The attached is part of a series of training materials prepared via collaboration between
ADB consultants (led by Carsten Huttemeier and Myint Myint San, with additional technical
experts John Cracknell, Stephan Giebel, and John Larsen) and officials and school staff
from the Myanmar Ministries of Education and Industry.
For the Ministry of Education (Executing Agency for TA 8634) and Ministry of Industry.
This consultant’s report does not necessarily reflect the views of ADB or the Government concerned, and
ADB and the Government cannot be held liable for its contents. (For project preparatory technical
assistance: All the views expressed herein may not be incorporated into the proposed project’s design.
၊
-၁
Road Construction Competency-Based Modular Short Course
Skill Level-1
(Course Code‐TVETRC1000; Nominal Duration‐ 520 hours)
၂၀၁၇ခုနှစ်၊ဇန်န၀ါရီလ
ADB TA-8634 MYA: Skills Development for Inclusive Growth
(Finaced by the Japan Fund for Poverty Reduction)
-၁
Road Construction Competency-Based Modular Short Course
Skill Level-1
(Course Code‐TVERC1000; Nominal Duration‐ 520 hours)
ဤ
(၁) (semi-skilled worker)
၊ ၊
ဤ
(၁)
(၁)
/ (Learning
Outcomes- LO)
(Course Structure)
1
ဤ (၆) /
-
ှ
1
(Modules) - ၊
၊
( )
၊
၊၄
2
(Learning Outcomes- LO)
(၁) ၊ ၊ ၊
(၂) ှ
2
Learning Outcome (LO)- ၊
(၃)
(Module Code ‐RC1003A; Nominal Duration‐ 120 hours)
LO 1 -
LO 2 -
LO 3 -
(၄) ၊ ှ
(Module Code ‐RC1004A; Nominal Duration‐ 80 hours)
LO 1 -
LO 2 -
LO 3 - ှ
LO 4 - ှ
(၅)
(Module Code ‐RC1005A; Nominal Duration‐ 80 hours)
LO 1 -
LO 2 - ှ ှ
LO 3 -
LO 4 -
LO 5 - ှ
(၆)
(Module Code ‐RC1006A; Nominal Duration‐ 120 hours)
LO 1 -
LO 2 - ှ ၊
LO 3 -
LO 4 -
LO 5 - ှ
(၁)
၊ ၊
(Module Code -RC1001A; Nominal Duration- 80 hours)
၁
- ၄ ၏ ၁
- ၁
- ၂
- ှ ၄
- (Different forms of measurements) ၆
- ၤ ၈
- ၏ - ၁၀
- ၁၃
- ေေၤ ၊ ှ ၁၈
- ၁၈
- ၁၈
- ေေၤတ ၁၉
- ၂၁
LO3- ၂၂
ှ
- ၂၂
- ၂၃
- ၂၂
- ၂၂
- ၂၄
- ၂၈
LO 5- ၏ (Job Specifications) ၍ ၃၀
- ၃၀
- (Road materials) ၃၀
- ၃၃
- ၃၆
- ၃၆
References ၃၇
