Professional Documents
Culture Documents
Cashflow Print - As Per Schedule G - 30!12!2018
Cashflow Print - As Per Schedule G - 30!12!2018
Cashflow Print - As Per Schedule G - 30!12!2018
Name of Project: Widening of existing road to 2 lane from Nechipu to Hoj in Arunachal Pradesh on NH-229 on DBFOT Annuity basis
A S H O K A B U I L D C O N L T D.
Name of Project: Construction of Eight - Lane Vadodara Kim Expressway, Package IV from km. 279.000 to km. 292.000 (Ankaleshwar to Section)
in the State of Gujarat Under NHDP Phase VI on Hybrid Annuity mode (Phase IA - Package 4).
Stage for Payment Total % of Cost Months Months Month -1 Month -2 Month -3 Month -4 Month -5 Month -6 Month -7 Month -8 Month -9 Month -10 Month -11 Month -12 Month -13 Month -14 Month -15 Month -16 Month -17 Month -18 Month -19 Month -20 Month -21 Month -22 Month -23 Month -24 Month -25 Month -26 Month -27 Month -28
per Acivity
Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20 Feb-20 Mar-20 Apr-20 May-20 Jun-20 Jul-20 Aug-20 Sep-20 Oct-20 Nov-20 Dec-20 Jan-21 Feb-21 Mar-21
B. New Realignment
MCW Unit
(1) Earthwork upto top of Subgrade KM 18.61% 313.90 13.00 13.00 0 1 1 1 2 1.70 1 0 0 1 2 1 1
18.61% 0.57% 1.43% 1.86% 2.00% 2.15% 2.43% 0.72% 0.29% 0.29% 1.57% 2.15% 1.72% 1.43%
(2) Granular work (sub-base, base, Shoulders)
GSB KM 1.81% 30.49 10.00 10 0.50 1.00 1.50 2 1 0 1.00 1.20 1.10 1.00
1.81% 0.09% 0.18% 0.27% 0.27% 0.14% 0.07% 0.18% 0.22% 0.20% 0.18%
(3) Shoulder KM 0.16% 2.68 9.00 9.00 1.00 1.40 0.50 1.11 0.93 1 0.50 2.00 1.00
0.16% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0 0 0 0.02% 0.02% 0.01% 0.02% 0.02% 0.01% 0.01% 0.04% 0.02%
(5) Rigid Pavement
(a) DLC KM 2.21% 37.23 10.00 10 0.50 0.90 1 1 1 0.90 1.00 1.10 1.20 1.20
2.21% 0.11% 0.20% 0.24% 0.24% 0.22% 0.20% 0.22% 0.24% 0.26% 0.26% 0.00%
(b) PQC KM 7.09% 119.60 11.00 11 0.60 0.80 1 1.00 1.00 1.20 1.20 1.20 1 1.40 0.50
7.09% 0.39% 0.52% 0.52% 0.00 0.00 0.64% 0.64% 0.77% 0.77% 0.77% 0.84% 0.90% 0.32%
C- New culverts, minor bridges, underpasses, overpasses on existing road, realignment, bypasses
0.00
1) Culverts (Box and Pipe)
(i) Box Culvert No 0.47% 7.94 6.00 6.00 0.50 1.00 1.50 1.00 1.00 1.00
0.47% 0.04% 0.08% 0.12% 0.08% 0.08% 0.08%
(ii) Pipe Culvert No 0.10% 1.72 3.00 3.00 1.00 1.00 1.00
0.10% 0.03% 0.03% 0.03%
2) Minor Bridge
(a) Foundation No 0.53% 9.02 4.00 4.00 0.50 1.00 1.00 1.50
0.53% 0.07% 0.13% 0.13% 0.20%
(b) Sub-structure No 0.42% 7.11 3.00 3.00 1.00 1.00 1.00
0.42% 0.14% 0.14% 0.14%
(c) Super-Structure ( including crash barrier, complete ) No 0.47% 7.87 5.00 5.00 1.00 1.00 1.00 1.00 1.00
0.47% 0.09% 0.09% 0.09% 0.09% 0.09%
(3) Cattle/Padesterian Underpass
(a) Foundation No 0.60% 10.06 3.00 3.00 0.50 1.00 1.50
0.60% 0.10% 0.20% 0.30%
(b) Sub-structure No 0.39% 6.59 3.00 3.00 0.50 1.00 1.50
0.39% 0.07% 0.13% 0.20%
(c) Super-Structure ( including crash barrier, complete ) No 0.46% 7.84 4.00 4.00 1.00 1.50 1.00 0.50
0.46% 0.12% 0.17% 0.12% 0.06%
0.67% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.07% 0.07% 0.13% 0.20% 0.20%
Other Item
i) Service roads/Slip Road Km. 0.19% 3.20 4.00 4.00 1.00 1.00 1.00 1.00
0.19% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.05% 0.05% 0.05% 0.05%
(ii) Toll Plaza
(a) Tunnel No 0.16% 2.72 3.00 3.00 1.00 1.00 1.00
0.16% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.05% 0.05% 0.05%
(b) Toll Both No 0.09% 1.50 4.00 4.00 0.50 1.00 1.50 1.00
0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.01% 0.02% 0.03% 0.02%
(c) Admin Building No 0.09% 1.46 4.00 4.00 0.50 1.50 1.50 0.50
0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.01% 0.03% 0.03% 0.01%
(d) Toll Canopy No 0.34% 5.74 5.00 5.00 1.00 1.50 1.50 0.50 0.50
0.34% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.07% 0.10% 0.10% 0.03% 0.03%
(e) New jersey Crash Barrier RMT 0.05% 0.87 3.00 3.00 1.00 1.00 1.00
0.05% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.02% 0.02% 0.02%
(iii) Road Side Drain Km. 1.14% 19.30 19.00 19.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.50 1.50 1.50 1.30 1.30 1.50 1.00 0.20 0.10 0.10
1.14% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.06% 0.09% 0.09% 0.09% 0.08% 0.08% 0.09% 0.06% 0.01% 0.01% 0.01%
(iv) Road signs, markings, km stone, safety devices
(a) Road signs, Markings, KM Stones etc. Km. 0.41% 6.95 10.00 10.00 1.00 1.00 1.50 1.50 2.00 2.00 0.50 0.20 0.20 0.10
0.41% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.04% 0.04% 0.06% 0.06% 0.08% 0.08% 0.02% 0.01% 0.01% 0.00% 0.00%
(b) Concrete Crash barrier/ W-Beam Crash Barrier in Road Work Km. 2.50% 42.10 14.00 14.00 0.80 1.30 1.60 1.80 2.20 1.50 1.00 1.00 1.00 1.00 0.50 0.10 0.10 0.10
2.50% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0 0.00% 0.00% 0.00% 0.14% 0.23% 0.29% 0.32% 0.39% 0.27% 0.18% 0.18% 0.18% 0.18% 0.09% 0.02% 0.02% 0.02% 0.00%
(vii) Road Side Plantation Km. 0.33% 5.64 6.00 6.00 2.00 1.80 1.40 0.50 0.20 0.10
0.33% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.11% 0.10% 0.08% 0.03% 0.01% 0.01%
(viii) Protection works
(a) Boulder Pitching on Slopes RMT 1.10% 18.48 14.00 14.00 0.80 1.30 1.60 1.80 2.20 1.50 1.00 1.00 1.00 1.00 0.50 0.10 0.10 0.10
1.10% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.06% 0.10% 0.13% 0.14% 0.17% 0.12% 0.08% 0.08% 0.08% 0.08% 0.04% 0.01% 0.01% 0.01%
(x) Miscellaneous Work
(a) Chain Link Fencing RMT 1.09% 18.46 8.00 8.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
1.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.14% 0.14% 0.14% 0.14% 0.14% 0.14% 0.14% 0.14% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(b) Kerb RMT 0.08% 1.38 5.00 5.00 1.00 1.00 1.00 1.50 0.50
0.08% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.02% 0.02% 0.02% 0.02% 0.01% 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(c) Electrification
