2 Proportions of the Contract Price for different stages of Construction of the Project Highway shall be as specified below:-
Weightage in
Item Stage for Payment Percentage weightage
% of CP
1 2 3 4
A- New 2/4 - lane realignment/
bypass (Flexible pavement) Excluding
approaches of Structures i.e. other
than TCS 3,3A &3B
(1) Site Clearance 0.09%
(2) Earthwork upto bottom of Subgrade 5.01%
(3) Subgrade Top 2.09%
(4) Sub-base Course (GSB/CTSB) 3.66%
(5) Non bituminous base course
6.93%
(CTB+AIL)
(6) Bituminous base course (DBM) 7.39%
(7) Bituminous Wearing course (BC) 6.17%
(8) Earthern Shoulder with slope
dressing in separator (Excluding PCC 0.67%
on top)
(9) Median dressing and drain 1.00%
B New 2/4 - lane realignment/
bypass (Flexible pavement) at
approaches of Structures i.e. TCS
3,3A &3B
(1) Site Clearance 0.06%
(2) Earthwork upto bottom of Subgrade 6.59%
Road works (3) Subgrade Top 0.81%
(excluding the road (4) Sub-base Course (GSB/CTSB) 1.42%
works in (5) Non bituminous base course
approaches of 2.70%
(CTB+AIL)
structures) (6) Bituminous base course (DBM) 2.87%
53.83%
including Culverts,
widening and repair (7) Bituminous Wearing course (BC) 2.40%
of culverts. (8) Earthern Shoulder with slope
including Culverts, dressing in separator and kerb
1.65%
widening and Channel(Excluding PCC on
top)

C Service Road (Flexible pavement)

(1) Earthwork up to top of the sub-grade 3.39%


(2) Sub-base Course (GSB) 3.09%
(3) Non bituminous base course
6.79%
(CTB+AIL)
(4) Bituminous course including
6.02%
earthern shoulder
D Service Road (Rigid pavement)
(1) Earthwork up to top of the sub-grade 1.30%
(2) Sub-base Course (GSB) 0.89%
(3) Base Course (DLC) 2.24%
(4) Wearing course (PQC) 6.27%
E Slip Road/Entry-exit arrangements
(Flexible pavement)
(1) Earthwork up to top of the sub-grade 0.28%
(2) Sub-base Course (GSB) 0.20%
(3) Non bituminous base course
0.53%
(CTB+AIL)
(4) Bituminous course including
1.58%
earthern shoulder
F -Re-Construction and New Culvert
on existing road, realignment, bypass.
Box /Slab Culverts (length < 06 m) 11.56%
Protection /Misc. works of Box/Slab
2.89%
Culverts
HPC Culverts (length < 06 m) 1.17%
Protection/Misc works of Box/Slab
0.29%
Culverts

A.1 Repair/Rehabilitation of
existing Minor Bridges (length > 06
m and < 60 m)
(1) Minor Bridges 0.00%
A.2 New /Reconstruction Minor
Bridges (length >6m and<60m).
(1)Foundation 14.69%
(2) Sub Structure (upto bottom of
5.88%
pier cap)
(3) Sub Structure (Pier Cap including
pedestals or final lift and bracket 5.88%
portion)
(4) Super structure (Castig and
completion of girder, fit for 11.75%
launching)
(5) Super structure (Launching of
10.58%
girder and deck slab casting )
(6) Super-structure On completion of
super structure in all respects including
wearing coat,bearings, expansion joints,
2.94%
hand rails, crash barriers, road signs and
marking excluding tests on completion
etc. Complete in all respect.
(7) Approaches On completion of
approach slab ,backfilling of filter
Minor Bridges media , return wall 2.94%
(including Service includingreturn/Retaining walls,
road 15.77% complete in all respect .
bridges)/Underpass/ (8) Protection Works on
overpass completion of stone pitching,
2.94%
protection works complete in all respect
.
(9) Guide Bunds and River Training
Works on
completion of guide bunds and 1.15%
river training works complete in all
respect.
(10) Other Works (Test on 1.18%
completion)
A.2 New /Reconstruction
UnderPass/Over pass
(length >6m and<60m).
(1)Foundation 8.46%
(2) Sub Structure (upto bottom of
3.39%
pier cap)
(3) Sub Structure (Pier Cap including
pedestals or final lift and bracket 3.39%
portion)
(4) Super structure (Castig and
completion of girder, fit for 3.39%
launching)
(5) Super structure (Launching of
girder and deck slab casting ) only 8.47%
deck slab for LVUP
(6) Super-structure On completion of
super structure in all respects including
wearing coat, bearings, expansion
3.39%
joints, hand rails, crash barriers, road
signs and marking excluding tests on
completion etc. Complete in all respect.
(7) Approaches of structures
7.1 RE panel casting 1.55%
7.2 Erection and back filling 2.48%
7.3 Coping Beam and friction
Slab/geocell 2.17%
completion
(8) Under Bridge works such as
footpath , 1.69%
painting of RE wall etc.
(9) Other Works (Test on completion) 1.69%
B.1 Repair/Rehabilitation of
existing
underpass/overpass
underpass/overpass 0.00%

