POTABLE WATER AND FIRE FIGHTING

Client: INJAZ Development Co.


Project: Al Marina Development PAGE
PACKAGE 1 I/1
NUMBER
Bill of Quantities (MEASURED WORKS)
Potable Water and Fire Fighting Network

Amount
Ref Description Unit Quantity Rate
SAR

CLASS I: PIPEWORK – PIPES

POTABLE WATER SYSTEM

HOUSE / FUTURE CONNECTION

High-density polyethylene (HDPE) pipes including all


necessary fittings/accessories; to complete as described
drawing SO487 - 28

I712.1 Nominal bore: 20 mm m 3,698

I712.2 Nominal bore: 25 mm m 429

I712.3 Nominal bore: 32 mm m 792

I712.4 Nominal bore: 40 mm m 681

I712.5 Nominal bore: 50 mm m 381

I712.6 Nominal bore: 63 mm m 275

I712.7 Nominal bore: 80 mm m 601

House connection kit saddle, Ferrule cock as applicable


including all necessary accessories as shown in
drawing SO487 - 28 nr 402

Flow meter assembly as applicable including GRP box and


all necessary accessories to complete as describe
drawing SO487 - 28 nr 464

Total - SAR
Carried to Collection
Client: INJAZ Development Co.
Project: Al Marina Development PAGE
PACKAGE 1 I/2
NUMBER
Bill of Quantities (MEASURED WORKS)
Potable Water and Fire Fighting Network

Amount
Ref Description Unit Quantity Rate
SAR
Total - SAR
Carried to Collection

CLASS I: PIPEWORK – PIPES (CONT'D)

POTABLE WATER SYSTEM (CONT'D)

High-density polyethylene (HDPE) pipes; to


complete as described (cont'd)

Nominal bore: 110 mm

I712.8 In trenches, depth: not exceeding 1.5 m m 244

Nominal bore: 150 mm

I712.9 In trenches, depth: not exceeding 1.5 m m 2,824

Nominal bore: 200 mm

I712.10 In trenches, depth: not exceeding 1.5 m m 9,820

Ductile iron (DI) pipes; complete as described

Nominal bore: 250 mm

I322.1 In trenches, depth: not exceeding 1.5 m m 4,113

Nominal bore: 400 mm

I332.2 In trenches, depth: not exceeding 2 m m 350

FIRE FIGHTING SYSTEM

High-density polyethylene (HDPE) pipes; to


complete as described (cont'd)

Nominal bore: 150 mm

I512.1 In trenches, depth: not exceeding 1.5 m m 255


Client: INJAZ Development Co.
Project: Al Marina Development PAGE
PACKAGE 1 I/3
NUMBER
Bill of Quantities (MEASURED WORKS)
Potable Water and Fire Fighting Network

Amount
Ref Description Unit Quantity Rate
SAR

Total - SAR
Carried to Collection
Client: INJAZ Development Co.
Project: Al Marina Development PAGE
PACKAGE 1
NUMBER
Bill of Quantities (MEASURED WORKS)
I/S
Potable Water and Fire Fighting Network

Amount
Ref Description
SAR

CLASS I: PIPEWORK – PIPES

COLLECTION

Page I / 1

Page I / 2

Total - SAR
Carried to Potable Water and Fire Fighting Network Summary
Client: INJAZ Development Co.
Project: Al Marina Development PAGE
PACKAGE 1
NUMBER
Bill of Quantities (MEASURED WORKS)
I/S
Potable Water and Fire Fighting Network

Amount
Ref Description
Total - SAR SAR
Carried to Potable Water and Fire Fighting Network Summary
Client: INJAZ Development Co.
Project: Al Marina Development PAGE
PACKAGE 1 J/1
NUMBER
Bill of Quantities (MEASURED WORKS)
Potable Water and Fire Fighting Network