(i) High Mast No 0.03% 0.50 2.00 2.00 1.00 1.00
0.03% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.01% 0.01% 0.00% 0.00% 0.00% 0.00% 0.00%
(ii) Street light poles with double arm (Built up Section) No 0.06% 1.00 4.00 4.00 1.00 1.00 1.00 1.00
0.06% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.01% 0.01% 0.01% 0.01% 0.00% 0.00% 0.00%
(iii) Street light poles with single arm (Major Bridge, Bus bays and Truck Lay byes) No 0.43% 7.31 7.00 7.00 1.00 1.00 0.50 2.00 1.00 0.50 0.50 0.50
0.43% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.06% 0.06% 0.00 0.00 0.00 0.03% 0.12% 0.06% 0.03% 0.03% 0.03% 0.00%
(iv) Lighting in VUP inside No 0.01% 0.16 2.00 2.00 1.00 1.00
0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Traffic Management System
(i) Weigh Motion Bridge No 0.06% 0.94 2.00 2.00 1.00 1.00
0.06% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.03% 0.03% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(ii) Lane level equipment's (Hybrid ETC) Lumpsum 0.65% 11.03 2.00 2.00 1.00 1.00
0.65% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.33% 0.33% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00%
(iii) Plaza Level Equipment ( Mobile Communication System, Variable Message Sign, Automatic Lumpsum 0.84% 14.17 5.00 5.00 1.50 1.00 0.50 0.50 1.50
Traffic Counter and Vehicle Claasification , Metereological Data collection System, Video
Survillience System, Video Incident detection Centre. 0.84% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.25% 0.00 0.00 0.00 0.25% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(iv) Control Room Lumpsum 0.09% 1.57 2.00 2.00 1.00 1.00
0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.05% 0.05% 0.00% 0.00% 0.00% 0.00% 0.00%
(v) OFC Cable Km. 0.19% 3.15 3.00 3.00 1.00 1.00 1.00
0.19% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.06% 0.06% 0.06% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(vi) On Site Support & Spares Lumpsum 0.09% 1.57 2.00 2.00 1.00 1.00
0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.05% 0.05% 0.00% 0.00% 0.00% 0.00% 0.00%
(xi) Clover Leaf 0.00
(a) Loop A 0.00
(1) Earthwork upto top of Sub-grade Km. 0.42% 7.13 3.00 3.00 0.60 1.00 1.40
0.42% 0.08% 0.14% 0.20% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(2) Granular Work (Sub-base, Shoulder) 0.00% 0.00
GSB Km. 0.05% 0.85 2.00 2.00 1.00 1.00
0.05% 0.00% 0.00% 0.00% 0.03% 0.03% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(3) Shoulders Km. 0.004% 0.06 2.00 2.00 0.50 1.50
0.004% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(4) Rigid Pavement 0.00% 0.00
(i) DLC Km. 0.06% 1.03 1.00 1.00 1.00
0.06% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.06% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(ii) PQC Km. 0.18% 2.97 1.00 1.00 1.00
0.18% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.18% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(b) Loop B
(1) Earthwork upto top of Sub-grade Km. 0.47% 7.87 3.00 3.00 0.60 1.00 1.40
0.47% 0.00% 0.09% 0.16% 0.22% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(2) Granular Work (Sub-base, Shoulder)
GSB Km. 0.11% 1.85 2.00 2.00 1.00 1.00
0.11% 0.00% 0.00% 0.00% 0.00% 0.05% 0.05% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00%
(3) Shoulders Km. 0.004% 0.06 2.00 2.00 0.50 1.50
0.004% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(4) Rigid Pavement
(i) DLC Km. 0.13% 2.25 1.00 1.00 1.00
0.13% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.13%
(ii) PQC Km. 0.42% 7.04 1.00 1.00 1.00
0.42% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.42% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(c) Loop C
(1) Earthwork upto top of Sub-grade Km. 0.43% 7.17 3.00 3.00 0.60 1.00 1.40
0.43% 0.00% 0.00% 0.09% 0.14% 0.20% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(2) Granular Work (Sub-base, Shoulder)
GSB Km. 0.09% 1.49 2.00 2.00 1.00 1.00
0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.04% 0.04% 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(3) Shoulders Km. 0.00% 0.06 2.00 2.00 0.50 1.50
0.004% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(4) Rigid Pavement
(i) DLC Km. 0.11% 1.81 1.00 1.00 1.00
0.11% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.11% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00%
(ii) PQC Km. 0.17% 2.93 1.00 1.00 1.00
0.17% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.17% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(d) Loop D
(1) Earthwork upto top of Sub-grade Km. 0.37% 6.20 3.00 3.00 0.60 1.00 1.40
0.37% 0.00% 0.00% 0.00% 0.07% 0.12% 0.17% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(2) Granular Work (Sub-base, Shoulder)
GSB Km. 0.15% 2.53 2.00 2.00 1.00 1.00
0.15% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.07% 0.07% 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(3) Shoulders Km. 0.003% 0.06 2.00 2.00 0.50 1.50
0.003% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00%
(4) Rigid Pavement
(i) DLC Km. 0.17% 2.95 1.00 1.00 1.00
0.17% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.17% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00
(ii) PQC Km. 0.31% 5.23 1.00 1.00 1.00
0.31% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.31% 0.00% 0.00% 0.00% 0.00%
(e) Ramp A
(1) Earthwork upto top of Sub-grade Km. 0.38% 6.33 3.00 3.00 0.60 1.00 1.40
0.38% 0.00% 0.08% 0.13% 0.18% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(2) Granular Work (Sub-base, Shoulder)
GSB Km. 0.09% 1.47 2.00 2.00 1.00 1.00
0.09% 0.00% 0.00% 0.00% 0.00% 0.04% 0.04% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00%
(3) Shoulders Km. 0.005% 0.08 2.00 2.00 0.50 1.50
0.005% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00%
(4) Rigid Pavement
