.0
Thick (40BC+ 25 Asphaltic) Thick (40BC+ 25 Asphaltic)

Construction of Crash Barrier M40 grade incl. cost Construction of Crash Barrier M40 grade incl. cost
1.20 of all materials, labour, lead, lifts, loading, Rmtr 117.12 of all materials, labour, lead, lifts, loading, Rmtr 117.12 0.0
unloading etc., complete unloading etc., complete
Inner 0 58.56 0.00 Inner 0.00
Outer 2 58.56 117.12 Outer 2 58.56 117.12 0.0

1.21 PVC Utility pipes (150 dia) Rmtr 2 58.56 117.12 PVC Utility pipes (150 dia) Rmtr 2 58.56 117.12 0.0

5
Excess/
Breadth Breadth
Sl. No. Description Unit No. Length (m) Depth (m) Quantity Description Unit No. Length (m) Depth (m) Quantity Saving
(m) (m)
Qty.
Providing and applying 2 coats of Enamel paint to Providing and applying 2 coats of Enamel paint to
1.22 plastered concrete surface complete as per Sq.m 1 117.12 0.29 33.85 plastered concrete surface complete as per Sq.m 1 117.12 0.29 33.85 0.0
Tech.Spec Cl. 800 for RC Crash barrier Tech.Spec Cl. 800 for RC Crash barrier

Painting details of Structure and span arrangements Painting details of Structure and span arrangements
1.23 No's 4 4.00 No's 4 4.00 0.0
as Tech.Spec.Cl. 800 as Tech.Spec.Cl. 800

Provide and lay stone pitching as per Tech. Spec. Provide and lay stone pitching as per Tech. Spec.
1.24 Cu.m. 25.97 Cu.m. 410.40 384.4
Cl. 2504. Cl. 2504.
A1 end (both corner) (3.142x5.892x7.081)/
for quandrantal pitching 4 Area= 21.64 0.30 25.97 for quandrantal pitching (Below 2 0.300 19.663
A2 end boulder)
(both corner) 4=32.772
(3.142x3.9975x4.804)/
(Below boulder) 2 4=15.085 0.300 9.051
Sides A1 Approach 2 30.00 11.18 0.30 201.17
Sides A2 Approach 2 30.00 10.03 0.30 180.52

1.25 metallic crash barrier m15 garde Cum 40.00 metallic crash barrier m15 garde Cum 40.00 0.0

2 10.00 20.00 2 10.00 20.00


2 10.00 20.00 2 10.00 20.00

1.26 Railing Rmtr Railing Rmtr


2 58.56 117.12 2 58.56 117.12 0.0

Painting of concrete hand rails/ parapets/ crash Painting of concrete hand rails/ parapets/ crash
barriers with two coats of enamel paint as per barriers with two coats of enamel paint as per
1.27 Sq.m 45.68 Sq.m 45.68 0.0
Technical Specification and the directions of the Technical Specification and the directions of the
Engineer Engineer

1 117.12 0.39 45.68 1 117.12 0.39 45.68

Paininting of sub structures & super structures Paininting of sub structures & super structures
1.28 with two coats of enamel paint as per Technical Sq.m 909.40 with two coats of enamel paint as per Technical Sq.m 1623.30 713.9
Specification and the directions of the Engineer Specification and the directions of the Engineer

sub structures 1 424.66 424.66 sub structures 1 1181.65 1181.65


Super structures 1 484.74 484.74 Super structures 1 441.64 441.64
ChippinganddressingoftheR.C.C.pilesupto0.60meter
includingcleaningreinforcementandremovalofdisman
tledmaterialsuptoadistanceof50meterbeyondthebuild Nos 42.00 42.00
ingareaetc.for providing pile caps.Spec :(As directed
by Engineer in Charge
Pile in A1 15 15.00
Pile in A2 15 15.00
Pile in P1 6 6.00
Pile in P2 6 6.00