Amount
Ref Description Unit Quantity Rate
SAR

CLASS J: PIPEWORK – FITTINGS AND VALVES

POTABLE WATER SYSTEM

High-density polyethylene (HDPE) pipes fitting; complete


as described

Bends (11.25°)

J611.1 Nominal bore: 150 mm nr 6

J611.2 Nominal bore: 200 mm nr 49

Bends (22.5°)

J611.3 Nominal bore: 150 mm nr 5

J611.4 Nominal bore: 200 mm nr 13

Bends (45°)

J611.5 Nominal bore: 110 mm nr 4

J611.6 Nominal bore: 150 mm nr 27

J611.7 Nominal bore: 200 mm nr 86

Bends (90°)

J611.8 Nominal bore: 110 mm nr 8

J611.9 Nominal bore: 150 mm nr 2

J611.10 Nominal bore: 200 mm nr 10

Total - SAR
Carried to Collection
Client: INJAZ Development Co.
Project: Al Marina Development PAGE
PACKAGE 1 J/2
NUMBER
Bill of Quantities (MEASURED WORKS)
Potable Water and Fire Fighting Network

Amount
Ref Description Unit Quantity Rate
SAR
Total - SAR
Carried to Collection

CLASS J: PIPEWORK – FITTINGS AND VALVES


(CONT'D)

POTABLE WATER SYSTEM (CONT'D)

High-density polyethylene (HDPE) pipes fitting; complete


as described (Cont'd)

Junctions and branches (Tee)

J621.1 110 mm x 110 mm nr 2

J621.2 150 mm x 150 mm nr 36

J621.3 200 mm x 150 mm nr 8

J621.4 200 mm x 200 mm nr 94

Tapers

J631 200 mm x 150 mm nr 1

End caps

J691.1 Nominal bore: 110 mm nr 4

J691.2 Nominal bore: 200 mm nr 5


Client: INJAZ Development Co.
Project: Al Marina Development PAGE
PACKAGE 1 J/3
NUMBER
Bill of Quantities (MEASURED WORKS)
Potable Water and Fire Fighting Network

Amount
Ref Description Unit Quantity Rate
SAR

Total - SAR
Carried to Collection

CLASS J: PIPEWORK – FITTINGS AND VALVES


(CONT'D)

POTABLE WATER SYSTEM (CONT'D)

Ductile iron (DI) pipes fitting; complete as described

Bends (11.25°)

J312.1 Nominal bore: 250 mm nr 8

Bends (22.5°)

J312.2 Nominal bore: 250 mm nr 4

Bends (45°)

J312.3 Nominal bore: 250 mm nr 12

J312.4 Nominal bore: 400 mm nr 2

Bends (90°)

J312.5 Nominal bore: 250 mm nr 4

J312.6 Nominal bore: 400 mm nr 2

Junctions and branches (Tee)

J322.1 250 mm x 110 mm nr 2

J322.2 250 mm x 150 mm nr 2

J322.3 250 mm x 200 mm nr 10

J322.4 250 mm x 250 mm nr 5

J322.5 400 mm x 400 mm nr 3


Client: INJAZ Development Co.
Project: Al Marina Development PAGE
PACKAGE 1 J/4
NUMBER
Bill of Quantities (MEASURED WORKS)
Potable Water and Fire Fighting Network

Amount
Ref Description Unit Quantity Rate
SAR

Total - SAR
Carried to Collection

CLASS J: PIPEWORK – FITTINGS AND VALVES


(CONT'D)

POTABLE WATER SYSTEM (CONT'D)

Ductile iron (DI) pipes fittings; complete as described


(Cont'd)

Tapers

J332 400 mm x 250 mm nr 1

End caps

J392 Nominal bore: 250 mm nr 2

Valves and penstocks; complete as described

Gate valves: hand operated

J811.1 Nominal bore: 150 mm nr 18

J811.2 Nominal bore: 200 mm nr 75

J812.1 Nominal bore: 250 mm nr 23

J812.2 Nominal bore: 400 mm nr 1


Client: INJAZ Development Co.
Project: Al Marina Development PAGE
PACKAGE 1 J/5
NUMBER
Bill of Quantities (MEASURED WORKS)
Potable Water and Fire Fighting Network