(i) DLC Km. 0.11% 1.79 1.00 1.00 1.00
0.11% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.11% 0.00%
(ii) PQC Km. 0.33% 5.56 1.00 1.00 1.00
0.33% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.33%
(f) Ramp B
(1) Earthwork upto top of Sub-grade Km. 0.62% 10.40 3.00 3.00 0.60 1.00 1.40
0.62% 0.00% 0.00% 0.12% 0.21% 0.29% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00%
(2) Granular Work (Sub-base, Shoulder)
GSB Km. 0.07% 1.17 2.00 2.00 1.00 1.00
0.07% 0.00% 0.00% 0.00% 0.00% 0.00% 0.03% 0.03% 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(3) Shoulders Km. 0.004% 0.07 2.00 2.00 0.50 1.50
0.004% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(4) Rigid Pavement
(i) DLC Km. 0.08% 1.42 1.00 1.00 1.00
0.08% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.08%
(ii) PQC Km. 0.26% 4.41 1.00 1.00 1.00
0.26% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.26%
(g) Ramp C
(1) Earthwork upto top of Sub-grade Km. 0.34% 5.75 3.00 3.00 0.60 1.00 1.40
0.34% 0.00% 0.00% 0.00% 0.07% 0.11% 0.16% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(2) Granular Work (Sub-base, Shoulder)
GSB Km. 0.16% 2.75 2.00 2.00 1.00 1.00
0.16% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.08% 0.08% 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00%
(3) Shoulders Km. 0.005% 0.08 2.00 2.00 0.50 1.50
0.005% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(4) Rigid Pavement
(i) DLC Km. 0.20% 3.35 1.00 1.00 1.00
0.20% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.20% 0.00% 0.00% 0.00% 0.00%
(ii) PQC Km. 0.33% 5.58 1.00 1.00 1.00
0.33% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.33% 0.00% 0.00% 0.00% 0.00%
(h) Ramp D
(1) Earthwork upto top of Sub-grade Km. 0.25% 4.17 3.00 3.00 0.60 1.00 1.40
0.25% 0.00% 0.00% 0.00% 0.00% 0.05% 0.08% 0.12% 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00%
(2) Granular Work (Sub-base, Shoulder)
GSB Km. 0.10% 1.63 2.00 2.00 1.00 1.00
0.10% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.05% 0.05% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00%
(3) Shoulders Km. 0.004% 0.07 2.00 2.00 0.50 1.50
0.004% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(4) Rigid Pavement
(i) DLC Km. 0.10% 1.76 1.00 1.00 1.00
0.10% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.10% 0.00% 0.00% 0.00%
(ii) PQC Km. 0.19% 3.17 1.00 1.00 1.00
0.19% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.19% 0.00% 0.00% 0.00% 0.00%
100.00% 1687 0 2.2% 4.5% 6.6% 8.7% 9.4% 9.5% 5.5% 2.7% 2.4% 6.1% 7.4% 6.5% 6.0% 4.4% 3.8% 3.4% 2.8% 2.2% 1.3% 0.9% 0.9% 1.2% 0.8% 0.4% 0.2% 0.1% 0.1% 0.0%
0 2.19% 6.69% 13.28% 21.98% 31.40% 40.91% 46.44% 49.10% 51.51% 57.66% 65.09% 71.60% 77.62% 82.03% 85.86% 89.27% 92.03% 94.22% 95.53% 96.39% 97.26% 98.43% 99.27% 99.63% 99.80% 99.91% 100.00%
Monthly Cashflow - Target 1687 0 37.00 76.00 111.00 147.00 159.00 160.00 93.00 45.00 41.00 104.00 125.00 110.00 102.00 75.00 65.00 57.00 47.00 37.00 22.00 14.00 15.00 20.00 14.00 6.00 3.00 2.00 1.00
Cumulative Cashflow - Target 0.00 37.00 113.00 224.00 371.00 530.00 690.00 783.00 828.00 869.00 973.00 1098.00 1208.00 1309.00 1384.00 1448.00 1506.00 1553.00 1589.00 1612.00 1626.00 1641.00 1660.00 1675.00 1681.00 1684.00 1685.00 1687.00
Targetted Project Milestone 20.00% 35.00% 75.00% 100%
Appointment Date Mile Stone -1 ( 20% @ 180 Days ) Mile Stone -2 ( 35% @ 400 Days ) Mile Stone - 3 ( 75% @ 650 Days ) Mile Stone - 4 ( 100% @ 910 Days )
Project Milestone as per CA Clause no. 12.1A 12/10/2018 6/8/2019 1/14/2020 9/20/2020 6/7/2021
0 337.4 590.45 1265.25 8/13/1904
Ashoka Buildcon Ltd.
Name of Project: Construction of Eight - Lane Vadodara Kim Expressway, Package IV from km. 279.000 to km. 292.000 (Ankaleshwar to Section) in the State of Gujarat Under NHDP Phase VI on Hybrid Annuity mode (Phase IA - Package 4).
As on
Description Unit Total Sept - 18 Balance Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20 Feb-20 Mar-20 Apr-20 May-20 Jun-20 Jul-20 Aug-20 Sep-20 Oct-20 Nov-20
Ashoka Buildcon Ltd.
Road Work
Earth work in Embankment & SG (Including Fly
1 m3 4,127,371 - Err:508 126,996 317,490 412,737 444,486 476,235 539,733 158,745 63,498 63,498 349,239 476,235 380,988 317,490 - - - - - - - - - - -
Ash)
3 Granular Sub Base m3 90,537 - Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508
4 Dry Lean Concrete m3 90,686 - Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508
5 Plain Quality Concrete m3 164,290 - Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508 Err:508
Structure work -
1 M-15 m3 - - - - - - - - - - - - - - - - - - - - - - - - - - -
2 M-20 m3 4,332 - 4,332 3 71 159 288 227 144 131 90 87 45 90 131 180 175 180 180 169 180 56 - 28 519 502 695
3 M-25 m3 - - - - - - - - - - - - - - - - - - - - - - - - - - -
4 M-30 m3 - - - - - - - - - - - - - - - - - - - - - - - - - - -
5 M-35 m3 66,320 - 66,320 7,630 9,423 14,373 12,822 8,793 5,297 5,651 1,690 568 73 - - - - - - - - - - - - - -
6 M-40 m3 5,115 - 5,115 - - - - - - - - - - - - - - - - - - - - 77 1,437 1,437 2,165
7 M-50 m3 3,724 - 3,724 - - 168 241 570 584 136 - - 466 1,221 337 - - - - - - - - - - - -
6 Reinforcement MT 6,764 - 6,764 687 848 1,309 1,176 843 529 521 152 51 49 110 30 - - - - - - - - 7 129 129 195
7 Structural Steel MT 1,148 - 1,148 - - - - - 402 574 172 - - - - - - - - - - - - - - - -
225,270
Sr Material Unit GSB DLC PQC M-15 M-20 M-25 M-30 M-35 M-40 M-50
Density 2.250 2.346 2.302 2.311 2.192 2.218 2.210 2.260 2.281 2.407
160.0 Cr
159.0 Cr
147.0 Cr
180.0 Cr
160.0 Cr
125.0 Cr
111.0 Cr
110.0 Cr
140.0 Cr
104.0 Cr
102.0 Cr
93.0 Cr
120.0 Cr
76.0 Cr
75.0 Cr
100.0 Cr
80.0 Cr
45.0 Cr
41.0 Cr
37.0 Cr
60.0 Cr
40.0 Cr
20.0 Cr
0.0 Cr
Dec-18
Jan-19
Feb-19
Mar-19
Apr-19
May-19
Jun-19
Aug-19
Sep-19
Oct-19
Nov-19
Dec-19
Jan-20
Jul-19
