L-1 No.

16 16 May'15

EXAMINATION NO.16

TECHNICAL EXAMINATION QUESTION SHEETS

CATEGORY Mechanical (HVAC)


GRADE Level - 1

CONTENTS :

1. Option <30points>

. OP-1; OP-2; OP-3; OP-4; OP-5;

TIME SCHEDULE :

15:30 to 17:30

NOTE :

1. Check this Examination question sheets and confirm the category and grade
are proper for those which you are going to take.

2. This Examination question sheets consists of 15 sheets.


Confirm you have all the sheets.
Inform to Observer immediately when you do not have all the sheets.

3. Write your examinee's NO. onto this cover and all the answer sheets
at first. If missing, it will be considered no answer written

4. Optional question
<Option -1> to <Option -5> are optional questions.
Select and answer Three (3) questions in five questions.
If more than three (3) questions are answered, the lowest score questions
will be counted.

4 All the question sheets should be given back to the Observer after finish.

5 No examinees will be allowed to leave the examination centre before 30 min.


after starting of the examination.

EXAMINEE'S NO.

Date : 16 May 2015

1/18
L1 No.16 16/May/2015
Level - 1 Mechanical (HVAC )
No.
Option Option 1

< Question 1 > < 5 points >

Shown below is a schematic diagram of booster pump set consisting of two(2)


identical pumps, a pressure tank, control panel, and the interconnecting pipeworks.

Control
Panel
To Distribution
System 100mm dia. x 15m L

50mm dia. x 3.0m L

80mm dia. x 2m L
P P

P P

Max Water
100mm dia x 5m L

Level

Underground
Water Tank

Min Water
Level

Q1 Prepare the Bill of Quantity of valves and gauges as shown on the above < 2.5 points >
schematic diagram.

< Answer >

1) Isolating valve/ gate valve, 80mm dia. 2 pcs


2) Isolating valve/ gate valve, 50mm dia. 1 pc
3) Check valve, 80mm dia. 2 pcs
4) Y-Strainer, 100mm dia. 2 pcs
5) Foot valve with strainer, 100mm dia. 2 pcs
6) Flexible connection, 100mm dia. 2 pcs
7) Flexible connection, 80mm dia. 2 pcs
8) Concentric reducer 2 pcs
9) Eccentric reducer 2 pcs
10) Pressure gauge 4 pcs

Page 頁碼 of 18
L1 No.16 16/May/2015
Level - 1 Mechanical (HVAC )
No.
Option Option 1

Q2 What is the cost pipe and fittings around the booster pump system if the < 2.5 points >
unit rate of the pipe material is USD 2.00 / kg. Fitting cost is 35% of the
pipe material cost. Refer to the attached fot pipe technical data.
Pipe Material is GALVANIZED STEEL, MEDIUM CLASS

< Answer >

1) 100mm dia pipe = 25 m x 12.48 kg / m 312.00 kg


1) 80mm dia pipe = 4 m x 8.58 kg / m 34.32 kg
2) 50mm dia pipe = 3 m x 5.17 kg / m 15.51 kg
Total Weight of pipe = 361.83 kg

Cost of pipe = 361.83 x 2 = 723.66 USD


Cost of fitting = 723.66 x 35% = 253.29 USD

Total Cost of pipe & fitting = 976.95 USD

Page 頁碼 of 18
L1 No.16 16/May/2015
Level - 1 Mechanical (HVAC)
No.
Option Option 1

< Question 1 > Attachment

Page 4 of 18
L1 No. 16 16/May/2015

Level -1 Mechanical (HVAC)


No
Option Option-1

<Question 2> (5.0 points)

Given :
Centrifugal pump,
2,100 L/min
35 m Head

PUMP CL
500 mm

v MAX WATER 500 mm


LEVEL
Suction Pipe ( Steel ) :
L ength = 4.0 m
2,500 mm Diameter = 150 mm 1,500 mm

v MIN WATER
LEVEL
500 mm

Valves and Fittings Equivalent Lengths :

a) Gate Valve, 2.50 m e) Flexible Connection, 2.00 m


b) Check Valve, 15.00 m f) Eccentric Reducer, 3.00 m
c) Y-strainer, 25.00 m g) Concentric Reducer, 3.00 m
d) Foot valve with 18.00 m h) 90 deg elbow, 5.00 m
strainer,

Q-01) What is the pump suction lift in meter ( worst condition ) ? (1.5 points)

< Answer >

Suction Lift = 1.50 + 0.50 + 0.50


= 2.5 m

Page 5 of 18
L1 No. 16 16/May/2015

Q-02) What is the total equivalent length (Le) of pipe, valves and fittings at the
suction side of the pump ? (2.0 points)

