Click OK, wait for the hardware upgrade to complete, and restart
the software.
After the software restarts, it will continue to prompt "The
version of the FTC is too low to be processed normally. After
clicking OK, the hardware will be automatically upgraded." Click
"OK" as prompted to upgrade the program of the FTC
7、 Processing can be started after all prompts and alarms are cleared.
edge inspection
and cut off
Normal cut
·
left right
coordinate coordinate
of X of X
Sheet width
3. Added batch film removal function. Users can change the number
of batch film removal contours according to actual needs. After
film cutting is enabled, batch film removal will be completed
first and then the sheet will be cut.
1. New functions :
1) Added embedded layout function (NEST dongle is required), as
shown in the figure
Nesting interface
2. Optimization project:
1) The air movement trajectory has been optimized, and the
acceleration is faster.
content
New features :
1. New functions :
1、Added processing count management module (after the count is
completed, the following three states are provided: 1. Do not
do anythingaction.
2. A dialog box will pop up. 3. It is forbidden to continue
processing. )
Select the
change button
and change
the opening
way to:
SC2000
10. New speed units inch/s and inch/min, acceleration unit inch/s2,
as shown in the figure
11. Add the function of cleaning nozzle, enter through the advanced
menu----clean nozzle, as shown in the figure