CS2 ADSORPTION PLANT 2

(CAP-2) PROJECT
PT. SOUTH PACIFIC VISCOSE

PO Number : B21/1008/44710219

Equipment / Material : Steam Accumulator

INSPECTION AND TEST PLAN


FOR STEAM ACCUMULATOR (41.2.55.GE101)

Code Description
A Approved
B Approved With Comment
C Not Approved - Revise & Resubmit
D Cancelled
E Received as Information
Signature:
Hendra Maulana
Hadiana Abduh

1.0 Issued For Construction 28-Jun-22


RSS ADW DEP
0.0 Issued For Construction 25-Jun-22 RSS ADW DEP
0.3 Re-Issued For Approval 07-Jun-22 RSS ADW DEP
0.2 Re-Issued For Approval 02-Jun-22 RSS ADW DEP
0.1 Issued For Approval 07-Apr-22 RSS ADW DEP
Rev Issue Purpose Date Author Checked Approver OWNER

OWNER Project Number OWNER Doc Number EPCm VENDOR Doc Number

X-333004-023 2924-SKM-139AC-ITP-0001
CS2 ADSORPTION PLANT 2 (CAP-2) PROJECT
ITP For Steam Accumulator (41.2.55.GE101)

Revision Amender
Amendment Date Amendment
Number Name
07-04-2022 0.1 Ridho SS

02-06-2022 0.2 Ridho SS Re-Issued For Approval

For Insulation not our scope, scope PT. SKM only Fabrication
Insulation Cleat.
Explanation for Insulation Cleat at point No. V ( 4.Check Internal
& External)
07-06-2022 0.3 Ridho SS Re-Issued For Approval

25-06-2022 0.0 Ridho SS Issued For Construction

28-06-2022 1.0 Ridho SS Issued For Construction

Changes Point V. Fabrication ( add removable Internals


(demister))

Holds
Hold Section
Short description of hold
No Number

2924-SKM-139AC-ITP-0001
Rev No: 0.0 Page 2 of 9
CS2 ADSORPTION PLANT 2 (CAP-2) PROJECT
ITP For Steam Accumulator (41.2.55.GE101)

Table of Contents
1. INTRODUCTION........................................................................................................................................ 4
1.1. Project Background ……………………………………………………………………………………………………………………………4
1.2. Project Location …………………………………………………………………………………………………………………………………4
1.3. Reference Document …………………………………………………………………………………………………………………………4
2. INSPECTION & TEST PLAN ……..……………………………………………………………………………………………………….………5

2924-SKM-139AC-ITP-0001
Rev No: 0.0 Page 3 of 9
CS2 ADSORPTION PLANT 2 (CAP-2) PROJECT
ITP For Steam Accumulator (41.2.55.GE101)

1 INTRODUCTION

1.1 Project Background


Lenzing (SPV) is intended to setup new Carbon Disulfide (CS2) Adsorption Plant (CAP-2) at
existing manufacturing site PT South Pacific Viscose (SPV), Purwakarta, Indonesia. The existing
site already has CAP-1 plant which is currently in operation.
Lenzing AG is intended to setup new Carbon Disulfide (CS2) Adsorption Plant (CAP-2) at existing
manufacturing site of PT. South Pacific Viscose (SPV), Purwakarta, Indonesia. The existing SPV
facility includes an existing CAP-1 plant, which are running continuously.
SPV has conducted Basic Engineering of CAP-2 and is preparing for the execution phase. SPV is
hereby appointing EPCm Contractors for execution of CAP-2 Facilities.
Tripatra Engineering (CONSULTANT) has been awarded by PT SPV to perform EPCm Services
Carbon Disulfide 2 (CAP-2) Plant Project based upon Engineering Procurement and Construction
Management Contract of Carbon Disulfide Adsorption Plant -2 between PT SOUTH PACIFIC
VISCOSE and PT. TRIPATRA ENGINEERING.

1.2 Project Location

Figure 1. Project Location

1.3 Reference Document


The following documents shall be referred and followed.
Table 1-1 Reference Document

NO NAME DESCRIPTION
1
2

2924-SKM-139AC-ITP-0001
Rev No: 0.0 Page 4 of 9
PT. SOUTH PACIFIC VISCOSE

PT. SK METALINDO INSPECTION AND TEST PLAN FOR STEAM ACCUMULATOR (41.2.55.GE101)
Manufacturers & Fabricators

PROJECT : CS2 ADSORPTION PLANT 2 PROJECT DOC. NO. : 2924-SKM-139AC-ITP-0001 FABRICATOR : PT. SK METALINDO PI : PERUSAHAAN INSPEKSI (3rd PARTY)
DEPNAKER : DEPARTEMEN KETENAGAKERJAAN
PROJECT/ORDER NO : B21/1008/44710219 DATE ISSUE : 28 June 2022 CPY : PT. SOUTH PACIFIC VISCOSE
(GOVERNMENT/REGULATOR)
JOB/WO NO : FB-2204-0061-I REV : 1.0 MAIN CONTRACTOR : PT. TRIPATRA ENGINEERING CPY : COMPANY / OWNER