Road Construction CBMSC: Module 1- Read and Interpret Plans and Specifications
(၁)
၊ ၊
(Module Code – RC 1001A; Nominal Duration- 80 hours)
ဤေမာ်ဂျူဵတွင် ၊
၍ ၊ ွျ ှု၊ ၀ ။
အ ၊ ၄ ၏
၊ ှ ၊
၊ ၊
၊ ။
- ၄ ၏ ။
(ASSESSMENT CRITERIA)
၁.၁ (plans and
drawings) ။
၁.၂ ၏ ၊
။
၁.၃ / ၏ ၊
။
၁.၄ (job plans)၊ (specifications) ှ
1
Road Construction CBMSC: Module 1- Read and Interpret Plans and Specifications
၁။
- ။
2
Road Construction CBMSC: Module 1- Read and Interpret Plans and Specifications
(၁၄) (Protractor)
(၁၃)
(Triangle rule or Scale rule)
၂။
- ။
(၁)
(၂)
3
Road Construction CBMSC: Module 1- Read and Interpret Plans and Specifications
(၃) ၍
(၄) ၍
၂။
( ။)
A4 210x297
A3 297x420
A2 420x594
A3 594x841
A0 841x1189
4
Road Construction CBMSC: Module 1- Read and Interpret Plans and Specifications
(၁)
(၂)
5
Road Construction CBMSC: Module 1- Read and Interpret Plans and Specifications
၏
၁။
ပံုတြင္ျပထားေသာ ၏္ အတိုင္းအတာမ်ားသည္ အေဆာက္အဦ၏
မူလအတိုင္းအတာကို ေဖာ္ျပျခင္းျဖစ္သည္။
) Leader Line ( )
(mm)
(m) ။( ၊ ၁၀၀၀ =၁ )
(foot)၊ (inch)
။( ၊၁ = ၂၅.၄ )
(၃) ။ ၄ - ၊
၊ ။
6
Road Construction CBMSC: Module 1- Read and Interpret Plans and Specifications
(၁)
(meter-m) ။ -
၏
- ။
၏ -
2 x 7500 = 15000
2 x 4500 = 9000
၏ (Perimeter) = 24000 mm
or 24 m
( - / ၊
)
(၂)
(square meters-m²) ။ -
၏
-
။
။
- ၃၄ ၊ ၀.၅ ၊ ( )
( ) ၀.၆
။
( ) ၊ ။
7
Road Construction CBMSC: Module 1- Read and Interpret Plans and Specifications
။
(၁) (square) ၄ ။
၄ ။
(၉၀ ) ။
။
(၉၀ ) ။
(၂ (rectangle)
၄ ။
(square) ။ ။
(၉၀ ) ။
။
(၃) (Triangle)
၃ ။
၃ ၁၈၀ ။
၍၃ ။
8
Road Construction CBMSC: Module 1- Read and Interpret Plans and Specifications
(ဃ) (Circles)
- ၂၀ ။
၀ (Radius) = 20m ၊ π= 3.142
= π r²
= 3.142 x 20 x 20
= 1256.8m²
9
Road Construction CBMSC: Module 1- Read and Interpret Plans and Specifications
ေနာက္တစ္နည္းမွာ ၄င္းပံုမ်ားကိုၾတိဂံပံုမ်ားအျဖစ္ခဲက
ြ ာ
ဧရိယာမ်ားတြက္ျပီးေနာက္ ယင္းဧရိယာမ်ားေပါင္းျခင္းျဖစ္သည္။
၏ -
- ှ ှ ှ
၍ ှ ။
10
Road Construction CBMSC: Module 1- Read and Interpret Plans and Specifications
( ) ဂဳ ၏
(၁)- ဂ ၏ ၄ ၏ ဧ ှ
ှ ။
