6.0 Pipe bedding and foundation
1 brovide finm support for pipe, proper bedding under the pipe must be provided, During the
french excavation, a pipe bedding thickness of at Teast 1S cm must be provided. In case of very
Poor native soils (Silt, clay or mud) an additional 15 em thick foundation is to be excavated ang
provided below the bed. The selected backfill material should be placed in the foundation and
bedding layers and thoroughly compacted by the plate vibrators ot by hand tamping. Wetting of
sand bedding/foundation meteria prior to compaction will improve and facilitate the achievement
of the degree of compaction required,
Pipe laying should always take place in dry trenches. It is not acceptable to lay pipes in flooded
trenches. The contractor should provide the necessary dewatering equipment to enable installation
ta croveed in dry trench, Dewatering equipment should be removed and pumps tumed off only
afer completion of the pipe zone backfilling, and sufficient backfill has been provided to prevent
Pipes from floating if the normal ground water level is above the pipe invert
Fricr to lowering the pipe into the trench, the top 2-3 em of the compacted bedding should be
lightly raked, and small holes should be dug under each joint location so the pipé does not rest on
the joints, The bedding material should provide firm and continuous support over the entire length
of the pipe, excluding the joints areas,
ue contractor should lower the pipe into position after chesking the proper levels and alignment of
the pipeline,
6.1 Inserting the pipe in the coupling
Joints should be made inside the trench following the procedures shown in figures 18 and 19. A
Hee cae with rubber lining must be fixed on the installed pipe at the home line in order to stop
system if they are not removed before the hydrostatic test. Before insertion, the twa pipes should be
Perfectly aligned and leveled to avoid any damage to the rubber rings.
BF s212%00 Manual for underground Piping System] Kemoak8 OW OTN soe. OWE ALON JA0K COKE ow EACH soe)
eee Se SRS [
COUR sip.
—/
Te Shen tae,
HP axa co seit SPEOT Gite 40 oF courenc
ad oe RT iS AB
Figuee 18: Pipe Jointing using a”’come along” jack
0104 sewe asraueo
rai
JOWNG PPE WiTH BLLLDOZER
Figure 295.5 Thrust boring and micro-tunneting installations
This method is used when the ground above or around the pipe cannot be disturbed. This isthe case
for crossings under highways, railways, airport runways, rivers etc, This method might be
economical for very deep sewer lines where the cost of opened trench excavations may become
excessive due to the ground conditions where extensive sheet pilings and dewatering might be
required,
‘Two types of pipes are suitable for this kind of application. Special jacking pipe with flush Reka
couplings are available for direct jacking. Also, standard pipes can be provided in short lengths
Suitable for jacking inside a concrete jacket. In this case, the outer conerete pipe takes the jacking
load while the inner pipe provides the corrosion resistance and the required joint tightness. For
typical configurations see the figures below. When pipes are “jacked”, an 18-20 mm thick plywood
or similar compressible material must be placed between the pipe and joint ends to avoid point
loads during the jacking operations.
Figure 12: Thrust boring pipes
a Installation Manual for underground Piping System| XemrocéInstallation Type
Figures
installation Manual for underground Piping System] Kemrock