Inspection Level
No Stage Reference Acceptance Criteria Verifying Document
SKM TPE SPV DEPNAKER

I. ENGINEERING DOCUMENTS

 Drawing Approval
1. Drawing  Project Specification Latest Revision ( Approved
 Project Specification P R R
 Aplicable Code / Standard document )
 Purchase Order

II. QUALITY DOCUMENTS

1. Inspection & Test Plan


2. WPS & PQR
3. Welder Certificate  Latest Revision
( Approved document )
4. NDE Personnel Certificate  Project Specification
 Welder Certification
5. NDE Procedure  Purchase Order  Project Specification
 Nde Personnel P R R
6. Hydrotest Procedure  ASME Sect IX  Aplicable Code / Standard Certification
7. Visual Procedure  WPS & PQR
8. Pickling & Passivation Procedure
9. Painting Procedure
10. Packing Procedure

 Project Spesification
III PRE-INSPECTION MEETING Purchase order  Engineering document Minutes of Meeting H H W
 Quality document

IV. MATERIAL RECEIVING INSPECTION

1. Review of Material Traceability,  ASME Sect II  Project Specification  Material Traceability P R R


Chemical Composition,
Mechanical Properties  Drawing Approval  ASME Sect II A  Receiving Material
PT. SOUTH PACIFIC VISCOSE

PT. SK METALINDO INSPECTION AND TEST PLAN FOR STEAM ACCUMULATOR (41.2.55.GE101)
Manufacturers & Fabricators

PROJECT : CS2 ADSORPTION PLANT 2 PROJECT DOC. NO. : 2924-SKM-139AC-ITP-0001 FABRICATOR : PT. SK METALINDO PI : PERUSAHAAN INSPEKSI (3rd PARTY)
DEPNAKER : DEPARTEMEN KETENAGAKERJAAN
PROJECT/ORDER NO : B21/1008/44710219 DATE ISSUE : 28 June 2022 CPY : PT. SOUTH PACIFIC VISCOSE
(GOVERNMENT/REGULATOR)
JOB/WO NO : FB-2204-0061-I REV : 1.0 MAIN CONTRACTOR : PT. TRIPATRA ENGINEERING CPY : COMPANY / OWNER

Inspection Level
No Stage Reference Acceptance Criteria Verifying Document
SKM TPE SPV DEPNAKER

2. Material Inspection, Check  Mill Certificate


Visual, Dimensional, Heat P W W
Number, Plate Number

V. FABRICATION

1. Check Marking & Cutting


 Check Trasfer Heat Number
2. Fit up Inspection
 Check Gap,Aligment, Dimension
& Orientation
3. Welding Inspection
 Variables in WPS  ASME Sec. II  ASME Sec. II  Dimensional Report
 Check Welding Consumable  ASME Sec. VIII Div. 1  ASME Sec. VIII. Div.1  Welding Inspection
 Verification Welder  Drawing Approval  Drawing Approval Report P R
R
 Check Visual & Dimensional  WPS & PQR Approval  WPS & PQR Approval
& Orientation
4. Check Internal & External
 Lifting Lug, Support, Insulation
Cleat, Etc
5. Removeble Internal (demister) - R R
 Fit up and Installation (By Other)

VI. NON DESTRUCTIVE TESTING

1. Visual Examination ( VT )
 100% For All Joint P R R
PT. SOUTH PACIFIC VISCOSE

PT. SK METALINDO INSPECTION AND TEST PLAN FOR STEAM ACCUMULATOR (41.2.55.GE101)
Manufacturers & Fabricators

PROJECT : CS2 ADSORPTION PLANT 2 PROJECT DOC. NO. : 2924-SKM-139AC-ITP-0001 FABRICATOR : PT. SK METALINDO PI : PERUSAHAAN INSPEKSI (3rd PARTY)
DEPNAKER : DEPARTEMEN KETENAGAKERJAAN
PROJECT/ORDER NO : B21/1008/44710219 DATE ISSUE : 28 June 2022 CPY : PT. SOUTH PACIFIC VISCOSE
(GOVERNMENT/REGULATOR)
JOB/WO NO : FB-2204-0061-I REV : 1.0 MAIN CONTRACTOR : PT. TRIPATRA ENGINEERING CPY : COMPANY / OWNER

Inspection Level
No Stage Reference Acceptance Criteria Verifying Document
SKM TPE SPV DEPNAKER

