Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 5

METHOD OF STATEMENT FOR ANTI TERMITE

The method statement for anti-termite defines the procedure for the sequence of works for surface
treatments and termite control after leveling/compaction of the filled soil and before
polythene/damp proof membrane is laid, considering all the necessary safety and quality aspects of
the work activities.

Anti-termite treatment is a process in which soil treatment is applied to a building in the early stages
of its construction. The purpose of anti-termite treatment is to provide the building with a chemical
barrier against the sub-terrain termites. The anti-termite treatment being a specialized job, calls for
thorough knowledge of the chemicals, soils, termite to be dealt with and the environmental
conditions, in order to give effective treatment and lasting protection to the property undergoing
treatment. It is therefore imperative that the works of anti-termite treatment should get executed
through specialized agencies only. The pre-constructional soil treatment is required to be applied
during the construction stages (usually under the concrete blindings) of the sub-structure up to the
subbase level.

1. PURPOSE
The purpose of this Method Statement for Anti-termite is to define the procedure for the sequence
of works for surface treatments and termite control after leveling/compaction of the filled soil and
before polythene/damp proof membrane is laid, considering all the necessary safety and quality
aspects of the work activities.

2. SCOPE OF WORKS
Termite control works for the complete project.

3. REFERENCES
3.1. Contract documents
1. Project Specification
2. Contract Drawings
3.2. Contractors Submittal
1. Project Quality Plan
2. Project Safety Plan
3. Material approvals (MAT)
4. Related method statements (MET)

4. DEFINITIONS / ABBREVIATIONS
4.1. Definition
1. Project -(Replace with project name)
2. Client -(Replace with clients name)
3. Developer -(Replace with developers name)
4. Consultant -(Replace with consultants name)
5. PMC -(Replace with PMC name)
6. Contractor -(Replace with contractors name)
7. Sub-contractor -(Replace with sub-contractors name)
8. Supplier -(Replace with suppliers name)
4.2. Abbreviations
1. Engineer – Representative of “Name of engineering consultancy”
2. ICL – Inspection Check List
3. IR – Inspection Request
4. ITL -Independent Testing Laboratory
5. ITP – Inspection and Test Plan
6. ITR -Inspection & Test Requests
7. MAT – Material Submittal
8. MEP – Mechanical Electrical Plumbing
9. MET – Method Statement
10. MIR – Material Inspection Request
11. MSDS – Material Safety Data Sheet
12. PPE -Personal Protective Equipment
13. PQP -Project Quality Plan
14. PTW -Permit To Work ( Working at Height or enclosed spaces)
15. RA -Hazard Identification and Risk Assessment
16. RFIA – Request for Inspection and Approval
17. SPD – Shop Drawing
18. TBM – Temporary Bench Mark

5. RESPONSIBILITIES
5.1. Project Manager
1. Ensuring that the project works in his zone are carried out in accordance with Company policies
and in accordance with the requirements of this Quality plan.
2. Ensuring the full compliance of subcontractors with Company Quality policies and with the
requirements of this Quality plan.
3. To ensure that the subcontractor performs the work as per the contract requirements.
4. To co-ordinate with the Construction Manager, Project Engineer, Safety Engineer, Foreman and
Surveyor for a safe and proper execution of the works.
5. To guide specific attention to all safety measures in co-ordination with the safety officer/engineer.
5.2. Construction Manager
1. Ensure area is ready and safe to start the works.
2. Arrange the required visit by the termite treatment subcontractor.
3. Ensure the works are carried out according to the specification, quality and approved shop
drawings.
4. Liaise and co-ordinate with the Project Manager for the agreed sequence of works with respect to
the construction programme.
5. Allocation of required manpower through co-ordination with the Project Manager.
6. Ensure that the risk assessments for the work is understood by all and implemented on site.
7. Provide sufficient and safe access for operatives, trucks and pumps.
8. Take precautionary measures with regards to protecting works from hot weather, wind, rain, and
sun.
5.3. Project Engineer
1. The engineer shall carry out his duties in a manner that shall be co-ordinated by the project
manager on a daily basis, and shall ensure proper distribution of the workforce and equipment at
required locations.
2. To coordinate with the subcontractor on location and the quantity of area to be treated.
3. To co-ordinate with the Safety Officer to maintain safe working and proper housekeeping of the
site. To comply with the safety measures and ensure that all Safety Officer Teams are aware of the
same to prevent accident and loss.
4. To monitor and check all activities and ensure that works shall be carried out according to
specifications, quality and approved drawings.
5. To inform the QC Inspector of the areas ready for inspection.
5.4. QA/QC Engineer / Inspector
1. Ensuring that Consultant/Client inspection requests are implemented.
2. Compilation of all necessary quality control checklists
3. Assisting Consultants during the Inspections.
4. Coordinating with the third party lab regarding tests and results.
5. The control of work performance by means of checking the work before consultants’ inspection
and issuing RFIs & punch lists as necessary.
6. Completion of documentation to verify the work performed.
7. Controlling all inspection activities on-site in line with ITPs.
5.5. Surveyor
1. To establish benchmarks from agreed reference points, provide required setting out and level
markings and follow up with regular checks.
2. Co-ordinate with the Project Engineer / Foreman and ensure the approved shop
drawings/construction drawings shall be implemented properly.
3. Maintain survey details and reports, periodically check the progressing works and advise the
project manager of any deviation from the drawings.
5.6. HSE Engineer/Officer
1. Provide the risk assessments for the works in hand.
2. To ensure implementation of all safety measures related to the nature of works being carried out,
and in accordance with the Project Safety Plan.
3. To ensure that all the persons involved in the works are aware of their responsibilities and that
they have enough understanding of the safety procedures.
4. The safety officer in co-ordination with the Project Manager shall ensure that all the implemented
safety measures are effective enough to maintain safe working on the site.
5. To maintain continuous inspections of the site activities, advise and train persons on a daily basis
to prevent accidents and personnel injury.
6. To give special concern to housekeeping, and ensure that the site is maintained clean and tidy.
7. To ensure all the relevant safety sign boards for different works are in place.
5.7. Foremen/ Works Supervisor
1. Ensure the works are progressed in the sequence as agreed with the Project Manager.
2. Liaise with the Project / Construction Manager for the allocation of the work force, ensuring
adequate manpower is available.
3. Liaise with the site manager to ensure all the required plant/materials are available to construct
the works.
4. Full-time supervision shall be required to ensure the works are carried out in accordance with
specifications, quality and approved drawings.