- ဂ ၏ ။
( = 12 cm3)
( ) ၏
(၂)- ၏ ၏ဧ ။
၏ ၏ဧ ှ ၂ ှ ှ
။
ၾတိဂံ၏ဧရိယာ= ၁/၂ x အေျခ x အျမင့္
=1/2 x b x h (သို့) 1/2 bhH
=1/2 x 4 x 6 = 12 cm2
ပရစ္ဇင္တံုး၏ထုထည္ = ၾတိဂံ၏ဧရိယာ x ၾတိဂံ၀ခုၾကားရွိအျမင့္္
V =1/2 x b x h x H (သို့)
V =1/2 bhH
V= 12 x 10= 120 cm3
- ၏ ။
( = 96 cm3)
11
Road Construction CBMSC: Module 1- Read and Interpret Plans and Specifications
( ) ၏
(၃)- ၏ ၏ဧ ။
၏ဧ ှ ၂ ှ ှ
။
၏ဧ = π x R2
= 3.142 x 32
= 28.278cm2
၏ = ၏ဧ x ၂ ှ
= 28.278 x 5
= 141.39 cm3
= 141 cm3
(ဃ) ၏
(၄)- ၏ ၏ဧ
။ ၏ဧ ှ ၂ ှ
ှ ။
၏ဧ = x ှ
၏ ှ
= 5 x (4+10)
2
3
= 35 cm
၏ = ၏ဧ x ၂ ှ
V = 35 x 8
= 280 cm3
- ၏ ။( = 134 cm3)
12
Road Construction CBMSC: Module 1- Read and Interpret Plans and Specifications
(Pythagoras’ Theorem)
။
-c ၏ ။ a b ။
၏ ။
၏
(၁) ၀ ၊ ၏
(၁)
13
Road Construction CBMSC: Module 1- Read and Interpret Plans and Specifications
(၂)
(၂)
MN ။M MO ။
၍ တူညီေသာအကြာအေှးျဖင့္ MO P, Q, R ။
R N ။ RN QQ PP ။
(၃)
BAC ။
။
A ။
AC AB E F ။
၎ ။
E F D ။ AD
။
၎ BAC ။ CAD
BAD ။
14
Road Construction CBMSC: Module 1- Read and Interpret Plans and Specifications
(၄)
။
။
၍ ။
။
(၄)
(၅)
P AB ။
0 ၍ P ၍ ။
။
Q ၍ QR ။
(၅)
15
Road Construction CBMSC: Module 1- Read and Interpret Plans and Specifications
(၆)
AB P ။
(၁) P ၍ ၀ R1 ၀ AB GH ။
(၂) ၍ ၀ R2 G H ၍ ၀ J ။
(၃) PJ ။
(၆)
(၇)
၃ L1,L2,L3 ။
L3 ၍AB ။ A L1 ။
B L2 ။ C ။
A C,B C ။
16
Road Construction CBMSC: Module 1- Read and Interpret Plans and Specifications
(၈)
။
၍ ။
၍ ။
၎ ။
(၉)
၏ ။
OD C၌ ။
C ၍CA AE ။A ၍AE EB
။
AB ၎ ။
17
Road Construction CBMSC: Module 1- Read and Interpret Plans and Specifications
LO 2- ။
၂.၁
၂.၂ ွန်ဵမျ ၊
။
စေကးမ်ား၊ သေကၤတမ်ားႏွင့္ အတိုေကာက္မ်ား
စေကးျဖင့္ဆေ
ြဲ သာပံုမ်ားကို နားလည္ေစရန္ ပံုဆြရ
ဲ ာတြင္စေကးအသံုးျပဳတတ္ေစရန္
လမ္းတည္ေဆာက္ေရးလုပ္ငန္းမ်ားတြင္အသံုးျပဳေသာသေကၤတမ်ား ၊ အတိုေကာက္မ်ား ႏွင့္
အတိုင္းအတာမ်ားကိုဖတ္တတ္ေစရန္
၁။ (Scales)
/ ၍ ဟ ဓ ။
အေဆာက္အဦ/လမ္းပံုမ်ားေရးဆြရ
ဲ ာတြင္ေျမျပင္ေပၚတြင္ရွိသည့္အရြယ္အစားအတုိင္းပံုဆဲစ
ြ ာရြက္ေပၚတြင္ဆြရ
ဲ န္
မျဖစ္နုိင္ပါ။ထို့ေၾကာင့္ပံုဆစ
ြဲ ာရြက္ေပၚတြင္လြယ္ကူစြာဆြန
ဲ ုိင္ရန္စေကးကိုအသံုးျပဳရသည္။
မူလအရြယ္အစားထက္ ခ်ံဳ႕ဆြပ