Cash Flow - Package VME - Package - 4
Item Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19
Monthly Execution Cost 37.0 Cr 76.0 Cr 111.0 Cr 147.0 Cr 159.0 Cr 160.0 Cr 93.0 Cr 45.0 Cr 41.0 Cr 104.0 Cr 125.0 Cr
Cumulative Cost 37.0 Cr 113.0 Cr 224.0 Cr 371.0 Cr 530.0 Cr 690.0 Cr 783.0 Cr 828.0 Cr 869.0 Cr 973.0 Cr 1098.0 Cr
1800.0 Cr
1600.0 Cr
1506
1448.0 Cr
1400.0 Cr 1384.0 Cr
1309.0 Cr
1208.0 Cr
1200.0 Cr
1098.0 Cr
1000.0 Cr 973.0 Cr
869.0 Cr
828.0 Cr
800.0 Cr 783.0 Cr
690.0 Cr
600.0 Cr
530.0 Cr
400.0 Cr 371.0 Cr
224.0 Cr
200.0 Cr
113.0 Cr
37.0 Cr
0.0 Cr
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 1
onthly Execution Cost - VME - Package 4
125.0 Cr
110.0 Cr
102.0 Cr
75.0 Cr
65.0 Cr
57.0 Cr
47.0 Cr
37.0 Cr
22.0 Cr
20.0 Cr
15.0 Cr
14.0 Cr
14.0 Cr
6.0 Cr
3.0 Cr
2.0 Cr
1.0 Cr
Oct-19
Nov-19
Dec-19
Jan-20
Feb-20
Mar-20
Apr-20
May-20
Jun-20
Aug-20
Sep-20
Oct-20
Nov-20
Dec-20
Jan-21
Feb-21
Jul-20
Nov-19 Dec-19 Jan-20 Feb-20 Mar-20 Apr-20 May-20 Jun-20 Jul-20 Aug-20 Sep-20 Oct-20 Nov-20 Dec-20 Jan-21
110.0 Cr 102.0 Cr 75.0 Cr 65.0 Cr 57.0 Cr 47.0 Cr 37.0 Cr 22.0 Cr 14.0 Cr 15.0 Cr 20.0 Cr 14.0 Cr 6.0 Cr 3.0 Cr 2.0 Cr
1208.0 Cr 1309.0 Cr 1384.0 Cr 1448.0 Cr 1506.0 Cr 1553.0 Cr 1589.0 Cr 1612.0 Cr 1626.0 Cr 1641.0 Cr 1660.0 Cr 1675.0 Cr 1681.0 Cr 1684.0 Cr 1685.0 Cr
Row 28
13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Feb-21
1.0 Cr
1687.0 Cr
Ashoka Ankleshwar Manubar Ex
Name of Project: Construction of Eight - Lane Vadodara Kim Expressway, Package IV from km. 279.000 to km. 292.000 (Ankaleshwar to Manubar Section) in the State of Gujarat Under NHDP Phase VI on Hybrid Annuity mode (Phase IA - Package 4).
MONTHLY CASHFLOWS & S-CURVE STATEMENT
Stage for Payment Total % of Cost Months Months Month -1 Month -2 Month -3 Month -4 Month -5 Month -6 Month -7
per Acivity
Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19
B. New Realignment
(1) Earthwork upto top of Subgrade KM 20.715 17.82% 300.62 13.00 13.00 0 1 1 1 2 1.70 1
17.82% ###### 0.55% 1.37% 1.78% 1.92% 2.06% 2.33% 0.69%
(2) Granular work (sub-base, base, Shoulders)
GSB KM 20.715 1.77% 29.86 10.00 10 0.50 1.00 1.50 2
1.77% 0.09% 0.18% 0.27% 0.27%
(3) Shoulder KM 20.715 0.16% 2.70 9.00 9.00
0.16% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0
(5) Rigid Pavement
(a) DLC KM 20.715 2.16% 36.44 10.00 10 0.50 0.90 1
2.16% 0.11% 0.19% 0.24%
(b) PQC KM 20.715 6.93% 116.91 11.00 11 0.60 0.80 1
6.93% 0.38% 0.50% 0.50%
0.00
Appointment Date Mile Stone -1 ( 20% @ 180 Days ) Mile Stone -2 ( 35% @ 400 Days )
Project Milestone as per Schedule "G" ( In Crores ) 12/10/2018 6/8/2019 1/14/2020
0.00 337.4 590.45
0.00 Milestone-1 @ 10% Milestone-2 @ 10% 0.00
(8% of Bid Cost) (8% of Bid Cost)
Annuity Payment Milestone During Construction Period ( In Crores ) as Per article no. 23.4 of CA
134.96 134.96
eshwar Manubar Expressway Pvt Ltd.
Revision- 01
Date- 10-12-2018
Month -8 Month -9 Month -10 Month -11 Month -12 Month -13 Month -14 Month -15 Month -16 Month -17 Month -18 Month -19 Month -20 Month -21 Month -22 Month -23 Month -24 Month -25 Month -26 Month -27
Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20 Feb-20 Mar-20 Apr-20 May-20 Jun-20 Jul-20 Aug-20 Sep-20 Oct-20 Nov-20 Dec-20 Jan-21 Feb-21
Milestone-3 @75% Milestone-4
@100%
0 0 1 2 1 1
0.27% 0.27% 1.51% 2.06% 1.64% 1.37%
0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
1
0.00% 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
1 1
0.28% 0.28% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
1.00 1.00
0.06% 0.06%
1.00
0.21% 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
1.00 1.00
0.11% 0.11% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
1.00 1.00 1.00
0.08% 0.08% 0.08% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
1.00 1.00 1.00
0.00 0.01% 0.01% 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
1.00 1.00 1.00
0.00 0.00 0.23% 0.23% 0.23% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
1.00
0.25% 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.50 0.50 1.00 2.00
0.03% 0.03% 0.06% 0.13% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
1.00 1.00 1.00
0.00 0.00 0.00% 0.13% 0.13% 0.13% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.5 0.5 0.8 1 1 1.2 2 1.4 1.2 1.2 1.2 0.5 0.5 0.5 1.5 1 1
0.34% 0.34% 0.54% 0.68% 0.68% 0.81% 1.35% 0.95% 0.81% 0.81% 0.81% 0.34% 0.34% 0.34% 1.02% 0.68% 0.68%
0.7 1 1.2 1.3 1.3 1.3 1.5 1.2 1.2 0.8 0.8 0.5 0.2 1 1 1
0.00 0.00 0.00% 0.10% 0.15% 0.18% 0.19% 0.19% 0.19% 0.22% 0.18% 0.18% 0.12% 0.12% 0.07% 0.03% 0.15% 0.15% 0.15% 0.00%
1 1.3 1.5 1.2 0.5 0.5 1 1 1 1 1
0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.06% 0.08% 0.09% 0.07% 0.03% 0.03% 0.06% 0.06% 0.06% 0.06% 0.06% 0.00%
1 1 1 1
0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.13% 0.13% 0.13% 0.13%
0.5 0.5 2
0.17% 0.17% 0.69% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
1 1
0.00 0.31% 0.31% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
1 1
0.00 0.00 0.21% 0.21% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
1.00 1.00 1.50 1.50 1.00 1.50 1.00 0.70 0.70 0.10
0.00 0.00 0 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.04% 0.04% 0.06% 0.06% 0.04% 0.06% 0.04% 0.03% 0.03% 0.00%
0.80 1.00 1.00 1.00 1.50 1.20 0.50 0.50 1.20 1.50 1.50 1.50 0.70 0.10
0.00 0.00 0 0.00% 0.00% 0.00% 0.14% 0.17% 0.17% 0.17% 0.26% 0.21% 0.09% 0.09% 0.21% 0.26% 0.26% 0.26% 0.12% 0.02%
1.50 1.50 1.50 1.00 0.40 0.10
0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.18% 0.18% 0.18% 0.12% 0.05% 0.01%
0.80 1.30 1.60 1.80 2.20 1.50 1.00 1.00 1.00 1.00 0.50 0.10 0.10 0.10
0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.07% 0.12% 0.15% 0.16% 0.20% 0.14% 0.09% 0.09% 0.09% 0.09% 0.05% 0.01% 0.01% 0.01%
1.00 1.00 1.00 1.00 1.00 1.00