< Answer >


Equivalent Length
Straight pipe = 4.0 m
Foot Valve = 18.00 m
90 deg. Elbow = 5.00 m
Y-strainer = 25.00 m
Flexible Connection = 2.00 m
Eccentric reducer = 3.00 m

Total Equiv. Length, Le = 57.0 m

Q-03) Determine the friction loss at the suction side of the pump. The friction
rate for 150mm dia. pipe at a flowrate of 2,100 L/m is 250 Pa / m. (1.5 points)

< Answer >

hf = hf / m x Le
= 250 x 57
= 14,250 Pa

Page 6 of 18
Level - 1 Mechanical (HVAC) L1 No. 16 / 16 May 2015
No.
Option Option 2

Question 1
NC(Noise Criterion) -diagram is as below 7 point

1. What does A at X coordinate represent and its unit?


Answer
Octave band center frequency ( Hz )

2. What does B at Y coordinate represent and its unit?


Answer
Sound Pressure Level ( dB )

3.What is the value of Recommended Noise Criterion for open-plan area of office?
Answer
NC 35 ~ 40

4. What is Equivalent Sound Level (dBA) to NC45


Answer
50dBA

Page 7 of 18
Level - 1 Mechanical (HVAC) L1 No. 16 / 16 May 2015
No.
Option Option 2

5. Please input the approximate values in the below table

If the levels to be added differ The total is the larger level


by … (dB) plus…(db)
0 or 1 3

2 or 3 2

4 to 9 1

10 or more 0

Page 8 of 18
L1 No. 16 / 16May 2015

Level-1 Mechanical (HVAC)


No.
Option Option 2

< Question 2 > ( 3 points )

From the Axial fan curve , make a selection of fan capacity as follows:

Flow rate = 36,000 CMH

Fan total pressure = 400 Pa

Air density = 1.2 Kg/m3

Please find

(a) Fan blade pitch angle

Answer : 13 degree

(b) Absorbed Power (KW)

Answer : 6.0~6.5 KW

(c) Fan static pressure

Answer : 300 Pa ( from curve)

Page 9 of 18
<Option 2 - Q 2 Attached sheet>
L1 No.16 / 16 May 2015

Level - 1 Mechanical ( HVAC )


No.
Option Option 3

< Question 1 > ( 4 points)


Identify the drawings of sanitary fixtures below with the necessary pipe sizes
for cold water supply and drain pipe size requirement for each fixture.

Cold Water Drain Pipe


Drawing Supply Pipe Connection Size
Name of Fixture Connection Size
B
A
Water Closet Ø25 mm Ø100 mm
A (Flush valve type)
(Example)

Urinal Ø15mm Ø50 mm


(Wall hung type) or
A (Example) Ø40 mm

Water Closet Ø15 mm Ø100mm


(Low tank type) or
Ø75 mm
A (Example)

Lavatory Ø15 mm Ø40 mm


or ( Ø32 mm )
Wash basin
A (Example)

Page 頁碼 of 18
L1 No. 16 / 16 May 2015

Level -1 Mechanical (HVAC)


No
Option Option 3

< Qusetion 2 > (6 points)


Q-1. Calculate the U-factor of the partition wall shown in bellow.
The thermal properties of layers please refer to attached table.
<3 points>

1. 25mm Stucco
2. 200mm lightweight concrete
3. 19mm Acoustic tile

1
2
3
given:
Formula:
1 1
U= =
1/αo + Σ L/k +1/αi Ro + Σ R +Ri

U: Coefficient of heat transfer 【W/(m2 . ℃)】


L: Thickness 【m】
k: Material thermal conductivity 【W/ ( m . ℃)】
R: thermal resistance 【(m2 .℃)/ W】
Ro: Outside surface resistance 【(m2 .℃)/ W】
Ri: Inside surface resistance 【(m2 .℃)/ W】
Attached sheet for factors

< Answer >

Σγ= (0.019/0.061)+(0.2/0.173)+(0.025/0.692)=1.504 【W/(m2 . ℃)】


U= 1/ (0.059+1.504+0.121)=0.594 【W/(m2 . ℃)】

Page 12 of 18
L1 No. 16 / 16 May 2015

Q-2. Whenever a conditioned space is adjacent to a space with a different temperature,


regarding partition construction is as same as above.
To calculate the transfer of heat through the separating section.
<3 points>
given:
1. Area of separating section is 【15m *4m】
2. Temperature in conditioned space 【24℃】
3. Temperature in adjacent space 【36℃】

< Answer >

q= U*A*Δt
= 0.594*15*4*(36-24)
= 428 【W】

[ Attached sheet ]

Page 13 of 18
L-1 No. 16/16 May 2015

Level - 1 Mechanical ( HVAC)


No.
Compulsory Option-4

< Question 1>

The figure below shows a typical sprinkler control valve and accessories. < 5 point >

5
2

SPRINKLER CONTROL
VALVE

To match the correct part number designation shown in the above figure.