ဲ ါက (scale down) ။ ၏
(scaleoff) ။
ံးမ်ားေသာ စေကးမ်ားမွာ-
Elevations 1:100 or 1:50
Sections 1:100 or 1:50
Location 1:5000
Block/Site plans 1:500 or 1:200
Details 1:20, 1:10, 1:5, 1:2 or 1:1
၁။
)၊ (vernier scale)
ပံုအရြယ္အစား
:=
မူလအရြယ္အစား
- = ၁၀
= ၂၀ =၂၀၀၀
၁၀ စင္တီမီတာ
= = ၁ ၂၀၀
၂၀၀၀ စင္တီမီတာ
။ ။working drawing ။
18
Road Construction CBMSC: Module 1- Read and Interpret Plans and Specifications
၂။ (Symbols)
(၁) (Roadway markings)
၊ ၊ ။
၊ ၊ ။
၊ ။
(solid line) (broken line) ။
။
။
၀
၀ ။
တဆေ်တည်ဵဆွဲေသာအ၀ါေရာင်မျဥ်ဵ
အ၀ါေရာင်မျဥ်ဵအစေ်လိုင်ဵနှငအ
်ဴ ြဖူေရာင်
မျဥ်ဵအစေ်လိငု ်ဵ
19
Road Construction CBMSC: Module 1- Read and Interpret Plans and Specifications
။
။
အဖ
ြ ူေရာင်ြမာဵညွှန်ြပေသာဦဵတည်ရာ
လမ်ဵေေ
ေ ာင်ဵမျာဵ
(Stop Lines)
။ ( )
။
(Cross walks)
။
၊ ။
။ ၏
။ ။
20
Road Construction CBMSC: Module 1- Read and Interpret Plans and Specifications
(Dip or Bump)
(dip) ။
(Abbreviations)
(1) AC = Asphalt concrete
(2) BM = Bench Mark
(3) CL = Centre line
(4) e = Super elevation
(5) M = Meter
(6) N = North
(7) NGL = Natural Ground Level
21
Road Construction CBMSC: Module 1- Read and Interpret Plans and Specifications
LO 3- (Site Plan) ။
၃.၁ ၏ ှ ှ
၃.၂ ၏ ှ
၃.၃ ၏ ၊၀ ၊ ၊
) ၊
LO 4- (Project Requirements)
။
၁။
-
- ၏ ၊
(၄) ။
(၁) / (Plan View)
။ (solid line)
ှ (A )။ B ှ C (dash and dotted
lines) ှ ှ ှ ။D( )
။ ၏
( ) ၁၀၀ ( )၊ ၂၀
( ) ။
22
Road Construction CBMSC: Module 1- Read and Interpret Plans and Specifications
(E )။
(F G )။
( (H I )။
23
Road Construction CBMSC: Module 1- Read and Interpret Plans and Specifications
၂။
(၁) (RIGHT OF WAY)
။
၌ ၊
။
24
Road Construction CBMSC: Module 1- Read and Interpret Plans and Specifications
(၅) (SHOULDER)
၏ ။
(၆) (SIDE SLOPE)
၏ ှ
( ) ၍ ၌ ။
(၇) ( ) (BERM ROAD)
။ ၌
။
(၈) (ROAD SIDE DRAIN)
၍ ၊
၌ ၍ ။
၎ ၌ ၊ (PLATFORM)
။
-၁
26
Road Construction CBMSC: Module 1- Read and Interpret Plans and Specifications
-၂
-၃
(၉) (SUPER ELEVATION)
27
Road Construction CBMSC: Module 1- Read and Interpret Plans and Specifications
၃။
၁ subgrade)၊ ၂ sub-basecourse)၊