Amount
Ref Description Unit Quantity Rate
SAR

Total - SAR
Carried to Collection

CLASS J: PIPEWORK – FITTINGS AND VALVES


(CONT'D)

Valves and penstocks; complete as described (Cont'd)

Air release valves

J861.1 Nominal bore: 200 mm nr 1

J862.1 Nominal bore: 250 mm nr 4

Flow meter

J893 Nominal bore: 400 mm nr 2

FIRE FIGHTING SYSTEM

High-density polyethylene (HDPE) pipes fitting; complete


as described

Bends (90°)

J611.1 Nominal bore: 150 mm nr 51

Valves and penstocks

Fire hydrant including valves and steel bollards complete as


shown on standard drawings of Ministry of Water and
Electricity for potable water and fire fighting network
reference drawing no.26

J691 Fixing to 150 mm diameter pipe nr 51


Client: INJAZ Development Co.
Project: Al Marina Development PAGE
PACKAGE 1 J/6
NUMBER
Bill of Quantities (MEASURED WORKS)
Potable Water and Fire Fighting Network

Amount
Ref Description Unit Quantity Rate
SAR

Total - SAR
Carried to Collection
Client: INJAZ Development Co.
Project: Al Marina Development PAGE
PACKAGE 1
NUMBER
Bill of Quantities (MEASURED WORKS)
J/S
Potable Water and Fire Fighting Network

Amount
Ref Description
SAR

CLASS J: PIPEWORK – FITTINGS AND VALVES

COLLECTION

Page J / 1

Page J / 2

Page J / 3

Page J / 4

Page J / 5

Total - SAR
Carried to Potable Water and Fire Fighting Network Summary
Client: INJAZ Development Co.
Project: Al Marina Development PAGE
PACKAGE 1
NUMBER
Bill of Quantities (MEASURED WORKS)
J/S
Potable Water and Fire Fighting Network

Amount
Ref Description
Total - SAR SAR
Carried to Potable Water and Fire Fighting Network Summary
Client: INJAZ Development Co.
Project: Al Marina Development PAGE
PACKAGE 1 K/1
NUMBER
Bill of Quantities (MEASURED WORKS)
Potable Water and Fire Fighting Network

Amount
Ref Description Unit Quantity Rate
SAR

CLASS K: PIPEWORK – MANHOLES AND


PIPEWORK ANCILLARIES

POTABLE WATER SYSTEM

Chamber: including pipework and associated fittings,


heavy lockable cast iron cover and frame, reinforced
concrete, steel steps, pipework supports, and water proofing
membrane, as shown on standard drawings of Ministry of
Water and Electricity for potable water and fire fighting
network reference drawing no.09 up to 32; complete as
described

In situ concrete: for washout chamber

K231.1 Depth: not exceeding 1.5 m nr 3

In situ concrete: for gate valve

K231.2 Depth: not exceeding 1.5 m nr 117

In situ concrete: for air release valve

K231.3 Depth: not exceeding 1.5 m nr 5

In situ concrete: for flow meter

K231.4 Depth: not exceeding 1.5 m nr 2

Total - SAR
Carried to Collection
Client: INJAZ Development Co.
Project: Al Marina Development PAGE
PACKAGE 1 K/2
NUMBER
Bill of Quantities (MEASURED WORKS)
Potable Water and Fire Fighting Network

Amount
Ref Description Unit Quantity Rate
Total - SAR SAR
Carried to Collection
Client: INJAZ Development Co.
Project: Al Marina Development PAGE
PACKAGE 1
NUMBER
Bill of Quantities (MEASURED WORKS)
K/S
Potable Water and Fire Fighting Network