6. EQUIPMENTS/ TOOLS / MANPOWER


6.1. Equipments / Tools
1. 500 liter Tank
2. Pump Machine
6.2. Manpower
1. Project Manager
2. Project Engineer
3. Safety Engineer/Officer
4. Technician
5. Helpers
6.3. Materials
1. Contra Insect from Frunol Delicia (Germany)
2. Water
Note: Quantity of manpower, materials, and types of equipment shall be submitted on the daily
progress report.

7. PROCEDURE
7.1. Anti-Termite Treatment Stages
1. The anti-termite treatment works shall be carried out in four stages during the construction of the
building, which is as under:
a. Treatment to Soil under substructure slabs.
b. Treatment to Soil along the External Perimeter of the Building
2. Mixing Chemical
3. For every liter of chemical 49 liters of water shall be mixed. In plain horizontal surfaces, a 5ltr/m2
dose shall be applied. For trenches and edges, a 6ltr/m dose shall be used.
4. Chemical Application
5. The one 5 liter dose Chemical shall be added to the 500-liter tank. The pump machine shall be set
to a 20bar pressure that shall produce a flow of 5 liters per 15seconds. So, in 15 seconds an area of
1m2 will be covered. For the linear meter applications, the pump shall be set to 15 bar pressure to
produce a 6 liter per 20second flow and this shall cover a distance of one linear meter.
6. Treatment to Soil under Slabs at Plinth Level
7. The treatment of soil under slabs at plinth level shall be carried out into the following sequence
7.2. Foundation
1. A trench 200 x 200mm x total perimeter, along with proposed foundation, shall be excavated.
2. Application of Anti-termite along trench shall be done with 6 liters per linear meter of (Approved
anti-termite material) mixed with water using 1:49 ratio.
3. Backfill of trench up to existing foundation level shall be done in preparation for the second
application of Anti-termite.
4. Upon completion, 5 liters per square meter of (Approved anti-termite material) mixed with water
(1:49 ratio) shall be applied.
5. On completion, the treated area shall remain undisturbed for two hours. After two hours
polyethylene sheets can be placed over the treated area.
6. Preparation for structural works shall be done only within 24 hours for the anti-termite
application to remain effective.
7.3. Under Pile Cap
1. On the cleared and leveled ground the anti-termite treatment shall be done using 5 liters per
square meter of (Approved anti-termite material) mixed with water using a 1:49 ratio.
2. On completion, the treated area shall be covered with polyethylene sheets after two hours from
application.
3. Preparation for structural works shall be done only within 24 hours for the anti-termite
application to remain effective
7.4. Ground Beam/PCC
1. Application of Anti-termite shall be done at the rate of 5 liters per square meter of (Approved
anti-termite material) mixed with water at a ratio of 1:49 and covered by polythene sheets after 2
hours.
2. Preparation for structural works shall be done only within 24 hours for the anti-termite
application to remain effective
3. When the ground beam/pick shall be cast, excavate a trench 200 x 200mm along the perimeter of
ground beam/ PCC. The Anti-termite treatment shall be done with 6 liters per linear meter of
(Approved anti-termite material) mixed with water using a 1:49 ratio.
4. After completion of the anti-termite application, the trench shall be backfilled.
7.5. Slab on Ground
1. Excavate a trench 200 x 200mm along the perimeter of the slab.
2. Application of Anti-termite shall be done with 6 liters per linear meter of (Approved anti-termite
material)  mixed with water using 1:49 ratio. After completion, the trench shall be backfilled and
leveled.
3. Application of Anti-termite shall be done with 5 liters per square meter of (Approved anti-termite
material)  mixed with water using 1:49 ratio along the substructure slab area.
4. On completion, the treated area shall be covered with polyethylene sheets after two hours from
application
5. Treatment to Soil along the External Perimeter of the Building: Soil around utility pipe openings,
floor drains, expansion joints, electrical conduit entry point shall be sprayed at a rate of 6liters/linear
meter with (Approved anti-termite material) mixed in 1:49 ratio with water.

8. HSE PRECAUTIONS
1. The applicator must follow the HSE precautions before spraying the pesticide chemical.
2. The applicator shall wear the protective gloves, protective glasses, protective boots or shoes and
protective clothing during mixing, loading, and application.
3. The applicator shall use a respirator with filter A or A/P for the protection of breath.

9. ATTACHMENTS
9.1. Inspection Checklists
9.2. Inspection Test Plan
9.3. Risk Assessment
9.4. Technical Data sheet (TDS)

You might also like