(၃ base course) ှ ၄ surfacing or
။ sub-b ။
(၁) (subgrade)
(subsoil)
(subgrade) ။
။ (Road Formation)
(Highest Flood Level) ၃
။ ၍
။
(Camber) ။
(၂) / (Sub-base course)
၌
၃ ၆ ၊ ၊ ၊ ၊
၊ ၊ Ashes, Clinker, ။
။ ၍ (sub-base)
။
၌ (subsoil drainage)
၎
၌ (subbase) ။
- ။
။ ၍ ၏
၏
။ ။
28
Road Construction CBMSC: Module 1- Read and Interpret Plans and Specifications
29
Road Construction CBMSC: Module 1- Read and Interpret Plans and Specifications
LO 5- (Job Specifications) ၍
၅.၁ ၊ ၊
၅.၂ ၏ ၊
၅.၃
(Road materials)
၌ -
(၁) (Earth) (၄) (Kanker) (၇) (Deelone)
(၂) (၅) (Laterite) (၈) (Bitumen)
(၃) (Sand) (၆) (Shingle/Gravel) (၉) (Cement)
(၁ (Earth)
၁ ၁ ။
၁ ၁
၁ ။၎ -
ဂျင်ဵေေျာေ်ေ ြမ
ေမ
ြ နီ
ေေျာေ်စရစ်ေုန်ဵေမ
ြ တို့ ြဖစ် ေေသည်။
(၂)
(၃) ။
၎ -
( ) (Igneous Rock)
( ) (Sedimentary Rock)
( ) (Metamorphic Rock)
။
( ) (Igneous Rock)
(Lava) ှ
။
- (Granite) ။
30
Road Construction CBMSC: Module 1- Read and Interpret Plans and Specifications
( ) (Sedimentary Rock)
ှ ၊ ှ
။ (Sand
Stone)၊ (Lime Stone ) ။
( )
၊ ၊
။
(marble) (Slate ) ။
(၃) (Sand)
၊ ၊
၊ ။
။ ၎ -
( ) (pit or quarry sand)- ။
( ) (river sand)- ။
(sea sand)- ။
(crushed stone)- ၊ ။
(၄) / (Kanker)
၌ ။ ၍
။ (kanker) ။ ၊
။
၍ ၊
။
။
၏ ၊ ၊
၏ ။
(½ʺx½ʺ)
၍ ။
(၅) (Laterite)
၍ ၌ ၍
။ ၌ ။
။
ှ ။ ၌ ၊ ၊
၌ ။
31
Road Construction CBMSC: Module 1- Read and Interpret Plans and Specifications
(၆) (Shingle/gravel)
။ ။
။ ၍
။ ။
၏ ။
၊ ။
(၇) (deelone)
၌ ။
။ ၍ ၃" ၄"
၍ ၍ ။
(၈) (bitumen)
(၂) ။ (hot
application bitumen) (cold application bitumen) ။
(solid) ။
။ ၎ (pure bitumen)
။ ၃၅၀ ။
(၁၀) ။
၅% ၍ ။ ၎
(seal coat) ၊ (prime coat) ။
။
။ ၎ (cold emulsion)
(cut back bitumen ) ။
(cold emulsion)
။
။
(cut back bitumen)
၊ ၊
။ ၊
၊
၍ ။
(၉) (cement)
။
၁၇၀ (British Standard Seive no.-170) ။၁
32
Road Construction CBMSC: Module 1- Read and Interpret Plans and Specifications
၉၄ ၍ ။
။
၍ ၍
။ ၍ ၍
။
(tension)
(compression) ။ ၍
၍ (initial setting time) ၁၀ ၍ ။ (Final
setting time) ၍ ။ ၁၁၂
(၅၀ ) ။
၊ ။
၌ ( ) ၍
။၎ (Soil Cement
stabilization) ။
(၆) ။
( ) ( )
၊ ၍
။
(၆) ။