Amount
Ref Description
SAR

CLASS K: PIPEWORK – MANHOLES AND


PIPEWORK ANCILLARIES

COLLECTION

Page K / 1

Total - SAR
Carried to Potable Water and Fire Fighting Network Summary
Client: INJAZ Development Co.
Project: Al Marina Development PAGE
PACKAGE 1
NUMBER
Bill of Quantities (MEASURED WORKS)
K/S
Potable Water and Fire Fighting Network

Amount
Ref Description
Total - SAR SAR
Carried to Potable Water and Fire Fighting Network Summary
Client: INJAZ Development Co.
Project: Al Marina Development PAGE
PACKAGE 1 L/1
NUMBER
Bill of Quantities (MEASURED WORKS)
Potable Water and Fire Fighting Network

Amount
Ref Description Unit Quantity Rate
SAR

CLASS L: PIPEWORK – SUPPORTS AND


PROTECTION, ANCILLARIES TO LAYING AND
EXCAVATION

POTABLE WATER SYSTEM

Concrete stools and thrust blocks: concrete class 210/25,


poured against undisturbed soil, pipe and fittings entry and
exit parts, and thrust block details, drawing no. 01 up to 08
shown on standard drawings of Ministry of Water and
Electricity for potable water and fire fighting network with
thrust block details reference drawing no.01 up to 08;
complete as described

Volume: 0.1 - 0.2 m³

L721.1 Pipe bore: 150 mm nr 12

L721.2 Pipe bore: 200 mm nr 16

Volume: 0.2 - 0.5 m³

L731.1 Pipe bore: 150 mm nr 28

L731.2 Pipe bore: 200 mm nr 51

L732 Pipe bore: 250 mm nr 13

L733 Pipe bore: 400 mm nr 8

Total - SAR
Carried to Collection
Client: INJAZ Development Co.
Project: Al Marina Development PAGE
PACKAGE 1 L/2
NUMBER
Bill of Quantities (MEASURED WORKS)
Potable Water and Fire Fighting Network

Amount
Ref Description Unit Quantity Rate
Total - SAR SAR
Carried to Collection
Client: INJAZ Development Co.
Project: Al Marina Development PAGE
PACKAGE 1
NUMBER
Bill of Quantities (MEASURED WORKS)
L/S
Potable Water and Fire Fighting Network

Amount
Ref Description
SAR

CLASS L: PIPEWORK – SUPPORTS AND PROTECTION, ANCILLARIES TO LAYING


AND EXCAVATION

COLLECTION

Page L / 1

Total - SAR
Carried to Potable Water and Fire Fighting Network Summary
Client: INJAZ Development Co.
Project: Al Marina Development PAGE
PACKAGE 1
NUMBER
Bill of Quantities (MEASURED WORKS)
L/S
Potable Water and Fire Fighting Network

Amount
Ref Description
Total - SAR SAR
Carried to Potable Water and Fire Fighting Network Summary
Client: INJAZ Development Co.
Project: Al Marina Development PACKAGE 1 PAGE
POTABLE WATER & FF NUMBER
Bill of Quantities SUMMARY PWFF / S
Potable Water and Fire Fighting Network

Amount
Ref Description
SAR

POTABLE WATER AND FIRE FIGHTING SUMMARY

Class I - Pipework - Pipes From Page I / S

Class J - Pipework - Fittings and Valves From Page J / S

Class K - Pipework - Manholes and Pipework Ancillaries From Page K / S

Class L - Pipework - Supports and Protection Ancillaries From Page L / S

Total - SAR
Carried to Grand Summary
Client: INJAZ Development Co.
Project: Al Marina Development PACKAGE 1 PAGE
POTABLE WATER & FF NUMBER
Bill of Quantities SUMMARY PWFF / S
Potable Water and Fire Fighting Network

Amount
Ref Description
Total - SAR SAR
Carried to Grand Summary