0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.09% 0.09% 0.09% 0.09% 0.09% 0.09%
1.00 1.00
0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.09% 0.09% 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
1.00 1.00
0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.02% 0.02% 0.00% 0.00% 0.00% 0.00%
1.00 1.00 1.00 1.00
0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.02% 0.02% 0.02% 0.02% 0.00% 0.00%
1.00 1.00 0.50 2.00 1.00 0.50 0.50 0.50
0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.06% 0.06% 0.00 0.00 0.00 0.03% 0.12% 0.06% 0.03% 0.03% 0.03%
1.00 1.00
0.00 0.00 0.00% 0.00% 0.00% 0.02% 0.02% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
1.00 1.00
0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.03% 0.03% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
1.00 1.00
0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.32% 0.32% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00%
1.50 1.00 0.50 0.50 1.50
0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.39% 0.00 0.00 0.00 0.39% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.50 1.50
0.00 0.00 0.00% 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
1.00
0.00 0.00 0.06% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
1.00
0.00 0.00 0.17% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00%
0.50 1.50
0.00 0.00 0.00% 0.00% 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
1.00
0.00 0.00 0.00% 0.13%
1.00
0.00 0.00 0.00% 0.40% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.50 1.50
0.00 0.00 0.00% 0.00% 0.00% 0.01% 0.00% 0.00% 0.00% 0.00% 0.00%
1.00
0.00 0.00 0.00% 0.00% 0.10% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00%
1.00
0.00 0.00 0.00% 0.00% 0.17% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
1.00
0.08% 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.50 1.50
0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.01% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00%
1.00
0.00 0.00 0.00% 0.00% 0.00% 0.18% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00
1.00
0.00 0.00 0.00% 0.00% 0.00% 0.30% 0.00% 0.00% 0.00% 0.00%
0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00%
0.50 1.50
0.00 0.00 0.00% 0.01% 0.00% 0.00% 0.00%
1.00
0.00 0.00 0.10% 0.00%
1.00
0.00 0.00 0.32%
0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00%
0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
0.50 1.50
0.00 0.00 0.00% 0.00% 0.01% 0.00% 0.00% 0.00% 0.00%
1.00
0.00 0.00 0.00% 0.08%
1.00
0.00 0.00 0.00% 0.25%
0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
1.00
0.08% 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00%
0.50 1.50
0.00 0.00 0.00% 0.00% 0.00% 0.01% 0.00% 0.00%
1.00
0.00 0.00 0.00% 0.00% 0.19% 0.00% 0.00% 0.00% 0.00%
1.00
0.00 0.00 0.00% 0.00% 0.32% 0.00% 0.00% 0.00% 0.00%
0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00%
1.00 1.00
0.05% 0.05% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00 0.00 0.00 0.00% 0.00%
0.50 1.50
0.00 0.00 0.00% 0.00% 0.00% 0.00% 0.01% 0.00% 0.00% 0.00%
1.00
0.00 0.00 0.00% 0.00% 0.00% 0.11% 0.00% 0.00% 0.00%
1.00
0.00 0.00 0.00% 0.00% 0.00% 0.19% 0.00% 0.00% 0.00% 0.00%
3.2% 2.8% 6.6% 6.7% 5.4% 5.1% 3.5% 3.0% 2.8% 2.6% 2.9% 1.7% 1.1% 1.2% 2.4% 1.8% 1.9% 1.0% 0.7% 0.3%
46.40% 49.24% 55.88% 62.60% 68.04% 73.19% 76.68% 79.65% 82.40% 84.98% 87.85% 89.52% 90.66% 91.82% 94.24% 96.06% 97.92% 98.94% 99.66% 100.00%
54.00 48.00 112.00 113.00 92.00 87.00 59.00 50.00 46.00 44.00 48.00 28.00 19.00 20.00 41.00 31.00 31.00 17.00 12.00 6.00
783.00 831.00 943.00 1056.00 1148.00 1235.00 1294.00 1344.00 1390.00 1434.00 1482.00 1510.00 1529.00 1549.00 1590.00 1620.00 1652.00 1669.00 1681.00 1687.00
75.00% 100%
0 Days ) Mile Stone - 3 ( 75% @ 650 Days ) Mile Stone - 4 ( 100% @ 910 Days )
9/20/2020 6/7/2021
1265.25 1687
0 Milestone-3 @ Milestone-4 @ Milestone-5 @
10% (8% of Bid 10% (8% of Bid 10% (8% of Bid
Cost) Cost) Cost)
Month -28
Mar-21
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.0%
Ashoka Ankleshwar Manubar Expressway Pvt Ltd.
Name of Project: Construction of Eight - Lane Vadodara Kim Expressway, Package IV from km. 279.000 to km. 292.000
Cash Flow VME - Package - 4
149.0 Cr
148.0 Cr
138.0 Cr
160.0 Cr
113.0 Cr
112.0 Cr
140.0 Cr
106.0 Cr
120.0 Cr
92.0 Cr
87.0 Cr
84.0 Cr
100.0 Cr
70.0 Cr
59.0 Cr
80.0 Cr
54.0 Cr
50.0 Cr
48.0 Cr
48.0 Cr
46.0 Cr
44.0 Cr
41.0 Cr
60.0 Cr
33.0 Cr
31.0 Cr
31.0 Cr
28.0 Cr
20.0 Cr
19.0 Cr
17.0 Cr
40.0 Cr
12.0 Cr
6.0 Cr
20.0 Cr
0.0 Cr
Dec-18
May-19
Apr-20
May-20
Jul-20
Jan-19
Feb-19
Mar-19
Apr-19
Jun-19
Jul-19
Aug-19
Sep-19
Oct-19
Nov-19
Dec-19
Feb-20
Mar-20
Jun-20
Aug-20
Sep-20
Oct-20
Nov-20
Dec-20
Jan-21
Feb-21
Jan-20
Cash Flow - Package VME - Package - 4
Item Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20 Feb-20 Mar-20 Apr-20 May-20 Jun-20 Jul-20 Aug-20 Sep-20 Oct-20 Nov-20 Dec-20 Jan-21 Feb-21
Monthly Execution Cost 33.0 Cr 70.0 Cr 106.0 Cr 138.0 Cr 149.0 Cr 148.0 Cr 84.0 Cr 54.0 Cr 48.0 Cr 112.0 Cr 113.0 Cr 92.0 Cr 87.0 Cr 59.0 Cr 50.0 Cr 46.0 Cr 44.0 Cr 48.0 Cr 28.0 Cr 19.0 Cr 20.0 Cr 41.0 Cr 31.0 Cr 31.0 Cr 17.0 Cr 12.0 Cr 6.0 Cr
Cumulative Cost 33.0 Cr 103.0 Cr 209.0 Cr 347.0 Cr 497.0 Cr 645.0 Cr 728.0 Cr 783.0 Cr 831.0 Cr 943.0 Cr 1056.0 Cr 1148.0 Cr 1235.0 Cr 1294.0 Cr 1344.0 Cr 1390.0 Cr 1434.0 Cr 1482.0 Cr 1510.0 Cr 1529.0 Cr 1549.0 Cr 1590.0 Cr 1620.0 Cr 1652.0 Cr 1669.0 Cr 1681.0 Cr 1687.0 Cr
Cumulative Percentage Completion 1.95% 6.11% 12.39% 20.60% 29.44% 38.21% 43.18% 46.40% 49.24% 55.88% 62.60% 68.04% 73.19% 76.68% 79.65% 82.40% 84.98% 87.85% 89.52% 90.66% 91.82% 94.24% 96.06% 97.92% 98.94% 99.66% 100.00%
1800.0 Cr
831.0 Cr Row 31
800.0 Cr 783.0 Cr
728.0 Cr
645.0 Cr
600.0 Cr
497.0 Cr
400.0 Cr 347.0 Cr
209.0 Cr
200.0 Cr
103.0 Cr
33.0 Cr
0.0 Cr
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
Ashoka Buildcon Ltd.