Emptyboringfor725to1050mmdia.boredR.C.C.castin
situpilesincludingwithdrawalofshell, removal of earth
420.00 420.00
to a distance of 50 metres etc. complete.Spec :(As
directed by Engineer in Charge)
Pile in A1 15 10 150.00
Pile in A2 15 10 150.00
Pile in P1 6 10 60.00
Pile in P2 6 10 60.00
3.00 3.00
Pile load test Nos 3 3.00

Mt 65.08 65.08
6mm thick MS Liner Mt 42 9.50 3.14 Wt.=0.0472mt 58.88
12mm thick MS Cutting edge Mt 42 0.50 3.14 Wt.=0.094mt 6.20

6
UPGRADATION OF GADCHIROLI-ASTHI ROAD TO TWO LANE WITH PAVED SHOULDERS/FOUR LANE CONFIGRATION ( PACKAGED NO- NH/IAHE/02) IN THE STATE OF MAHARASTRA ON ENGINEERING, PROCURMENT & CONSTRUCTION (EPC)
BASIS CONTRACT DESIGN CHAINAGE - CH. 123+100 TO CH. 151+020

Change of Scope Abstruct


Minor Bridge 129+275
ANNEXURE-IV

Derived Rate, with ADD


Quantity as per Quantity as per SSR Item 2019-
Sl. No. Description Unit Excess Qty. Rate Area Weightage of GST(IGST+SGST Amount Remarks
DPR Revision 20
30% (Rs) ) @ 12%

Clearing and grubbing at site which includes


cleaning and removal of vegetation growth
1.01 from structures, channel and protective works Sqm. 1808.56 1950.00 141.44 2.09 9 11.70 13.10 1,854.00
as per direction of Engineer as per Tech.Spec.
Cl. 201

Dismantle existing cross drainage structure


Including disposal of resulting material and
1.02 Cu.m.
salvage reusable materials complete as per
Tech.Spec.Cl. 202
a) Brick / Stone/RCC structure 564.91 564.91 - - -
b) PCC in Substructure 119.65 119.65 - - -
c) RCC in Superstructure 370.80 370.80 - - -
g) Wearing coat 454.61 454.61 - - -

Earthwork in excavation of foundation for


1.03 structures in all types of soil including lead and Cu.m.
lifts complete as per Tech. Spec. Cl. 304

a) ordinary soil 1182.61 3281.33 2098.72 12.02 181.00 235.30 263.54 553,090.00
b) in soft/weathered rock 1213.65 140.20 (1073.45) 12.08 463.00 601.90 674.13 (723645.00)
c) in Hard Rock 140.20 140.20 12.09 918.00 1193.40 1336.61 187,388.00

Back filling behind abutments, wing walls,


return walls and foundation trenches with
1.04 selected granular material of approved quality Cu.m. 1198.00 1071.94 (126.06) 12.70 728.00 946.40 1059.97 (133618.00)
complete with all leads as per Tech. Spec.
Cl.710.1.4 of IRC:78and lifts complete

634544966.xlsx 7 of 12
Derived Rate, with ADD
Quantity as per Quantity as per SSR Item 2019-
Sl. No. Description Unit Excess Qty. Rate Area Weightage of GST(IGST+SGST Amount Remarks
DPR Revision 20
30% (Rs) ) @ 12%

Cement Concrete/Reinforced Cement Concrete


in open foundation / leveling course including
1.05 centering and shuttering but excluding Cu.m.
reinforcement all complete as per Tech.
Spec.Cl. 1500, 1700 & 2100

a) M15 Grade - Levelling Course 115.56 216.70 101.14 17.38 5916.00 7690.80 8613.70 871,209.00
Below Approach slab 17.52 24.45 6.93 14.58 4729.00 6147.70 6885.42 47,716.00

Cement concrete grade M20 in sub-structures


1.06 40.71 40.71 - 17.39 6200.00 8060.00 9027.20 -
and Foundation as per Tech. Spec. Cl. 1700.

