Deck job work progress by shipyard asf:
1. Steel work
1.1 Main deck top plate and hatch coaming
1.2 Electric cable pipe.
1.3 Hatch cover ( top and under side)
1.4 Cargo hold tank top ( hold no.4 and 6)
1.5 Lower stool bulk head, frame face plate and bracket.
1.6 Damaged bilge pipe and air vent pipe.
1.7 Insert face plate to mooring bitts on deck (at mark by LR survey)
Action : Not progress
7. In quotation:
7.1 Blasting and painting under SUL structure starboard side (H&M)
7.2 Blasting and painting APT (H&M)
7.3 Blasting and painting crane body under stand platform.
Action: No progress
10. Repair davit pulley corroded Steel structure lifeboat port side ( Lifeboat
deficiency recommended)
Action: No progress
2. Radio service
Action: found definitely item
- Battery for SART not good // in Requested
- EPIRB battery No power // in Requested
- ITU publication need to ne edition update// in Requested