Name of Project: Construction of Eight - Lane Vadodara Kim Expressway, Package IV from km. 279.000 to km. 292.000 (Ankaleshwar to Section) in the State of Gujarat Under NHDP Phase VI on Hybrid Annuity mode (Phase IA - Package 4).
Description Unit Total As on Nov- Balance Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20 Feb-20 Mar-20 Apr-20 May-20 Jun-20 Jul-20 Aug-20 Sep-20 Oct-20 Nov-20
18
Ashoka Buildcon Ltd.
Road Work
Earth work in Embankment & SG
1 (Including Fly Ash) m3 4,153,146 - 4,153,146 105,779 463,671 624,086 863,567 758,393 373,330 72,365 39,696 45,262 227,619 144,787 123,051 140,847 143,305 27,390 - - - - - - - - -
3 Granular Sub Base m3 90,537 - 90,537 - - 5,454 12,338 16,936 14,668 5,271 1,747 1,677 3,912 - 9,873 17,192 1,471 - - - - - - - - - -
4 Dry Lean Concrete m3 90,686 - 90,686 - - - - 3,921 9,404 5,346 1,069 1,782 11,361 15,893 18,021 17,222 6,667 - - - - - - - - - -
5 Plain Quality Concrete m3 164,326 - 164,326 - - - - - 11,907 4,517 - - - 11,763 12,050 30,165 16,508 11,179 14,230 16,590 17,328 8,385 2,795 497 2,979 497 -
Structure work -
1 M-15 m3 179 - 179 - - 12 37 36 37 18 6 6 27 - - - - - - - - - - - - - -
2 M-20 m3 4,332 - 4,332 13 62 108 125 - - - - - - 171 171 177 177 165 177 171 177 86 29 29 171 727 806
3 M-25 m3 - - - - - - - - - - - - - - - - - - - - - - - - - - -
4 M-30 m3 - - - - - - - - - - - - - - - - - - - - - - - - - - -
5 M-35 C 67,671 - 67,671 1,166 7,357 11,429 12,948 13,255 11,334 2,504 1,072 1,061 3,072 999 923 550 - - - - - - - - - - -
6 M-40 m3 5,115 - 5,115 - - - - - - - - - - - - - - - - - - - - - - 1,662 1,737
7 M-50 m3 3,220 - 3,220 - - - - 522 1,201 613 771 113 -
6 Reinforcement MT 10,261 - 10,261 157 993 1,543 1,748 1,860 1,692 338 145 143 498 239 140 74 - - - - - - - - - 224 234
7 Structural Steel MT 1,148 - 1,100 - - - - 14 426 206 69 69 316 - - - - - - - - - - - - - -
315 1,737 2,409 2,965 3,258 3,271 599 765 669 1,428 1,038 780 789 723 662 692 209 126 60 18 11 65 265 315
Sr Material Unit GSB DLC PQC M-15 M-20 M-25 M-30 M-35 M-35 Pile M-40 M-45 M-50 M-50 Pile
Density 2.250 2.351 5.100 4.136 4.320 4.468 4.975 5.123 5.460 5.963 6.152 6.370 6.763
Sr no.
Highway Qty
1 C&G 123.29 36.39 27.3 34.68 22.12 2.8
3 E/winEmbankment 3,824,320.47 105779.42 463670.5 609173.02 844148.84 697081.33 302887.48 72364.79 31347.94 31347.94 188087.61 137991.75 123050.55 127152.24 90237.07
4 E/winSubgrade 328,825.28 14912.5 19418.5 61311.95 70442.22 8348.17 13913.61 39531.24 6795 13694.85 53067.54 27389.7
3 Embankment +Subgrade 4153145.76 105779.42 463670.5 624085.52 863567.34 758393.28 373329.7 72364.79 39696.11 45261.55 227618.85 144786.75 123050.55 140847.09 143304.61 27389.7 0 0 0 0 0 0 0 0 0 0 0 0
4 GranularSubbase 90537.01 5454.43 12337.57 16935.63 14668.17 5270.5 1746.5 1676.6 3911.6 9872.8 17192.33 1470.88
5 EarthenShoulder 32400 3504 876 5175 3450 3375 2025 3975 7950 1050 1020
6 DLC 90686 3920.8 9404 5346 1069.2 1782 11360.8 15892.95 18021.3 17222.15 6666.8
7 PQC 164326.01 11907.4 4516.6 11763.4 12050.35 30165.25 16508 11179 14230.4 16589.88 17328.22 8384.63 2794.88 496.5 2979 496.5 2936
1 M15 179 11.93 36.99 35.8 36.99 17.9 5.97 5.97 27.45
2 M20 4331.99 13.13 61.53 108.33 125 171 171 176.7 176.7 165.3 176.7 171 176.7 85.5 28.5 28.5 171 726.74 805.67 688.52 104.47
3 M35 67670.81 1166.48 7357.45 11428.78 12947.73 13255.24 11334.46 2503.54 1072.39 1060.66 3072.4 998.7 922.92 550.06
4 M40 70705.37 1749.42 8264.05 9617.98 10863.27 10512.85 10441.32 3675.1 823.56 823.56 2636.44 1430.29 589.66 603.78 603.78 564.82 19.48 1662.38 2226.68 2097.15 961.36 538.44
5 M50 86413 2657.14 5543.64 8300.08 4545.26 1515.09 1515.09 8566.56 8812.68 6643.81 7138.04 7402.86 6967.59 7569.06 4383.96 1413.13 662.35 220.78 220.78 798.71 561.89 406.22 204.6 341.98 21.7
A B C D E F G H I J K L M N O P Q R S T U V W X Y Z AA AB AC AD
1 Engineer/Support Staff 83 83 83 83 83 83 83 83 83 83 83 83 83 83 83 83 83 83 83 83 83 83 83 83 83 83 83 83
2 Mate 145 15 58 85 127 128 114 39 10 13 62 79 98 145 68 25 27 32 33 16 5 1 6 1 3 6 4 3