2. Radiography Examination ( RT )  VT Report P R R


 100%  Welding & NDE Map  ASME Sec V  RT Report P R R
3. Dye Penetrant Test ( DPT )  NDE Procedure  ASME Sec VIII Div. 1  DPT Report P R R
 Yes For All Joint

VII. FINAL INSPECTION

1. Check Visual & Final Dimensionn


 Drawing Approval  Drawing Approval  Dimensional Report P W W
2. Check Completeness of Part

VIII. HYDROTEST

1. Test Pressure operation


“hydrotest for the equitment witness
by Customer / Owner will be selected  Hydrotest Procedure  No Leak
 Hydrotest Report P H H W
by owner based on equipment citical  Holding Time 1 Hours
rating
2. Record

IX. PICKLING & PASSIVATION

1. Surface Preparation
 Project Specification  Pickling Procedure  Pickling Report P R R
2. Cleaning

XI. PAINTING

1. Surface Preparation  Painting Procedure  Painting Procedure  Painting Report P R R


PT. SOUTH PACIFIC VISCOSE

PT. SK METALINDO INSPECTION AND TEST PLAN FOR STEAM ACCUMULATOR (41.2.55.GE101)
Manufacturers & Fabricators

PROJECT : CS2 ADSORPTION PLANT 2 PROJECT DOC. NO. : 2924-SKM-139AC-ITP-0001 FABRICATOR : PT. SK METALINDO PI : PERUSAHAAN INSPEKSI (3rd PARTY)
DEPNAKER : DEPARTEMEN KETENAGAKERJAAN
PROJECT/ORDER NO : B21/1008/44710219 DATE ISSUE : 28 June 2022 CPY : PT. SOUTH PACIFIC VISCOSE
(GOVERNMENT/REGULATOR)
JOB/WO NO : FB-2204-0061-I REV : 1.0 MAIN CONTRACTOR : PT. TRIPATRA ENGINEERING CPY : COMPANY / OWNER

Inspection Level
No Stage Reference Acceptance Criteria Verifying Document
SKM TPE SPV DEPNAKER

2. Painting Inspection (3 Coat  Project Specification  DFT Thickness


System)

INSPECTION RELEASE NOTE  IRN Report P H R

XI. MANUFACTURING DATA REPORT

Manufacturing data Report ( MDR )


MDR Index MDR Index
MDR BOOK P R R

XII. DISNAKER Certification DISNAKER Certification M R R

XIII. Preservation, Packing and Marking  Packing Procedure  Packing Procedure P R R

LEGEND

DOCUMENT ACTIVITY
Provide (P) Perform (P)
An activity to create and deliver a document for review and/or approval The execution of a scope of work
Approval (A) Verify (V)
Document shall be subject for approval prior to activity commencement Verification action for make sure inspection report document.
Review (R) Monitor (M)
Document to be reviewed and commented prior to activity commencement A designated activity that does not require formal advance notification to COMPANY or its appointees or certifying authorities.
Work may proceed without regard to the presence of COMPANY or its appointees on schedule. COMPANY or its appointees
will provide an ad-hoc or informal surveillance.
Witness (W)
A designated activity that requires a 3 Days advance notification to COMPANY or its appointees and certifying authorities.
Work may proceed on schedule if COMPANY or its appointees or certifying authorities fail to show at the appointed time for
PT. SOUTH PACIFIC VISCOSE

PT. SK METALINDO INSPECTION AND TEST PLAN FOR STEAM ACCUMULATOR (41.2.55.GE101)
Manufacturers & Fabricators

PROJECT : CS2 ADSORPTION PLANT 2 PROJECT DOC. NO. : 2924-SKM-139AC-ITP-0001 FABRICATOR : PT. SK METALINDO PI : PERUSAHAAN INSPEKSI (3rd PARTY)
DEPNAKER : DEPARTEMEN KETENAGAKERJAAN
PROJECT/ORDER NO : B21/1008/44710219 DATE ISSUE : 28 June 2022 CPY : PT. SOUTH PACIFIC VISCOSE
(GOVERNMENT/REGULATOR)
JOB/WO NO : FB-2204-0061-I REV : 1.0 MAIN CONTRACTOR : PT. TRIPATRA ENGINEERING CPY : COMPANY / OWNER

Inspection Level
No Stage Reference Acceptance Criteria Verifying Document
SKM TPE SPV DEPNAKER

the activity. Activity may be waived by COMPANY or its appointees and shall be in writing.
Hold (H)
A designated activity that requires a 3 Days advance notification to COMPANY or its appointees and certifying authorities.
Work shall not proceed beyond this point without written confirmation of witness or waiver.

PT. SK METALINDO PT. TRIPATRA ENGINEERING PT. SOUTH PACIFIC VISCOSE


Prepared By Approved By Approved By Approved By

Ridho Syahidussukron Danang Edi Prasetyo


QC Engineer QA/QC Manager