Cement concrete grade M30 in sub-structures


1.07
and Foundation as per Tech. Spec. Cl. 1700.

Approach Slab Cu.m. 33.60 1180.49 1146.89 14.59 8427.00 10955.10 12269.71 14,072,010.00
Cement concrete grade M35 in Foundations as
1.08 Cu.m. 676.16 377.04 (299.12) 17.46 7084.00 9209.20 10314.30 (3085164.00)
per Tech. Spec. Cl. 1700.

Cement concrete grade M35 in sub-structures as


1.09 Cu.m. 539.37 1181.65 642.29 17.46 7615.30 9899.89 11087.88 7,121,586.00
per Tech. Spec. Cl. 1700. Hight upto 5 Mtr

Cement concrete grade M40 in super structures


1.10 Cu.m. 484.74 414.33 (70.40) 14.90 8138.00 10579.40 11848.93 -834,196.00
as per Tech. Spec. Cl. 1700.
Providing, cutting, bending and fixing in
position of TMT bar reinforcement in
1.11 Mt 189.06 307.12 118.06 14.01 62581.00 81355.30 91117.94 10,757,021.00
reinforced cement concrete structures complete
as per Tech. Spec. Cl 1600

Filter media with stone crushed aggregates


1.12 abutments/return walls as per clause 2504.2.2 Cu.m. 95.16 410.52 315.36 14.74 1946.00 2529.80 2833.38 893,540.00
and Tech. Spec. Cl.710.1.4 of IRC:78

Providing weep holes in abutments, returnwalls,


1.13 with 100mm dia AC pipes complete as per no's 150.00 418.00 268.00 17.37 424.00 551.20 617.34 165,449.00
drawing and Tech. Spec. Cl. 2706

1.14 Providing and fixing Expansion joint


Providing expansion joints with 25mm thick
bituminous pad as per detailed drawings Rmtr 35.31 35.31 - 14.33 845.00 1098.50 1230.32 -
etc.complete.

634544966.xlsx 8 of 12
Derived Rate, with ADD
Quantity as per Quantity as per SSR Item 2019-
Sl. No. Description Unit Excess Qty. Rate Area Weightage of GST(IGST+SGST Amount Remarks
DPR Revision 20
30% (Rs) ) @ 12%

Providing copper plate expansion joints as per


detailed drawing No.4/D-1 of 1972 D type etc. Rmtr 70.62 105.92 35.31 14.32 3816.00 4960.80 5556.10 196,176.00
complete.

Providing and fixing Tar paper bearing


1.15 Sq.m 10.59 10.59 - 13.02 81.00 105.30 117.94 -
complete as per drawing and IRC:SP:13-1973.

Supply, fitting and fixing in position true to line


1.16 and level POT-PTFE Bearings complete as per 42.00 0.00 (42.00) 60580.00 78754.00 (3307668.00) DPR Rate
Tech. Spec. Cl. 2000
Free bearing No 12.00 12.00 29618.00 38503.40 43123.81 517,486.00 New rate
Long guide bearing No 8.00 8.00 34309.00 44601.70 49953.90 399,632.00 New rate
Transverse bearing No 6.00 6.00 33259.00 43236.70 48425.10 290,551.00 New rate
Fix bearing No 4.00 4.00 49029.00 63737.70 71386.22 285,545.00 New rate

Proving and fixing Drainage spouts complete as


1.17 Each 22.00 22.00 - 19.41 897.99 1167.39 1307.47 - DPR Rate
per Tech. Spec. Cl. 2705

Providing and filling joint sealing compound as


per drawings with coarse sand and 6 percent
bitumen by weight (0.083 kg/m bitumen)
1.18 Rmtr 70.62 70.62 - 14.64 36.00 46.80 52.42 -
including cost and conveyance of all materials,
labour, fixing in position, etc., complete as per
drawing and Tech. Spec. Cl

Providing and laying wearing course on top of


Rs.385 rate on 12 mm
1.19 deck complete as per Tech.Spec.Cl.515 & 2702 Cum 44.62 44.62 - 14.86 9785.00 12720.50 14246.96 -
thick
65mm Thick (40BC+ 25 Asphaltic)

Construction of Crash Barrier M40 grade incl.