PART NO. ANSWER PART NAME

(1) f a ) Flow meter


b ) Connected to drain
(2) d c ) Connected to Sprinkler System
d ) Installation pressure gauge
(3) g e ) Alarm Gong
f ) Y-Strainer
(4) c g ) Connected from Sprinkler pumps

(5) e

Page 14 of 18
L-1 No.16 /16 May 2015

Level-1 Mechanical (HVAC)


NO.
Option Option-4

Q-2 Different type of Sprinkler System (2 points)

a) Wet Pipe Installation :- Installation where the pipework is filled with water and
ready to discharge once the sprinkler bulb breaks

b) Dry Pipe Installation :- Installation where the pipe is always filled with air under
pressure. Air is released when the sprinkler buld breaks
and the water fills the pipe and is discharged at the
sprinkler heds

c) Pre-action Installation :- Installation where the pipeworks is charged with air


underpressure and a valve is opened to filled the system
with water when fire is detected by smoke or heat
detectors. Water is charged only when the sprinkler bulb
breaks

d) Deluge Installation :- Installation where the sprinkler heads has no bulb and
water is discharged simultaneously from all heads when
fire is detected and the valve is opened.

Q-3 List down the 6 cheking points for the Fire Alarm Cabling during procurement
(3 points)
Answer

1) Type of cable

2) Size of cable

3) Country of Manufacture

4) Make and Model

5) Testing Standard

6) Validity of Fire Department Certificate


7) Type of conduit or trunking
8) Size of conduit or trunking

Page 15 of 18
L-1 No. 16 /16 May 2015

Level - 1 Mechanical (HVAC)


No.
Option Option-5

<Question 1> ( 6 points )


For Fan Running Test ,please list items to check in each parts as follow.
Answer to sellect from phrases as shown below.

1 List 4 item for Mechanical Check before fan operation.

1 c). Fan type , model , numbering is correct

2 n). All components , bolt fixing are secured

3 e). Fan Impeller are secured and freely rotate by hand

4 o). Alignment of belt and pulley is confirmed

2 List 4 items for Electrical Check included motor starter panel before fan operation.

1 f). No visible damage and live component in panel

2 b). All connection on busbar and wiring are tightened

3 j). Motor Insulation test completed

4 d). Fuse and circuit breaker rating is correct

3 List 4 items what to be checked during Fan Running

1 m). Check Fan rotation and speed are correct

2 g). No abnormal vibration and undue noise

3 r). Check Running current is balance on all phase

4 s). No abnormal overheat or over current of motor

< Word formation >


a). Maintenance manual is prepaered k). Shop drawing is prepared.
b). All connection on busbar and wiring are tightened l). Check pump rotation and speed are correct
c). Fan type , model , numbering is correct m). Check fan rotation and speed are correct
d). Fuse and circuit breaker rating is correct n). All components , bolt fixing are secured
e). Fan Impeller are secured and freely rotate by hand o). Alignment of belt and pulley is confirmed
f). No visible damage and live component in panel p). Alignment of coupling is confirmed
g). No abnormal vibration and undue noise q). Start the fan / Stop the fan
h). Pump current check, compare with design current r). Check Running current is balance on all phase
i). Pump pressure check, compare with design pressure s). No abnormal overheat or over current of motor
j). Motor Insulation test completed

Page 16 of 18
L-1 No.16 / 16 May 2015

Level -1 Mechanical ( HVAC )


No.
Option Option - 5

<Question 2> (4 points)


Please select name of vent. pipe from following word formation ,answer the alphabet
in answer culomn.

     ①     ⑨


     ②

     ③

     ④

     ⑤

[Word formation]

a. Wet vent pipe b. Vent stack pipe c. Return vent pipe

d. Common vent e. Header vent pipe f. Individual vent pipe

g.. Yoke vent pipe h. Loop vent pipe i. Stack vent pipe

< Answer >

① f (example) ⑥ g

② h ⑦ b

③ a ⑧ i

Page 17 of 18
L-1 No.16 / 16 May 2015

④ d ⑨ e

⑤ c

Page 18 of 18