Schedule H PKG-3
Schedule H PKG-3
2 Proportions of the Contract Price for different stages of Construction of the Project Highway shall be as specified below:-
Weightage in
Item Stage for Payment Percentage weightage
% of CP
1 2 3 4
A- New 2/4 - lane realignment/
bypass (Flexible pavement) Excluding
approaches of Structures i.e. other
than TCS 3,3A &3B
(1) Site Clearance 0.09%
(2) Earthwork upto bottom of Subgrade 5.01%
(3) Subgrade Top 2.09%
(4) Sub-base Course (GSB/CTSB) 3.66%
(5) Non bituminous base course
6.93%
(CTB+AIL)
(6) Bituminous base course (DBM) 7.39%
(7) Bituminous Wearing course (BC) 6.17%
(8) Earthern Shoulder with slope
dressing in separator (Excluding PCC 0.67%
on top)
(9) Median dressing and drain 1.00%
B New 2/4 - lane realignment/
bypass (Flexible pavement) at
approaches of Structures i.e. TCS
3,3A &3B
(1) Site Clearance 0.06%
(2) Earthwork upto bottom of Subgrade 6.59%
Road works (3) Subgrade Top 0.81%
(excluding the road (4) Sub-base Course (GSB/CTSB) 1.42%
works in (5) Non bituminous base course
approaches of 2.70%
(CTB+AIL)
structures) (6) Bituminous base course (DBM) 2.87%
53.83%
including Culverts,
widening and repair (7) Bituminous Wearing course (BC) 2.40%
of culverts. (8) Earthern Shoulder with slope
including Culverts, dressing in separator and kerb
1.65%
widening and Channel(Excluding PCC on
top)
A.1 Repair/Rehabilitation of
existing Minor Bridges (length > 06
m and < 60 m)
(1) Minor Bridges 0.00%
A.2 New /Reconstruction Minor
Bridges (length >6m and<60m).
(1)Foundation 14.69%
(2) Sub Structure (upto bottom of
5.88%
pier cap)
(3) Sub Structure (Pier Cap including
pedestals or final lift and bracket 5.88%
portion)
(4) Super structure (Castig and
completion of girder, fit for 11.75%
launching)
(5) Super structure (Launching of
10.58%
girder and deck slab casting )
(6) Super-structure On completion of
super structure in all respects including
wearing coat,bearings, expansion joints,
2.94%
hand rails, crash barriers, road signs and
marking excluding tests on completion
etc. Complete in all respect.
(7) Approaches On completion of
approach slab ,backfilling of filter
Minor Bridges media , return wall 2.94%
(including Service includingreturn/Retaining walls,
road 15.77% complete in all respect .
bridges)/Underpass/ (8) Protection Works on
overpass completion of stone pitching,
2.94%
protection works complete in all respect
.
(9) Guide Bunds and River Training
Works on
completion of guide bunds and 1.15%
river training works complete in all
respect.
(10) Other Works (Test on 1.18%
completion)
A.2 New /Reconstruction
UnderPass/Over pass
(length >6m and<60m).
(1)Foundation 8.46%
(2) Sub Structure (upto bottom of
3.39%
pier cap)
(3) Sub Structure (Pier Cap including
pedestals or final lift and bracket 3.39%
portion)
(4) Super structure (Castig and
completion of girder, fit for 3.39%
launching)
(5) Super structure (Launching of
girder and deck slab casting ) only 8.47%
deck slab for LVUP
(6) Super-structure On completion of
super structure in all respects including
wearing coat, bearings, expansion
3.39%
joints, hand rails, crash barriers, road
signs and marking excluding tests on
completion etc. Complete in all respect.
(7) Approaches of structures
7.1 RE panel casting 1.55%
7.2 Erection and back filling 2.48%
7.3 Coping Beam and friction
Slab/geocell 2.17%
completion
(8) Under Bridge works such as
footpath , 1.69%
painting of RE wall etc.
(9) Other Works (Test on completion) 1.69%
B.1 Repair/Rehabilitation of
existing
underpass/overpass
underpass/overpass 0.00%
A-1 Flyovers
(1)Foundation 21.89%
(2) Sub Structure (upto bottom of
11.38%
pier cap)
(3) Sub Structure (Pier Cap including
13.13%
pedestals)
(4) Super structure (Castig and
completion of 17.51%
girder, fit for launching)
(5) Super structure (Launching of
girder and 17.51%
deck slab casting )
(6) Super-structure On completion of
Flyovers 5%
super structure in all respects including
wearing coat, bearings, expansion
4.38%
joints, hand rails, crash barriers, road
signs and marking excluding tests on
completion etc. Complete in all respect.
(7) Approaches of structures
7.1 RE panel casting 3.11%
7.2 Erection and back filling 4.98%
7.3 Coping Beam and friction
Slab/geocell 4.36%
completion
(8) Other Works (Test on completion) 1.75%