Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 3

CENTRAL TOOL ROOM LUDHIANA

NSQF (LEVEL-6) Final Exam

Course: ADMMA (____Batch) Max Marks: 60


Subject: Machine Maintenance Time : 2 hrs
Name: Roll No :

SET-A

Task 01:
a) Write down the various parts of Lathe Machine.
b) Let’s suppose spindle is not moving find out the causes of this fault.

MARKS DISTRIBUTION
Parts of Machines Fault diagnosis Steps for Troubleshooting TOTAL
10 20 30 60
CENTRAL TOOL ROOM LUDHIANA
NSQF (LEVEL-6) Final Exam

Course: ADMMA (____Batch) Max Marks: 60


Subject: Machine Maintenance Time : 2 hrs
Name: Roll No :

SET-B

Task 01: Discuss various steps for preventive maintenance of the Conventional and CNC Machine.

MARKS DISTRIBUTION
Maintenance of Conventional Machines Maintenance of CNC Machines TOTAL
30 30 60
CENTRAL TOOL ROOM LUDHIANA
NSQF (LEVEL-6) Final Exam

Course: ADMMA (___Batch) Max Marks: 60


Subject: Machine Maintenance Time : 2 hrs
Name: Roll No :

SET-C

Task 01:
a) Run the 3 HP, 3 phase induction motor with suitable starter and draw its control and power
diagram.
b) How you will change the direction of this motor?

MARKS DISTRIBUTION
Control Diagram Power Diagram Step to change the direction of Motor TOTAL
20 20 20 60