Skilled Mazdoor - - 36 82 165 393 171 26 35 178 380 478 775 335 160 203 237 248 120 40 7 43 7 40 42 32 21
3 775
4 Mazdoor 3,031 317 1,391 2,054 3,002 3,031 2,466 805 230 279 1,369 1,603 1,981 2,843 1,355 455 474 553 578 279 93 17 99 17 12 98 12 12
5 26.5 / 20 mm Aggregate MT 228,221 1,740 9,316 12,571 16,198 21,668 27,328 11,723 3,186 3,804 19,692 21,988 21,703 21,159 11,782 5,590 5,718 3,346 1,151 541 180 180 693 1,835 2,102 1,806 886 336
6 10 mm Aggregate MT 214,979 1,160 6,210 8,380 10,781 14,010 22,470 9,238 2,005 2,344 11,915 18,181 17,915 25,637 14,424 8,623 10,054 9,535 8,417 4,062 1,354 338 1,773 1,439 1,399 2,500 589 224
7 Dust / Crushed Sand / Natural Sand MT 377,816 2,413 12,941 17,497 21,613 26,683 40,566 16,081 3,485 4,068 19,976 30,333 30,111 43,361 23,836 13,872 16,180 15,817 14,382 6,945 2,315 554 2,971 2,753 2,798 4,702 1,107 454
8 Reinforcement Steel MT 20,433 265 1,420 1,913 2,406 2,664 2,734 975 310 309 1,298 1,022 741 754 728 685 690 399 128 60 20 20 73 202 239 209 118 51
9 Structural Steel MT 1,111 - - - - 14 431 208 69 69 319 - - - - - - - - - - - - - - - - -
Ashoka Ankleshwar Manu
Name of Project: Construction of Eight - Lane Vadodara Kim Expressway, Package IV from km. 279.000 to km. 292.000 (Anka
Equipment Deplo
Sr. no Machinery Total Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19
A B C D E F G H I J K L M
1 Excavator 31 4 17 22 31 31 31 31 31 31 31
2 Tipper 229 29 126 165 229 229 229 229 229 229 229
3 Backhoe 20 2 11 14 20 20 20 20 20 20 20
4 Soil Compactor 20 2 11 14 20 20 20 15 12 12 12
5 Motor Grader 17 2 9 12 17 17 17 17 17 17 17
6 Dozer Machine 4 1 2 3 4 4 4 4 4 4 4
7 Water Tanker 32 4 17 23 32 28 28 28 28 28 28
17 TCM 850 1 - - - 1 1 1 1 1 1 1
18 TCM 1600 1 - - - 1 1 1 1 1 1 1
19 TCM 1800 1 - - - 1 1 1 1 1 1 1
20 Chilling Plant 2 1 2 2 2 2 2 2 2 2 2
25 Tandom Roller 3 1 2 2 3 3 3 3 3 3 3
26 Transit Mixer 34 9 11 17 18 21 24 34 34 34 34
27 Concrete Pump 3 1 1 2 2 3 3 3 3 2 2
30 TMR 6 2 3 4 5 5 6 6 6 2 1
32 DG 500 Kva 2 - 1 2 2 2 2 2 2 2 2
33 DG 250 Kva 2 1 1 1 2 2 2 2 2 1 2
34 DG 160/200 Kva 1 1 1 1 1 1 1 1 1 1 1
35 DG 125 Kva 21 6 9 14 16 18 20 20 20 20 20
36 DG 82 Kva 3 1 1 2 2 3 3 3 3 3 3
38 DG 40 Kva 4 1 2 4 4 4 4 4 4 4 4
39 DG 25/20/15/10 Kva 4 1 2 4 4 4 4 4 4 4 4
40 Hydra Crane 12 3 4 6 6 7 8 12 10 10 10
41 Tractor 18 5 6 9 9 11 13 18 15 2 2
42 Trailer 3 1 1 2 2 2 2 3 3 3 3
48 Dewatering Pump 10 3 3 5 5 6 7 10 9 9 9
50 Mini Roller 4 1 1 2 2 2 3 4 4 4 4
52 Staff Bus 1 1 1 1 1 1 1 1 1 1 1
53 Tipper 06 Wheel 4 1 2 3 3 4 4 4 4 4 4
54 Tower Light 10 3 3 5 5 6 7 10 10 10 10
55 Vibrator Diesel/Electric 15 4 5 8 8 9 11 15 15 15 15
56 Boom Placer 3 1 1 2 2 3 3 3 3 3 3
58 Crane 75 T ACE 14 4 6 10 11 12 13 14 14 14 14
60 Segment Lifter 5 2 2 3 4 4 5 5 5 5 5
61 Girder Launcher 2 1 1 1 2 2 2 2 2 2 2
Page 24 of 42
Ashoka Ankleshwar Manu
Name of Project: Construction of Eight - Lane Vadodara Kim Expressway, Package IV from km. 279.000 to km. 292.000 (Anka
Equipment Deplo
Sr. no Machinery Total Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19
A B C D E F G H I J K L M
63 JCB 4 1 2 3 3 3 4 4 4 4 4
69 Boom Lifter 2 1 1 1 2 2 2 2 2 2 2
70 Scissors Lifter 2 1 1 1 2 2 2 2 2 2 2
71 Tower Crane 4 1 2 3 3 3 4 4 4 4 4
73 Lowbed Trailor 1 1 1 1 1 1 1 1 1 1 1
77 Motor Boat 3 1 1 2 2 3 3 3 3 3 3
78 Utility 4 1 2 3 3 3 4 4 4 4 4
79 Diesel Tanker 2 1 1 1 2 2 2 2 2 2 2
80 Tata 709 4 1 2 3 3 3 4 4 4 4 4
81 Roller 1 1 1 1 1 1 1 1 1 1 1
82 Compressor 3 1 1 2 2 3 3 3 3 3 3
83 Wheel Loader 2 1 1 1 2 2 2 2 2 2 2
84 Cement Silo 16 5 7 11 12 14 15 16 16 16 16
85 Tug 100HP 1 1 1 1 1 1 1 1 1 1 1
86 Tug 250HP 1 1 1 1 1 1 1 1 1 1 1
87 Motor Cycle 20 20 20 20 20 20 20 20 20 20 20
88 Bulker 1 1 1 1 1 1 1 1 1 1 1
89 Pile breaker 1 1 1 1 1 1 1 1 1 1 1
90 Cutting Machine 29 9 13 20 22 25 27 28 29 29 29
91 Bending Machine 23 7 10 16 18 19 22 22 23 23 23
92 Welding Machine 49 15 21 34 38 42 46 48 49 49 49
93 Sander 40 12 17 27 31 34 38 39 40 40 40
94 Jack 27 T15 42 13 18 29 32 36 39 41 42 42 42
95 Jack 19 T15 6 2 3 4 5 5 6 6 6 6 6
Page 25 of 42
eshwar Manubar Expressway Pvt Ltd.
