2 Method Statement - Second Fix Instal - ICU HTAR Complete
2 Method Statement - Second Fix Instal - ICU HTAR Complete
INSTALLATION OF THE CEILING PENDANTS SECOND FIX ASSEMBLY UNITS FOR THE TWIN PENDANTS,
MULTI - MOVEMENT PENDANTS FOR THE ICU, OPERATING THEATRE’S AND CCU AREAS.
ACTIVITIES
1) Delivery of the items on pallets to site on a suitably sized vehicle c/w tail lift.
2) Offloading of pallets using hydraulic pallet trucks.
3) Transporting by hydraulic pallet trucks to the correct levels and rooms for installation.
4) Positioning the units.
5) Fixing the units to the pre-installed First Fix assemblies.
SEQUENCE OF WORK
1) Site induction of all staff. This is to include information on signing on and off site, site hazards, how warnings are signalled and what
action is to be taken in the event of an alarm, location of First Aids and equipment .
2) Review of the method statement by all staff involved in the work. The method statement is to be signed when understood and
agreed by all staff.
3) Liase with the site supervisor and agree unloading area
4) Offload the tools, access platform, second fix assembly and portable lifting jack and transported to dedicated floors.
5) Erect the access platform and ladders to a suitable working height and inspect.
6) Inspect the portable lifting jack and ensure in order.
7) Secure the second fix assembly to the portable lifting jack and lift / manoeuvre in to position.
8) Secure the second fix assembly to the slab and the first fix assembly using the fixings specified . Fig: M-8000-SF-01
No problems foreseen. If the work cannot be done in accordance with this method statement, the work will be suspended and the
method reviewed and agreed before work recommences.