A-1 Repair/Reahabilitation of major


bridges
(1) Major bridge 0.00%
A.2-New Major Bridges
(1) Foundation 10.13%
(2) Sub Structure (upto bottom of
4.06%
pier cap)
(3) Sub Structure (Pier Cap including
4.06%
pedestals)
(4) Super structure (Castig and
completion of 8.12%
girder, fit for launching)
(5) Super structure (Launching of
girder and 7.31%
deck slab casting )
(6) Super-structure On completion of
super structure in all respects including
wearing coat, bearings, expansion
2.03%
joints, hand rails, crash barriers, road
Major Bridge signs and marking excluding tests on
(length >60m) 4.23% completion etc. Complete in all respect.
works and ROB (7) Approaches On completion of
approaches including return/Retaining
2.03%
walls, stone pitching, protection works
complete in all respect .
(8) Protection Works on
completion of stone pitching,
2.03%
protection works complete in all respect
.
(9) Guide Bunds and River Training
Works on completion of guide
1.46%
bunds and river training works
complete in all respect.
(10) Other Works (Test on
0.81%
completion)
B-1 ROB
(1)Foundation 8.14%
(2) Sub Structure (upto bottom of
5.43%
pier cap)
(3) Sub Structure (Pier Cap including
5.43%
pedestals)
(4) Super structure (Castig and
completion of 18.99%
girder, fit for launching)
(5) Super structure (Launching of
girder and 10.85%
deck slab casting )
(6) Super-structure On completion of
super structure in all respects including
wearing coat, bearings, expansion
4.34%
joints, hand rails, crash barriers, road
signs and marking excluding tests on
completion etc. Complete in all respect.
(7) Approaches of structures
7.1 RE panel casting 0.92%
7.2 Erection and back filling 1.48%
7.3 Coping Beam and friction
Slab/geocell 1.29%
completion
(8) Other Works (Test on completion
1.09%
)

A-1 Flyovers
(1)Foundation 21.89%
(2) Sub Structure (upto bottom of
11.38%
pier cap)
(3) Sub Structure (Pier Cap including
13.13%
pedestals)
(4) Super structure (Castig and
completion of 17.51%
girder, fit for launching)
(5) Super structure (Launching of
girder and 17.51%
deck slab casting )
(6) Super-structure On completion of
Flyovers 5%
super structure in all respects including
wearing coat, bearings, expansion
4.38%
joints, hand rails, crash barriers, road
signs and marking excluding tests on
completion etc. Complete in all respect.
(7) Approaches of structures
7.1 RE panel casting 3.11%
7.2 Erection and back filling 4.98%
7.3 Coping Beam and friction
Slab/geocell 4.36%
completion
(8) Other Works (Test on completion) 1.75%