၊ ၊
။
( (Earth Road)
၌
၍
။
33
Road Construction CBMSC: Module 1- Read and Interpret Plans and Specifications
34
Road Construction CBMSC: Module 1- Read and Interpret Plans and Specifications
( ) (CONCRETE ROAD)
၊ ၊ ( ) ၍
။
35
Road Construction CBMSC: Module 1- Read and Interpret Plans and Specifications
ှ ၍ စနစ်တေျ အချိန်မီ ( )
။
၁။(၉ x၆
။
(၂" x ၄") ၄" ၊ (၁" x၂") ၂" ၊ chipping(၃/၄)" ၊ (၁/၄)"
၂။(၉ x ၆ x၆ )
။(၁ ၂ ၄)
36
Road Construction CBMSC: Module 1- Read and Interpret Plans and Specifications
၏
ြမန်မာအေခါ် မေ်ထရစ် အေခါ် အဂလိ
င်္ ပ် အေခါ် ၁ တန် (၄၀ေပရှည်)
၁ေျပ်ခလ
ွဲ ဵုဳ 38 mm 1 ၉ေချာင်ဵ
2
၁ေျပ်တစ်မတ် 30 mm 1 ၁၄ေချာင်ဵ
4
၁ေျပ်လဵုဳ 25 mm 1 ၂၁ ေချာင်ဵ
မူဵတင်ဵလုဵဳ 24 mm 7/8 ၂၃ ေချာင်ဵ
References
( ၊ ၁၉၈၂) ။
37
(၂)
ှ
- ၁
၁
၂
(၁) (Hard Hat, Helmet) ၂
(၂) (Safety Boots, Safety Shoes) ၃
(၃) (Safety Gloves) ၃
(၄) (Safety Glasses, Goggles) ၄
(၅) (Ear Plug, Ear Muffs) ၄
(၆) ၊ (Dust Mask) ၅
(၇) (Respirator) ၅
၅
၊ ၆
ဳ (၃) ၈
/ ၉
၉
၁၀
LO 2- ၁၁
၁၂
ု ၁၂
ှ ၁၂
ှ ၁၃
၁၅
၁၈
LO 3-
ှ ၁၉
၁၉
ဴ ှ ၁၉
ှ (Clean Up) ၂၀
၂၂
References ၂၃
Road Construction CBMSC: Module 2- Follow OH&S policies and procedures
(၂)
ှ
ဤေမာ်ဂျူဵတွင် (OH&S) ၊
၊ ွျ ှု၊ ၀ ။ အ
၊ ၀ ။
LO 1- ။
၁.၁ ၊ /
၀
၁.၂ ၊ ၀ ၊
၊ (OH&S)
၊ ှ ဴ
၁.၃
၀ (PPE) ၊
၁.၄ ၏ ှ
။
၁.၅ ၊
။
၊ ။
။
ုရ (PPE)
ါ် (Personal Protective Equipment)
၀ ။
(Helmet, Hard Hat)
(Safety Boots, Safety Shoes)
(Hand Gloves)
(Safety Glasses, Goggles)
1
Road Construction CBMSC: Module 2- Follow OH&S policies and procedures
(Face Shield)
၊ (Ear Plug, Ear Muffs)
၊ (Dust Mask)
(Respirator)
(High Visibility Waistcoat)
။
၀ ၀ ။
၊ ၊
(Safety Shoes) ၏။
၏ (၂) ၏။
။
2
Road Construction CBMSC: Module 2- Follow OH&S policies and procedures
။ ။
။
3
Road Construction CBMSC: Module 2- Follow OH&S policies and procedures
ှ ၀ ။
။
။
။
4
Road Construction CBMSC: Module 2- Follow OH&S policies and procedures
(၇) ှ (Respirator)
(Confined Space) ၊ ၊
၊ ၌
။ ၀ ှ
ှ
၀ ။ ၀
၊
။ ှ
ှ ၀ ။
၀ ှ
၀
၀ ။
၀ ။ -
၊ ၌ ၀ ။
၀
။
၍ ၀ ။
၀ ။ -
( )
။ ၊
။ ၍
5
Road Construction CBMSC: Module 2- Follow OH&S policies and procedures
