Professional Documents
Culture Documents
EAC Project
EAC Project
INTRODUCTION
Need of estimating:
1) To know the approximate time limit.,
2) To invitation of tender.
3) To keep control over expenditure.
4) To draw up construction schedule and programme.
5) To obtain administrative approval and technical sanction.
This is an inexact estimate to find out a rough cost in a short time which
enables the authority concerned to consider the financial aspect of the scheme, for according
sanction to the same. Such an estimate is framed after knowing the rate of similar works and
from practical knowledge in various ways for various types of works such as:
4. Bay method,
In fixing the plinth area rate, careful observation and necessary enquiries are made in
respect of quality and quantity aspect of materials and labor, type of foundation, height of
building, roof, wood work, fixtures, number of stores etc.
As per IS 3861-1966, the following areas include while calculating the plinth area of
building:
TYPES OF ESTIMATES:
Area of walls at floor level.
Internal shafts of sanitary installations not exceeding 2.0 sq., lifts, air-conditioning ducts etc.,
Area of barsati at terrace level: Barsati means any covered space open on one side,
constructed on one side, constructed on terraced roof which is used as shelter during rainy
season.
Porches of non-cantilever type.
Area of lofts.
Unenclosed balconies.
This estimation is done by selecting the price of 1 square meter area of a building.
It is mainly adopted for calculating the cost of following buildings:
Office Buildings.
Residential Buildings.
School Buildings.
Apartment/Flat Buildings.
Hospitals.
This method is considered as the best method for calculating the cost of new
buildings. In case of multi-storeyed buildings, the following assumptions are to be considered
for the estimation.
1. For 1 square meter area, the cost of all the floors with basement and roof are in equal costs.
Plinth area cost estimate is prepared on the basis of plinth area of the building which
is the area covered by external dimensions of building at the floor level and plinth area rate of
the building which is the cost of similar building with specifications in that locality.
Plinth area estimate is obtained by multiplying plinth area of building with plinth area
rate. For example, if we require plinth area estimate of 100 sq.m in a particular locality and
plinth area rate of a building in the same locality is 2000 per sq.m then plinth area estimate is
100 X 2000 = 200000.
Open areas, courtyards etc. are should not be included in the plinth area. If the
building is multi-storied, plinth area estimate is prepared separately for each floor level.
The length and breadth are measured out to out of walls excluding the plinth offset.
The cost of string course, cornice, corbelling etc., is neglected.
1. For 1 meter cube area the costs of all floors are equal in costs.
1. Ground Floor: The height of ground floor is calculated from the top of the footing to the
middle of the parapet.
2. First Floor: The height of the first floor is calculated from the ground rooftop to the middle
of the parapet.
3. Other Floors: The height of other floors are calculated from floor to floor.
Cube rate cost estimate of a building is obtained by multiplying plinth area with the
height of the building. The height of the building should be considered from floor level to the
top of the roof level. It is more suitable for multi-storied buildings.
The unit rate is calculated by dividing the actual expenditure incurred or cost of
similar building in the nearby locality by the number of units.
In approximate quantity method cost estimate, Total wall length of the structure is
measured and this length is multiplied by the rate per running meter which gives the cost of
the building. Rate per running meter is calculated separately for foundation and
superstructure.
In this method, the main items are taken into account using short-cuts in the
approximate calculation of quantities of main items such as walls, roofs, doors and windows,
and finishes, and the cost is computed by adopting current unit costs for these items. The
grouping of items and fixing their approximate cost requires good judgement and experience.
This method though time-consuming, is more accurate than any of the above approximate
methods.
Then, the approximate cost of building = Number of bays in the building x cost of
one bay. Suitable correction factors may have to be used to take into account the
dissimilarities in end-bay (and in different floors, if applied to multi storeyed construction).
CONCLUSION:
So hereby we have concluded that there are various types for estimating and
they contain various subtypes in them. Estimating is necessary for all engineering work to
estimation quantities of different item of work is calculated and from these quantities cost is
calculated.
REFERENCES:
1. C. Lon Enloe, Elizabeth Garnett, Jonathan Miles, Physical Science: What the
Technology Professional Needs to Know (2000), p. 47.
2. Raymond A. Kent, "Estimation", Data Construction and Data Analysis for Survey
Research (2001), p. 157.
3. James Tate, John Schoonbeck, Reviewing Mathematics (2003), page 27: "An
overestimate is an estimate you know is greater than the exact answer".
4. James Tate, John Schoonbeck, Reviewing Mathematics (2003), page 27: "An
underestimate is an estimate you know is less than the exact answer".
5. A Guide to the Project Management Body of Knowledge (PMBOK Guide) Third
Edition, An American National Standard, ANSI/PMI 99-001-2004, Project
Management Institute, Inc, 2004,