(1) PCC lining at slope,slope protection


, Drain in 4.82%
Separator
(2) Lined Box Drain with footpath 6.46%
(3) Road signs, marking, km stones,
safety device 18.43%
etc
Other Works 17.96%
(4) Project facilities
a)Bus Shelter (34 nos.) 1.04%
b) Rest areas (works as per Schedule B) 2.03%
c) Street Lighting including connection
3.72%
charges
d) High Mast Lighting 0.93%
e) Medical/traffic and vehicle aid post 0.00%
(5) Junction improvement 18.88%
(6) Safety and traffic management
during 0.00%
construction.
(7) Median/New Jersey type crash
barriers 5.99%
including Anti Glare Device
(8) Plantation , landscaping and
asthetic 5.08%
improvement works
(9) Protection Work ( Retaining wall,
Toe Wall, 6.12%
Stone Pitching, Parapet Wall etc.)
(10) Ramp Toll Plazas,Control center
17.26%
and ATMS
(11) Incident Management System 1.07%
(12) MBCB-Thrie Beam 6.80%
(14) Rain water Harvesting 0.58%
(15) Utility Duct 0.79%
Shifting of Electrical & Water Supply
Shifting of Utility Utilities
3.21%
Services
(a) Electrical Utilities 100.00%
100.00%
1.3 Procedure of estimating the value of work done
1.3.1 Road works
Stage for Payment Percentage weightage Payment Procedure
1 2 3
A- New 2/4 - lane realignment/
bypass (Flexible pavement)
Excluding approaches of Structures
i.e. other than TCS 3,3A &3B
(1) Site Clearance 0.09%
(2) Earthwork upto bottom of Subgrade 5.01% Unit of measurement is linear length.
(3) Subgrade Top 2.09% Unit of measurement is linear length.
Payment of each stage shall be made on
(4) Sub-base Course (GSB/CTSB) 3.66%
pro rata basis on completion of a stage in
(5) Non bituminous base course a length of not less than 10 (ten) percent
6.93%
(CTB+AIL) of the total length. or 2km whichever
(6) Bituminous base course (DBM) 7.39% being lower..
(7) Bituminous Wearing course (BC) 6.17%
(8) Earthern Shoulder with slope
dressing in 0.67%
separator (Excluding PCC on top)
(9) Median dressing and drain 1.00%
B New 2/4 - lane realignment/
bypass (Flexible pavement) at
approaches of Structures i.e. TCS
3,3A &3B
(1) Site Clearance 0.06%
(2) Earthwork upto bottom of Subgrade 6.59% Unit of measurement is linear length.
(3) Subgrade Top 0.81% Unit of measurement is linear length.
Payment of each stage shall be made on
(4) Sub-base Course (GSB/CTSB) 1.42% pro rata basis on completion of a stage in
(5) Non bituminous base course a length of not less than 10 (ten) percent
2.70%
(CTB+AIL) of the total length. or 2km whichever
(6) Bituminous base course (DBM) 2.87% being lower.
(7) Bituminous Wearing course (BC) 2.40%
(8) Earthern Shoulder with slope
dressing in separator and kerb 1.65%
Channel(Excluding PCC on top)
C Service Road (Flexible pavement)
(1) Earthwork up to top of the sub- Unit of measurement is linear length.
3.39%
grade Unit of measurement is linear length.
(2) Sub-base Course (GSB) 3.09% Payment of each stage shall be made on
(3) Non bituminous base course pro rata basis on completion of a stage in
6.79% a length of not less than 10 (ten) percent
(CTB+AIL)
(4) Bituminous course including of the total length. or 1km whichever
6.02% being lower.
earthern shoulder
D Service Road (Rigid pavement)
(1) Earthwork up to top of the sub- Unit of measurement is linear length.
1.30%
grade Unit of measurement is linear length.
(2) Sub-base Course (GSB) 0.89% Payment of each stage shall be made on
pro rata basis on completion of a stage in
(3) Base Course (DLC) 2.24%
a length of not less than 10 (ten) percent
(4) Wearing course (PQC) 6.27% of the total length. or 1km whichever
being lower.
E Slip Road/Entry-exit
arrangements (Flexible pavement)
(1) Earthwork up to top of the sub- Unit of measurement is linear length.
0.28%
grade Unit of measurement is linear length.
(2) Sub-base Course (GSB) 0.20% Payment of each stage shall be made on
(3) Non bituminous base course pro rata basis on completion of a stage in
0.53% a length of not less than 10 (ten) percent