292.000 (Ankaleshwar to Manubar Section) in the State of Gujarat Under NHDP Phase VI on Hybrid Annuity mode (Phase IA - Package 4).
uipment Deployment Schedule
Oct-19 Nov-19 Dec-19 Jan-20 Feb-20 Mar-20 Apr-20 May-20 Jun-20 Jul-20 Aug-20 Sep-20 Oct-20 Nov-20 Dec-20 Jan-21 Feb-21
N O P Q R S T U V W X Y Z AA AB AC AD
31 31 31 31 31 31 31 31 31 31 31 31 31 31 31 31 31
229 229 165 24 24 24 24 24 24 24 24 24 24 24 24 24 24
20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20
15 16 12 11 8 7 7 7 6 6 4 4 4 4 4 4 4
17 17 17 17 16 17 17 17 17 17 17 17 17 17 17 17 17
4 4 4 4 4 3 3 3 3 3 3 3 3 2 2 2 2
28 28 28 28 28 28 28 28 28 28 28 28 28 28 28 28 28
4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 - - -
1 1 1 1 1 1 1 - - - - - - - - - -
4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
2 1 2 1 2 2 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 - - - - - - - - -
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 - -
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 - -
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 - -
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 - -
2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
3 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
34 34 34 34 34 34 34 34 34 34 34 7 8 6 6 6 6
2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
2 3 4 4 2 2 2 1 1 1 1 1 1 1 1 1 1
2 4 5 4 3 3 2 2 2 2 2 2 2 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
1 1 2 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
20 20 20 20 20 20 20 20 20 20 20 20 20 20 6 6 6
3 2 2 2 1 1 1 1 1 1 1 1 1 1 1 1 1
4 4 4 4 4 4 4 4 4 4 4 4 4 4 3 3 3
4 4 4 4 4 4 4 4 4 4 4 4 4 4 3 3 2
10 8 9 9 9 9 9 9 8 5 1 1 2 2 2 2 2
2 12 14 13 14 14 13 13 12 8 2 1 2 3 2 2 2
3 2 2 2 2 2 2 2 2 1 1 1 1 1 1 1 1
2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
9 7 8 7 8 8 7 7 6 4 1 1 1 2 1 1 1
4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
3 3 3 3 3 3 3 3 3 3 3 3 3 3 2 2 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10
15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15 15
3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8
14 14 11 10 9 6 5 4 4 4 4 4 4 3 3 3 3
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
5 5 5 5 5 5 5 5 5 5 5 4 3 2 2 1 1
2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Page 26 of 42
eshwar Manubar Expressway Pvt Ltd.
292.000 (Ankaleshwar to Manubar Section) in the State of Gujarat Under NHDP Phase VI on Hybrid Annuity mode (Phase IA - Package 4).
uipment Deployment Schedule
Oct-19 Nov-19 Dec-19 Jan-20 Feb-20 Mar-20 Apr-20 May-20 Jun-20 Jul-20 Aug-20 Sep-20 Oct-20 Nov-20 Dec-20 Jan-21 Feb-21
N O P Q R S T U V W X Y Z AA AB AC AD
4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
4 4 4 4 4 4 4 4 4 4 2 2 2 1 1 1 1
2 2 2 2 2 2 2 2 2 2 2 2 1 1 1 1 1
2 2 2 2 2 2 2 2 2 2 2 2 1 1 1 1 1
4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
16 16 16 16 16 16 16 16 16 16 16 16 16 16 16 16 16
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
29 29 29 29 29 29 29 29 29 29 29 29 29 29 29 29 29
23 23 23 23 23 23 23 23 23 23 23 23 23 23 23 23 23
49 49 49 49 49 49 49 49 49 49 49 49 49 49 49 49 49
40 40 40 40 40 40 40 40 40 40 40 40 40 40 40 40 40
42 42 42 42 42 42 42 42 42 42 42 42 42 42 42 42 42
6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6
25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25
8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8
Page 27 of 42
Ashoka Buildcon Ltd.
Name of Project: Construction of Eight - Lane Vadodara Kim Expressway, Package IV from km. 279.000 to km. 292.000 (Ankaleshwar to Section) in the State of Gujarat Under NHDP Phase VI on Hybrid Annuity mode (Phase IA - Package 4).
As on Nov-
Description Unit Total 18 Balance Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20 Feb-20 Mar-20 Apr-20 May-20 Jun-20 Jul-20 Aug-20 Sep-20 Oct-20 Nov-20
Ashoka Buildcon Ltd.
Road Work
Earth work in Embankment & SG
1 m3 4,153,146 - 4,153,146 105,779 463,671 624,086 863,567 758,393 373,330 72,365 39,696 45,262 227,619 144,787 123,051 140,847 143,305 27,390 - - - - - - - - -
(Including Fly Ash)
3 Granular Sub Base m3 90,537 - 90,537 - - 5,454 12,338 16,936 14,668 5,271 1,747 1,677 3,912 - 9,873 17,192 1,471 - - - - - - - - - -
4 Dry Lean Concrete m3 90,686 - 90,686 - - - - 3,921 9,404 5,346 1,069 1,782 11,361 15,893 18,021 17,222 6,667 - - - - - - - - - -
5 Plain Quality Concrete m3 164,326 - 164,326 - - - - - 11,907 4,517 - - - 11,763 12,050 30,165 16,508 11,179 14,230 16,590 17,328 8,385 2,795 497 2,979 497 -
Structure work -
1 M-15 m3 179 - 179 - - 12 37 36 37 18 6 6 27 - - - - - - - - - - - - - -
2 M-20 m3 4,332 - 4,332 13 62 108 125 - - - - - - 171 171 177 177 165 177 171 177 86 29 29 171 727 806
3 M-25 m3 - - - - - - - - - - - - - - - - - - - - - - - - - - -
4 M-30 m3 - - - - - - - - - - - - - - - - - - - - - - - - - - -
5 M-35 m3 67,671 - 67,671 1,166 7,357 11,429 12,948 13,255 11,334 2,504 1,072 1,061 3,072 999 923 550 - - - - - - - - - - -
6 M-40 m3 5,115 - 5,115 - - - - - - - - - - - - - - - - - - - - - - 1,662 1,737
7 M-50 m3 3,220 - 3,220 - - - - 522 1,201 613 771 113 -
6 Reinforcement MT 10,261 - 10,261 157 993 1,543 1,748 1,860 1,692 338 145 143 498 239 140 74 - - - - - - - - - 224 234
7 Structural Steel MT 1,100 - 1,100 - - - - 14 426 206 69 69 316 - - - - - - - - - - - - - -
- -
Arvind Technocrat Engineers Pvt - -
Ltd
Structure work - -
1 M-40 m3 65,590 65,590 1,749 8,264 9,618 10,863 10,513 10,441 1,576 2,922 1,873 2,380 837 584 604 604 390 - - - - - - - - 490
2 M-50 m3 82,689 82,689 - - - 2,657 5,022 7,099 1,321 3,964 3,964 7,953 8,042 6,531 7,341 7,424 6,968 7,690 2,317 1,398 662 201 120 718 456 410
3 Reinforcement MT 30,546 30,546 360 1,702 1,981 2,785 3,200 3,613 597 1,419 1,202 2,129 1,829 1,466 1,637 1,654 1,516 1,584 477 288 136 41 25 148 94 185
Total Material requirement 5,414 29,128 39,513 49,380 62,701 98,142 30,220 16,569 16,225 50,072 76,149 76,986 109,904 60,103 34,232 40,562 35,646 35,451 17,129 5,674 1,203 7,221 6,243 6,407
1 Granular Sub Base - GSB MT 203,708
2 Cement MT 132,552 -0 -0
3 31.5 mm Aggregate MT 111,084
4 26.5 mm Aggregate MT 79,532
5 20 mm Aggregate MT 177,110
6 10 mm Aggregate MT 216,909
7 Crushed Sand MT 269,861
8 Natural Sand MT 70,189
9 GGBS MT 27,490
10 Flyash MT 37,464 30,443
11 Admixture MT 1,264
12 Reinforcement Steel MT 40,806
13 Structural Steel MT 4,541
Sr Material Unit GSB DLC PQC M-15 M-20 M-25 M-30 M-35 M-35 Pile M-40 M-45 M-50 M-50 Pile
Density 2.250 2.351 5.100 4.136 4.320 4.468 4.975 5.123 5.460 5.963 6.152 6.370 6.763