။ ၏
။
၊
၌ ၊
။ ၊ ၀ ၊
၏။
‘ ’ ၏။
။ ။ -
။
6
Road Construction CBMSC: Module 2- Follow OH&S policies and procedures
၀ ‘ ’ ။
။ ။
‘ ’ ၏။ ‘ ’ ှ၍
။
။
။
7
Road Construction CBMSC: Module 2- Follow OH&S policies and procedures
ဳ (၃)
၂။ ေကာင်ဵစွာြမင်ရသည်ဴေနရာတွင် ေနပါ။
စက်ယန္တရာဵေမာင်ဵနှင်သူမျာဵက နိုင်ေသာေနရာ (blind spots) မျာဵရှသ
ိ ည်။
၎င်ဵတိ့ု သည် အနီဵကပ်ေနရာမျာဵကိုသာ အာရုထ ဳ ာဵေလဴ ှ သည်။ ထို ဴ
PPE ။
စကယန္တရာဵ ၏
။
ယန္တရာဵ
နိုင်ေသာ ။
ယန္တရာဵ ၏
စက်ေမာင်ဵသူ၏ မျက်လဵုဳ ကို
ည်ဴြပီဵ စက်ေမာင်ဵသူက မိမိကို ြမင်
ေသချာပါေစ။
Source- Wayne State University
8
Road Construction CBMSC: Module 2- Follow OH&S policies and procedures
၃။ လုပ်ငန်ဵခွင် ။
လုပ်ငန်ဵခွင် ၊ ၊
၍ ၊ စက်ယန္တရာဵ/ ၊
။ လုပ်ငန်ဵခွင် ၊
PPE ။
ှ ။
ှ ။
( )
။ ( - ှ့ ၊ ႊ ှ ၊
) ှ ။
ှ့ ၊ ႊ ှ
ှ့ ၅ မိငု ် ှ ၊ ှ
၌ ။
(၁) ( )
၀ ၊
9
Road Construction CBMSC: Module 2- Follow OH&S policies and procedures
(၂)
။
(၃) ၏ ၊၊ ၃ ၊
၁၂ ၍ ။
(၄) ၅ ၍
။
(၅) ၃၀၀ ၁၀၀၀ ၊
၁၀၀ ၃၀၀ ။
(၆) ၍ ။
။
၁။ ၏
။
( ) ( ) ( )
၂။ ။
( ) ( ) ( )
၃။ ၏ ။
( ) ( ) ( )
၄။ ၍ ။
( )၃ ( )၄ ( )၅
၅။ (၅) ။
၆။
(၂) ။
10
Road Construction CBMSC: Module 2- Follow OH&S policies and procedures
LO 2 -
၂.၁ ၊ ှ
ဴ
၂.၂ (OH&
၊ ှ ဴ
၂.၃
ှ
၂.၄ ၊ /
(OH&S)၊ ၊ ှ
ု
ု (၅) ။
၁။
( / / / / )
။
၂။
လမ်ဵခင်ဵေကျာက်မျာဵခွဲရာတွင် ြဖစ် လာေသာ ေကျာက်စ ေကျာက်နမျာဵလွင်ဴစင်ထိမှန် ြခင်ဵ၊
၌ လွင်ဴစင် ။
၃။
၊ ။
၄။
။
ေလာင်စာဆီ (ဒီဇယ်၊ဓာတ်ဆီ)မျာဵ ေလာင်ကျွမ်ဵ ြခင်ဵ။
ကျုိချက်ေနေသာ ကတ္တ ရာပုဳဵမျာဵထဲသို့ မီဵ၀င်ေရာက်ေလာင်ြခင်ဵ။
ေလအိုဵ၊ မီဵအိုဵမျာဵေပါက်ကွဲြခင်ဵ။
၊ ။
၅။
၊ ။
ှ
၁။
။
၊ ။
11
Road Construction CBMSC: Module 2- Follow OH&S policies and procedures
၂။
လမ်ဵခင်ဵေကျာက်မျာဵခွဲရာတွင် ြဖစ် လာေသာ ေကျာက်စ ေကျာက်နမျာဵ
လွင်ဴစင်ထိမှန် ြခင်ဵ (PPE) ။
၌ မ
။
၃။
၊ PPE
။
၄။
ေလာင်စာဆီ (ဒီဇယ်၊ဓာတ်ဆီ)မျာဵကို ေအဵ၍ေခ ြ ာက်ေသွ့ေသာေနရာ၌ စနစ်တကျ
ထာဵရန်။
ကျုိချက်ေနေသာ ကတ္တ ရာပုဳဵမျာဵထဲသို့ မီဵ၀င်ေရာက်ေလာင်ြခင်ဵ မဖ ြ စ်ေစရန်
ကတ္တ ရာပုဳဵမှထွက်လာေသာ မီဵခိုဵအေရာင်ကို ြကည်ဴရမည်။ အပ ြ ာေရာင် မီဵခိုဵမျာဵ
ထွက်လာပါက မီဵေလာင်ေတာဴမည်အ ဴ ေခ ြ အေနဖ ြ စ်ေသာေကြ ာင်ဴ မီဵေလှောဴရမည်။
၊ ။
ှ
သင် ြကာဵရသည်ဴရည်ရွယ်ချက်မျာဵ
။
။
။
၊
၊ ၊ ၊ ၊ ၊