(CTB+AIL)
(4) Bituminous course including of the total length. or 500m whichever
1.58% being lower..
earthern shoulder
F -Re-Construction and New Culvert
on existing road, realignment,
bypass.
Box /Slab Culverts (length < 06 m) 11.56%
Cost of completed culverts shall be
Protection /Misc. works of Box/Slab
2.89% determined on pro rata basis with respect
Culverts
to the total number of culverts.
HPC Culverts (length < 06 m) 1.17% Payment shall be made on the completion
Protection/Misc works of Box/Slab of at least two culverts.
0.29%
Culverts
1.3.2 Minor Bridges and Underpasses/Overpasses.
Stage for Payment Percentage weightage Payment Procedure
1 2 3
A.1 Repair/Rehabilitation of existing
Minor Bridges (length > 06 m and <
60 m)
Cost of each minor bridge shall be
determined on pro rata basis with respect
to the total linear length of the minor
(1) Minor Bridges 0.00%
bridges. Payment shall be made on the
completion of widening & repair work of
a minor bridge.
A.2 New /Reconstruction Minor
Bridges (length >6m and<60m).
(1)Foundation 14.69%
Cost of each minor bridge shall be
(2) Sub Structure (upto bottom of pier determined on pro rata basis with respect
5.88%
cap) to the total linear (m) of the minor
(3) Sub Structure (Pier Cap including bridges. Payment against foundation ,
pedestals or final lift and bracket 5.88% substructure, components of super
portion) structure shall be made on pro-rata basis
(4) Super structure (Castig and on completion of a stage i.e. not less than
11.75%
completion of girder, fit for launching) 25% of the scope of Foundation, Sub-
(5) Super structure (Launching of structure ,super structure component of
10.58%
girder and deck slab casting )
(6) Super-structure On completion of each bridge subject to completion of
super structure in all respects including atleast one span length..
wearing coat, bearings, expansion
joints, hand rails, crash barriers, road 2.94%
signs and marking excluding tests on
completion etc. Complete in all
respect.
(7) Approaches On completion of Payment shall be made on pro-rata basis
approach slab , backfilling of filter on completion of a stage i.e. completion
media , return wall including 2.94% of approaches in all respect and fit for
return/Retaining walls, complete in all movement of traffic for each Minor
respect . Bridge
(8) Protection Works on completion of
stone pitching, protection works 2.94% Payment shall be made on pro-rata basis
complete in all respect . on completion of a stage i.e. completion
of Guide Bunds, protection works and
(9) Guide Bunds and River Training
River training works in all respect for
Works on completion of guide bunds
1.15% each minor Bridge
and river training
works complete in all respect.
Payment shall be made on pro-rata basis
on completion of a stage i.e. completion
(10) Other Works (Test on completion) 1.18%
of Testings in all respect for each minor
Bridge
A.2 New /Reconstruction
UnderPass/Over pass (length >6m
and<60m).
(1)Foundation 8.46%
(2) Sub Structure (upto bottom of pier
3.39%
cap)
(3) Sub Structure (Pier Cap including
Cost of each Underpass/overpass shall be
pedestals or final lift and bracket 3.39%
determined on pro rata basis with respect
portion)
to the total linear (m) of the
(4) Super structure (Castig and
underpass/overpass. Payment against
completion of girder, fit for launching) 3.39%
foundation , substructure, components of
VUPs
super structure shall be made on pro-rata
(5) Super structure (Launching of
basis on completion of a stage i.e. not less
girder and deck slab casting ) only deck 8.47%
than 50% of the scope of Foundation,
slab for LVUP
Sub-structure ,super structure component
(6) Super-structure On completion of of each structure subject to completion of
super atleast one span length..
structure in all respects including 3.39%
wearing coat, bearings, expansion
joints, hand rails, crash
(7) Approaches of structures