1.20 cost of all materials, labour, lead, lifts, loading, Rmtr 117.12 117.12 - 7.37 3086.00 4011.80 4493.22 -
unloading etc., complete
1.21 PVC Utility pipes (110 dia) Rmtr 117.12 117.12 - 17.36 460.00 598.00 669.76 -

Providing and applying 2 coats of Enamel paint


1.22 to plastered concrete surface complete as per Sq.m 33.85 33.85 - New rate 101.00 131.30 147.06 -
Tech.Spec Cl. 800 for RC Crash barrier

Provide and lay stone pitching as per Tech.


1.23 Cu.m. 25.97 410.40 384.44 14.72 1407.00 1829.10 2048.59 787,554.00
Spec. Cl. 2504.

1.24 metallic crash barrier m15 garde Cum 40.00 40.00 - 17.38 5916.00 7690.80 8613.70 -
- - -
- - -
1.25 RC Railing Rmtr 117.12 117.12 - 14.49 1646.00 2,139.80 2,396.58 -

634544966.xlsx 9 of 12
Derived Rate, with ADD
Quantity as per Quantity as per SSR Item 2019-
Sl. No. Description Unit Excess Qty. Rate Area Weightage of GST(IGST+SGST Amount Remarks
DPR Revision 20
30% (Rs) ) @ 12%

Painting of concrete hand rails/ parapets/


crash barriers with two coats of enamel
1.26 Sq.m 45.68 45.68 - New rate 101.00 131.30 147.06 -
paint as per Technical Specification and the
directions of the Engineer

Paininting of sub structures & super


structures with two coats of enamel paint as
1.27 Sq.m 909.40 1623.30 713.90 New rate 101.00 131.30 147.06 104,984.00
per Technical Specification and the
directions of the Engineer
Empty boring for 725 to1050 mm dia.bored
R.C.C.cast in situ piles including withdrawal of
shell, removal of earth to a distance of 50
1.29 metres etc. complete.Spec :(As directed by Rmtr - 420.00 420.00 22.54 1219 1584.70 1774.86 745,443.00
Engineer in Charge)

Carrying out load test for1.5 times the proposed


safe working load on the pile in driven position
above 900mm diameter including construction
of test cap,use of accessories and instruments
1.30 including providing graphs as per I.S.code or Nos 3.00 3.00 22.49 316432 411361.60 460724.99 1,382,175.00
Std.Specifications and dismantling the test cap
after testing and cleaning the site complete

Chipping and dressing of the R.C.C.piles upto


0.60 meter including cleaning reinforcement
and removal of dismantled materials upto a
1.31 distance of 50 meter beyond the building area Nos 42.00 42.00 22.55 597 776.10 869.23 36,508.00
etc.for providing pile caps.Spec :(As directed
by Engineer in Charge

Providing,placing and driving in position 6mm


thick permanent MS liner upto required depth
with 12mm thick MS cutting edge of 0.50 meter
length of bottom including fabricating,cutting
1.32 the MS sheet to required diameter and Mt - 65.08 65.08 15.128 75547 98211.10 109996.43 7,158,874.00
shape,welding the joints and driving with the
help of required machineries, all materials,
labour and lift etc. complete.

Total Excess amount 38,491,500.00

634544966.xlsx 10 of 12
Diaphgram
end 2 2.28 0.625 1.2
tappered 2 1.2 0.4575 0.65
middle 1 7.68 0.29 0.65
top 1 14.64 0.59 0.15
bottom 1 14.64 0.625 0.25
1 14.64 0.4575 0.15

Diaphgram 6 13.225 0.4 1.2

Cross Girde 3 13.225 0.3 0.95


3.420
0.714
1.448
1.296
2.288
1.005
10.169

38.088

11.307