။
။
။
၊
။
။
၊
။
12
Road Construction CBMSC: Module 2- Follow OH&S policies and procedures
( ) ( )
( ) ( )
( ) ( )
(ဃ) ( )
( ) ( ) ။
၍
။
( ) ၊
၊ ။
( ) ( )
၊ ။
( ) ၊ ၊
။
(ဃ)
။
( )
( ) ၊
( ) ၊
(ဃ)
၍
မ်ဵ သည်။
13
Road Construction CBMSC: Module 2- Follow OH&S policies and procedures
(က) ဆ ( ှစ )
ပုတ
ဳ ွင်ြပထာဵသည်အ
ဴ တိငု ်ဵ စနက်တဳကိုြဖုတ်ပါ။
( )
ကစ က စ င င
က က င
က က င င င
စ စ
(ဂ) က
က စက င စ က ငစ စ
က င စ စ
က င င က င စ
က က င စ စ
(ဃ) က
က ဆ က င င ဆင
င (၃၀) င
င စ င င က က င
ကဆ င စ စ
14
Road Construction CBMSC: Module 2- Follow OH&S policies and procedures
ှာင်ရန်၊ ေဆာင်ရန် ။
။
15
Road Construction CBMSC: Module 2- Follow OH&S policies and procedures
ဓာတ် ြကိုဵမျာဵကို
ေမ
ြ ြကီဵ (သိ့ု ) ြကမ်ဵြပင်ချပ
ီ ီဵ
မသွယ်တန်ဵပါနှင။်ဴ
16
Road Construction CBMSC: Module 2- Follow OH&S policies and procedures
ပျက်စီဵ ချို့ယွင်ဵေနေသာ
ဓာတ် ြကိုဵမျာဵကိုမသုဳဵပါနှင်ဴ။
လှေပ်စစ်အန္တရာယ်သတိေပဵချက်မျာဵကို
လိက
ု ်နာပါ။
17
Road Construction CBMSC: Module 2- Follow OH&S policies and procedures
။
၁။ ကတ္တ ရာကျိုချက်ရာတွင်_________မီဵခိုဵမျာဵထွက်လာပါက မီဵေလာင်ေတာဴမည်ဴ
အေခြ အေနဖ ြ စ်ေသာေက ြ ာင်ဴ မီဵေလျာဴရမည်။
( ) ( ) ( )
၂။ __________ ။
( ) ၁၉၉ ( ) ၁၉၁ ( ) ၉၁၉
၃။ ၊ __________ ။
( ) ( ) ( )
၄။ ___________ ။
( ) ( ) ( )
၁။ ။
၂။ ။
၃။
။
18
Road Construction CBMSC: Module 2- Follow OH&S policies and procedures
LO 3- ။
စစ ဆ က စ
၃.၁
၃.၂ ၊
၀
၃.၃
၊
ဴ ှ
။
19
Road Construction CBMSC: Module 2- Follow OH&S policies and procedures
ှ (Clean Up)
။
၁.
။
၂. / ။
၃. ၏ ။ ဴ ှ ။
၄. (spirit level ) ။
။ spirit level (bubble)
။
၅. ။
။
၆. ၏
။
၇. ။
၈. ။
၉. ၊ ၊
။
၁၀. ၏
။
20
Road Construction CBMSC: Module 2- Follow OH&S policies and procedures
21
Road Construction CBMSC: Module 2- Follow OH&S policies and procedures
။
၁။ __________ ။
၂။ __________ ။
၃။ _________ ။
၄။ ၏ _________ ။
၅။ __________ ။
၁။
။
၂။ ။
22
Road Construction CBMSC: Module 2- Follow OH&S policies and procedures
References
( ၊ ၁၉၈၂) ။
)( ၊ ၂၀၁၃)
) ။
ှ -
https://sites.google.com/site/myanmarurbancities/improve-your-
driving-practice/traffic-1
23