7.1 RE panel casting 1.55% Unit of measurement will be sqm.


Payment will be made on completion of
7.2 Erection and back filling 2.48% 10% of total scope.

Unit of measurement will be linear


7.3 Coping Beam and friction
2.17% length.Payment will be made on
Slab/geocell completion
completion of 10% of total scope.
Cost of each underpass/overpass shall be
(8) Under Bridge works such as determined on pro rata basis with respect
1.69%
footpath , painting of RE wall etc. to the total linear length of the
under/overpass. Payment shall be made
on the completion of a
(9) Other Works (Test on completion) 1.69%
underpass/overpass.
B.1 Repair/Rehabilitation of existing
underpass/overpass
Cost of each underpass/overpass shall be
determined on pro rata basis with respect
underpass/overpass 0.00%
to the total linear length of the
under/overpass. Payment shall be made
on the completion of repair work of a
underpass/overpass.

1.3.3 Major Bridge (length >60m) works and ROB


Stage for Payment Percentage weightage Payment Procedure
1 2 3
A-1 Repair/Reahabilitation of major
bridges
Cost of each Major Bridge shall be
determined on pro rata basis with respect
to the total linear length of the Major
(1) Major bridge 0.00%
Bridges. Payment shall be made on the
completion of repair work of a major
bridge.
A.2-New Major Bridges
(1) Foundation 10.13%
(2) Sub Structure (upto bottom of pier
4.06%
cap)
(3) Sub Structure (Pier Cap including Cost of each major bridge shall be
4.06% determined on pro rata basis with respect
pedestals)
(4) Super structure (Castig and to the total linear (m) of the minor
8.12% bridges. Payment against foundation ,
completion of girder, fit for launching)
substructure, components of super
(5) Super structure (Launching of
structure shall be made on pro-rata basis
girder and 7.31%
on completion of a stage i.e. not less than
deck slab casting )
25% of the scope of Foundation, Sub-
(6) Super-structure On completion of
structure ,super structure component of
super structure in all respects including
each bridge subject to completion of
wearing coat, bearings, expansion
atleast one span length..
joints, hand rails, crash barriers, road 2.03%
signs and marking excluding tests on
completion etc. Complete in all
respect.
Payment shall be made on pro-rata basis
(7) Approaches On completion of
on completion of a stage i.e. completion
approaches including return/Retaining
2.03% of approaches in all respect and fit for
walls, stone pitching, protection works
movement of traffic for each Major
complete in all respect .
Bridge
(8) Protection Works on completion of
stone pitching, protection works 2.03%
Payment shall be made on pro-rata basis
complete in all respect .
on completion of a stage i.e. completion
(9) Guide Bunds and River Training of Guide Bunda and River training works
Works on in all respect for each major Bridge
1.46%
completion of guide bunds and river
training
Payment shall be made on pro-rata basis
on completion of a stage i.e. completion
(10) Other Works (Test on completion) 0.81%
of Testings in all respect for each major
Bridge
B-1 ROB
(1)Foundation 8.14% Cost of ROB shall be determined on pro
(2) Sub Structure (upto bottom of pier rata basis with respect to the total linear
5.43% (m) of the ROB. Payment against
cap)
(3) Sub Structure (Pier Cap including foundation , substructure, components of
5.43% super structure shall be made on pro-rata
pedestals)
(4) Super structure (Castig and basis on completion of a stage i.e. not less
18.99% than 25% of the scope of Foundation,
completion of girder, fit for launching)
Sub-structure
(5) Super structure (Launching of
10.85% ,super structure component of each bridge
girder and deck slab casting )
subject to completion of atleast one span
(6) Super-structure On completion of
4.34% length..
super
structure in all respects including
wearing coat,
(7) Approaches of structures

