Professional Documents
Culture Documents
Construction Management 1.0
Construction Management 1.0
Management
AR. ARJEE LOUIE DC. JIMENEZ, uap, rmp
Grading System
Passing Grade = 70.00 (zero based)
3 Grading Period:
Prelims (30%)
Midterms (30%)
Finals (40%)
Total of 100%
Midterm Grade
1/3 = Midterm Exam
2/3 = Class Standing (Quizzes, Assignments, Recitations, etc.)
SCOPE
VOLATILITY
05 POST CONSTRUCTION
OWNER
TEAM SUB-
CONTRACTOR
OWNER TEAM
An individual or business entity who
commissions and funds a project.
Public or private owners, owners
advisors, consultants, occupants, utility
service providers, and authorities having
jurisdiction.
AR. ARJEE LOUIE DC. JIMENEZ, uap, rmp
Supply Chain and Project Team Composition
DESIGN TEAM
The person or firm hired by an
owner to manage project design
and technical coordination between
engineering disciplines.
Architects, engineering consultants,
and specialty consultants.
AR. ARJEE LOUIE DC. JIMENEZ, uap, rmp
Supply Chain and Project Team Composition
CONTRACTOR TEAM
The team hired by an owner to
oversee day-to-day construction
operations and subcontractor
productivity during construction.
Contractors and subcontractors.
SUPPLIER TEAM
Manufacturers, distributors,
suppliers, and fabricators.
OWNER TEAM
Provide information to both designer and contractor
Pay for fees associated with the work
Make payments to the contractor. It has to be timely
Right to stop the work for a good and just cause
Right to carry out the work on the contractor's behalf
when it becomes necessary (not always due to the fault
or failure of contractor)
AR. ARJEE LOUIE DC. JIMENEZ, uap, rmp
Supply Chain and Project Team Composition
OWNER TEAM
Right to perform construction when it becomes
necessary
Right to award single or multiple separate contracts
Right to clean the project site
Right to beneficial occupancy
Right to terminate for convenience (ex. Emergency that
results to reallocation of resources)
Right to terminate for a cause
AR. ARJEE LOUIE DC. JIMENEZ, uap, rmp
Supply Chain and Project Team Composition
DESIGN TEAM
Translation of Owner's requirement, PPD and BOD to an
actual design
Develop and furnish both contractor and owner the
Design and Specifications
Respond to all queries RFI, Submittal, Clarification,
Change Orders, etc.
Observe the work
AR. ARJEE LOUIE DC. JIMENEZ, uap, rmp
Supply Chain and Project Team Composition
DESIGN TEAM
Certify and recommend
Right to receiving payments due him/her
Right to interpret contract documents (design and
specs)
Right to inspect work
CONTRACTOR TEAM
Review contract documents
Follow procedures in the PPM/CAG
Deploy competent personnel, supervisory and
management staff/ professionals
Site management
Maintenance of records
Indemnify and hold harmless the owners and staff
AR. ARJEE LOUIE DC. JIMENEZ, uap, rmp
Supply Chain and Project Team Composition
CONTRACTOR TEAM
Furnish copy of bonds to the owner
Manage field risks
AS EARLY AS POSSIBLE
Bid-Build (DBB)
Consultants
Engineer
Suppliers
Construction
Product representatives SUB-
Contract
BIDDER
CONTRACTOR
SUPPLIERS Procurement
Bid-Build (DBB)
Consultants
Engineer
Subcontract
SUCCESSFUL
CONTRACTOR
BIDDER
SUPPLIERS Procurement
Bid-Build (DBB)
Consultants
Engineer
SUPPLIERS Procurement
Owner Build
Consultants
Engineer
Product representatives
Construction
program
Owner Build
Consultants
Engineer
Owner Build
Consultants
Engineer
coordination Construction
Adversarial relationships fostered CONTRACTOR Contract SUPPLIERS
At Risk (CMAR)
Consultants
Engineer
Owner
Architect/ Engineer OWNER
Contractor TEAM
Subcontractors
Suppliers Construction
Contract
Product representatives
SubContract SubContract
At Risk (CMAR)
Consultants
Engineer
At Risk (CMAR)
Consultants
Engineer
SubContract SubContract
SUB- CONTRUCTION SUB-
CONTRACTOR MANAGER CONTRACTOR
Procurement
Purchase
Architect/ Engineer
Construction Contract SUB-
Consultants
CONTRACTOR
SubContract
Contractor
Subcontractors Architect/
CONTRACTOR
Suppliers Engineer
SUB-
Decision to use D-B Consultants Procurement CONTRACTOR
SUPPLIERS
Reduced disputes
Can cut time/cost Architect/
CONTRACTOR
Early involvement of Engineer
Purchase
SUPPLIERS
required
Potential for quality to be Architect/
CONTRACTOR
compromised Engineer
SubContract
SUB-
Consultants Procurement CONTRACTOR
Purchase
SUPPLIERS
Unique
Temporary
Limited Resources
Involves People
CREATION OF VALUE
Routine
Repetitive
Goes on as long as the organization exists
MAINTENANCE OF VALUE
AR. ARJEE LOUIE DC. JIMENEZ, uap, rmp
Project vs Operation
PERMANENT
TEMPORARY
(ON GOING)
DELIVERS THE
DELIVERS
SAME OUTPUT
UNIQUE OUTPUT CONTINUOSULY
INNOVATIVE IN REPETITIVE
NATURE IN NATURE
EXISTS
EXISTS BEFORE A
AFTER A
PRODUCT
PRODUCT
ENHANCES THE
PERFORMANCE
TRANSFORMATIONAL
OF NORMAL
PRACTICE
AR. ARJEE LOUIE DC. JIMENEZ, uap, rmp
1.7 PROJECT, PROGRAM,
PORTFOLIO MANAGEMENT
tangible
relatively easy to describe
relatively easy to define
relatively easy to measure
a group of projects
grouped to improve control
if a specific project fails to deliver the expected results, a
new project may be spawned
1.0 Project 2.0 Project 1.0 Project 1.0 Project 2.0 Project
MONITORING &
INITIATION PLANNING EXECUTION CLOSING
CONTROL
Risk Management
1. identify the risks
INITIATION 2. Quantify risks
3. Prioritize
4. Construct action plans