Supervision Consultant Weekly

Report
Construction Supervision Consultancy Services
for Beach Clubs

R03-C07B01
SC Weekly Report No. 44

From 16th December 2022 – 22th December 2022

ARCHIRODON PRIORITY
SAUD CONSULT WEEKLY PROJECT STATUS REPORT AS OF

22 DECEMBER 2022

Design and Build of Coastal Village Beach Clubs

NOTICE TO PROCEED (NTP) 01 January 2022


ORIGINAL END OF CONTRACT (EOC) 16 Months from NTP
CONTRACTORS R03-C07B01 ISLAM KABBANI PARTNERS

1. REVIEWED SUBMITTAL FOR BEACH CLUBS:

Review Time
S.# TRSDC DOCUMENT NO. DOCUMENT TITLE APPROVAL STATUS
(Days)
R03-C07B01-IKP-MAT-ME-0069 Material Submittal - Warning Tape for 3 Accepted with Comments
1
Mechanical Systems
R03-C07B01-IKP-RPT-ST-0005 Compliance sheet to the project performance 3 Revise and Resubmit
2 of structural curtain wall
R03-C07B01-IKP-MTS-ME-0011 Method Statement for Ecology Unit 3 Accepted with Comments
3
Installation
R03-C07B01-IKP-CAL-ST-0006 Structure Calculation for Aluminum Canopy 3 Revise and Resubmit
4

R03-C07B01-IKP-RPT-EN-0013 Indoor Air quality Report till 1st of December, 3 Review Not Required
5 2022
R03-C07B01-IKP-CAL-ST-0009 Load calculation of the Structural Glazed 3 Revise and Resubmit
6 Curtain wall
R03-C07B01-IKP-MAT-CI-0033 Material Submittal for Renderoc HS Xtra 3 Accepted with Comments
“Shrinkage controlled, cementitious high
7
specification repair mortar system” (For
Swimming Pool area)
R03-C07B01-IKP-MAT-CI-0032 Material Submittal for Sika Top - Seal 107 3 Accepted with Comments
8 Protective and Waterproofing Slurry (For
Swimming Pool area)
R03-C07B01-IKP-MAT-CI-0031 Material Submittal For Vetoset CA545 3 Accepted
9 Cementitious Deformable Tile Adhesive (For
Mosaic Tiles)
R03-C07B01-IKP-PLN-TC-0001 Commissioning Plan 3 Accepted with Comments
10

R03-C07B01-IKP-01-ZZ-DWG- TYPICAL VALVE CHAMBER DETAILS 3 Revise and Resubmit


11 ST-10025-DWG
R03-C07B01-IKP-CAL-ST-0005 ALUMINIUM LOUVRE ON ROOF 3 Revise and Resubmit
12

R03-C07B01-IKP-MAT-EL-0030 Lighting fixture Outdoor , via lighting co. 3 Accepted with Comments
13

R03-C07B01-IKP-MTS-AR-0007 Method Statement for Canopy Installation 3 Revise and Resubmit


14

R03-C07B01-IKP-01-ZZ-SDW- EIFS SYSTEM FLOOR-WALL TRANSITION 3 Accepted with Comments


15
AR-20081-DWG DETAILS
R03-C07B01-IKP-01-GF-SDW- F & B Counter Layout size 5700*4850*1100 3 Revise and Resubmit
16
ID-50101-DWG Mm
R03-C07B01-IKP-01-GF-SDW- F & B Counter Section Elevations-01 Size 3 Revise and Resubmit
17
ID-50111-DWG 5700*4850*1100 Mm
R03-C07B01-IKP-01-GF-SDW- F & B Counter Section Elevations-02 Size 3 Revise and Resubmit
18
ID-50121-DWG 5700*4850*1100 Mm
R03-C07B01-IKP-01-GF-SDW- F & B Counter Details Size 5700*4850*1100 3 Revise and Resubmit
19
ID-50131-DWG Mm
R03-C07B01-IKP-01-GF-SDW- Kitchen Sunkinslab Details 3 Revise and Resubmit
20
AR-40056-DWG
R03-C07B01-IKP-01-ZZ-SDW- Mirror elevation & Details 3 Revise and Resubmit
21
AR-10019-DWG
22
23
24
25
26
27
28
29
30
REVIEW REQUESTED BY TRSDC:

S#
1

REVIEWED MATERIAL:

S.# TRSDC DOCUMENT NO. DOCUMENT TITLE STATUS


R03-C07B01-IKP-MAT-CI-0031 Material Submittal For Vetoset CA545 Cementitious
1 Revise and Resubmit
Deformable Tile Adhesive (For Mosaic Tiles)
R03-C07B01-IKP-MAT-CI-0032 Material Submittal for Sika Top - Seal 107 Protective and
2 Accepted with Comments
Waterproofing Slurry (For Swimming Pool area)
R03-C07B01-IKP-MAT-CI-0033 Material Submittal for Renderoc HS Xtra “Shrinkage controlled,
3 cementitious high specification repair mortar system” (For Revise and Resubmit
Swimming Pool area)
4 R03-C07B01-IKP-MAT-EL-0030 Lighting fixture Outdoor , via lighting co. Accepted with Comments
5 R03-C07B01-IKP-MAT-ME-0069 Material Submittal - Warning Tape for Mechanical Systems Revise and Resubmit
6
DAILY REPORT VERIFICATION SUBMITTED BY IKP:

DWR NO REF NO. REMARKS


DWR No. 299 IKP03C07-DAYREP-000292
DWR No. 300 IKP03C07-DAYREP-000293
DWR No. 301 IKP03C07-DAYREP-000294
DWR No. 302 IKP03C07-DAYREP-000295
DWR No. 303 IKP03C07-DAYREP-000296
DWR No. 304 IKP03C07-DAYREP-000297
DWR No. 305 IKP03C07-DAYREP-000298 See SC respond in Aconex.
DWR No. 306 IKP03C07-DAYREP-000299
DWR No. 307 IKP03C07-DAYREP-000300
DWR No. 308 IKP03C07-DAYREP-000301
DWR No. 309 IKP03C07-DAYREP-000302
DWR No. 310 IKP03C07-DAYREP-000303
DWR No. 311 IKP03C07-DAYREP-000304
DWR No. 312 IKP03C07-DAYREP-000305
WORK INSPECTION REQUEST (WIR):

S# WIR No. REQUEST TILE STATUS


Re: WIR No. 289 Civil Rev.01, Site Preparation for Shoring.
1 IKP03C07-WIR-000768 Accepted with Comments
Attached
Re: WIR No. 90 Mech , installation of firefighting piping at F&B ,
2 IKP03C07-WIR-000773 kitchen area, male & female WC,staff and garbage, electrical rooms Revise and Resubmit
as per attached highlighted drawing
Re: WIR No. 88 Mech ,installation of shower mixer embedded valves
3 IKP03C07-WIR-000771 Revise and Resubmit
at male &female toilets as per attached highlighted drawing
Re: WIR No. 87 Mech , installation of Flush tank at male &female
4 IKP03C07-WIR-000770 toilets ,disable toilet and male &female staff toilets as per attached Accepted with Comments
highlighted drawing
Re: WIR No. 0138 Arch, curtain wall Bracket installation. Attached
5 IKP03C07-WIR-000769 Accepted with Comments
highlighted drawing.
Re: WIR No. 0137 Arch curtain wall Pre installation. Attached
6 IKP03C07-WIR-000766 Revise and Resubmit
highlighted drawing.
7 IKP03C07-WIR-000768 Re: WIR No. 289 Civil, Site Preparation for Shoring. Attached Revise and Resubmit
Re: WIR No. 0136 Arch , Insulation board + Accessories as per
attached highlighted drawing Excluded the MEP points which
8 IKP03C07-WIR-000765 Accepted with Comments
material not available now & once this finished another IR will be
submitted)
Re: WIR No. 288 Civil - Protection board installation for vertical
9 IKP03C07-WIR-000764 Accepted with Comments
surface as the per attached highlighted area.
Re: WIR No. 287 Civil - Kitchen screed coordinate & level as per
10 IKP03C07-WIR-000763 Accepted with Comments
attached highlighted area.
Re: WIR No. 121 Elec - Pulling BELDEN 4200FE Cable for BGM
11 IKP03C07-WIR-000761 Accepted with Comments
system at Recreation room.
Re: WIR No. 122 Elec - Pulling CAT6A cable for DATA & Wi-Fi at
12 IKP03C07-WIR-000762 Accepted with Comments
Male and Female Bathroom.
Re: WIR No. 135 Arch - Plastering application. Attached highlighted
13 IKP03C07-WIR-000760 Accepted with Comments
drawing.
Re: WIR No. 134 Arch - Base coat as per attached highlighted
14 IKP03C07-WIR-000759 Accepted with Comments
drawing.(Excluded the MEP points which material not available)
Re: WIR No. 84 Mech - Firefighting pressure test at all area except
15 IKP03C07-WIR-000757 Accepted with Comments
Kitchen and F&B area as per attached highlighted drawing
Re: WIR No. 85 Mech - Smoke test for supply air duct at corridor
16 IKP03C07-WIR-000758 Accepted with Comments
area as per attached highlighted drawing
Re: WIR No. 79 Mech - Plenum box installation with flexible
17 IKP03C07-WIR-000746 connection at Studio and recreation room as per attached Accepted with Comments
highlighted drawing
Re: WIR No. 289 Civil Rev.01, Site Preparation for Shoring.
18 IKP03C07-WIR-000768 Accepted with Comments
Attached

OBSERVATION:
S.# TRSDC DOCUMENT NO. DOCUMENT TITLE STATUS
1
2
Photos

GLASS CURTAIN WALL MOCKUP

DEWATERING WORKS FOR PUMP ROOM


F&B ETICS WORKS

FEMALE TOILET MEP WORKS


THERMAL INSULATION AT LPG AREA

MAIN SWIMMING POOL


MANHOLE AND CHAMBERS PRE CASTING

AC DUCT AT F&B
GLASS MATERIALS FOR CURTAIN WALL

PBC FRONT ELEVATION


FLOOR TILING AT MALE TOILET