7.1 RE panel casting 0.92% Unit of measurement will be sqm.


Payment will be made on completion of
7.2 Erection and back filling 1.48% 10% of total scope.
Unit of measurement will be linear
7.3 Coping Beam and friction length.
1.29%
Slab/geocell completion Payment will be made on completion of
10% of total scope.On Completion of
(8) Other Works (Test on completion ) 1.09% testing of ROB
1.3.4 Flyovers
Stage for Payment Percentage weightage Payment Procedure
1 2 3
A-1 Flyovers
(1)Foundation 21.89%
(2) Sub Structure (upto bottom of pier
11.38%
cap) Cost of each Flyover shall be determined
(3) Sub Structure (Pier Cap including on pro rata basis with respect to the total
13.13%
pedestals) linear (m) of the minor bridges. Payment
(4) Super structure (Castig and against foundation , substructure,
17.51%
completion of girder, fit for launching) components of super structure shall be
(5) Super structure (Launching of made on pro-rata basis on completion of a
17.51%
girder and deck slab casting ) stage i.e. not less than 25% of the scope
(6) Super-structure On completion of of Foundation, Sub-structure ,super
super structure in all respects including structure component of each bridge
wearing coat, bearings, expansion subject to completion of atleast 50% one
joints, hand rails, crash barriers, road 4.38% span length.
signs and marking excluding tests on
completion etc. Complete in all
respect.
(7) Approaches of structures
7.1 RE panel casting 3.11% Unit of measurement will be sqm.
Payment will be made on completion of
7.2 Erection and back filling 4.98% 10% of total scope.
7.3 Coping Beam and friction Unit of measurement will be linear
4.36%
Slab/geocell completion length.
Payment will be made on completion of
(8) Other Works (Test on completion) 1.75% 10% of total scope.
On Completion of testing of ROB
1.3.5 Other works
Stage for Payment Percentage weightage Payment Procedure
1 2 3
Unit of measurement is linear length.
Unit of measurement is linear length.
Payment of each stage shall be made on
(1) PCC lining at slope,slope protection
4.82% pro rata basis on completion of a stage in
, Drain in Separator
a length of not less than 10 (ten) percent
of the total length. or 2 km whichever
being lower..
(2) Lined Box Drain with footpath 6.46% Unit of measurement is linear length.
Unit of measurement is linear length.
(3) Road signs, marking, km stones, Payment of each stage shall be made on
18.43%
safety device etc pro rata basis on completion of a stage in
(4) Project facilities 0.00% a length of not less than 10 (ten) percent
of the total length.
Payment to be made on completion of
a)Bus Shelter (34 nos.) 1.04%
each shelter on pro data basis.
Payment to be made on completion of
b) Rest areas (works as per Schedule B) 2.03%
each Rest Area on pro rata basis.
Unit of measurement is linear length.
Unit of measurement is linear length.
Payment of each stage shall be made on
c) Street Lighting including connection
3.72% pro rata basis on completion of a stage in
charges
a length of not less than 10 (ten) percent
of the total length including its
connection and illumination.
Payment to be made on pro-rata basis
d) High Mast Lighting 0.93% after completion of each highmast
including its connection and illumination.
e) Medical/traffic and vehicle aid post 0.00%
Payment to be made on completion of
(5) Junction improvement 18.88%
each junction on pro-Data basis.
(6) Safety and traffic management
during 0.00%
construction.
Unit of measurement is linear length.
Unit of measurement is linear length.
(7) Median/New Jersey type crash Payment of each stage shall be made on
5.99%
barriers including Anti Glare Device pro rata basis on completion of a stage in
a length of not less than 10 (ten) percent
of the total length.
Payment to be made on completion of
(8) Plantation , landscaping and each location on pro- rata basis.
5.08%
asthetic improvement works Plantation -10%
Landscaping - 90%
Unit of measurement is linear length.
Unit of measurement is linear length.
(9) Protection Work ( Retaining wall,
Payment of each stage shall be made on
Toe Wall, Stone Pitching, Parapet Wall 6.12%
pro rata basis on completion of a stage in
etc.)
a length of not less than 10 (ten) percent
of the total length.
Payment will be made as per below:50%
on arrival of complete material in all
respect and verification by AE.25% on
(10) Ramp Toll Plazas and ATMS 17.26%
completion of installation.25% on
completion in all respect and successful
testing.
(11) Incident Management System 1.07% Payment to be made on completion .
Unit of measurement is linear length.
Unit of measurement is linear length.
Payment of each stage shall be made on
(12) MBCB-Thrie Beam 6.80%
pro rata basis on completion of a stage in
a length of not less than 10 (ten) percent
of the total length.
Payment to be made on completion on
(14) Rain water Harvesting 0.58%
pro rata basis
Payment to be made on pro rata basis for
each duct laid across the project highway
(15) Utility Duct 0.79%
not less than 02 in numbers and complete
in all respect.
1.3.5 Shifting of Utility Services.
Stage for Payment Percentage weightage Payment Procedure
1 2 3
Shifting of Electrical & Water
Supply Utilities
(a) Electrical Utilities
Unit of measurement will linear length
and payment to be made on pro-rata basis
for shifted utility of atleast 10% of total
EHT Towers 18.39%
scope after submission of handing over
certificate by
Utility owning agency.
Unit of measurement will numbers and
payment to be made on pro-rata basis for
EHT crossings 16.20% shifted utility of atleast 10% of total
scope after submission of handing over
certificate by Utility
Unit of measurement will linear length
and payment to be made on pro-rata basis
HT/LT lines 23.17% for shifted utility of atleast 10% of total
scope after submission of handing over
certificate by
Unit of measurement will numbers and
11KV/33KV crossings 37.32% payment to be made on pro-rata basis for
shifted utility of atleast 10% of total
DTR shifting 4.92% scope after submission of handing over
certificate by Utility owning agency.