Chart 2 PMP

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 6

ES

LS

Project Scope indicating tasks and activities Project Schedule: Netw


Project Title: Mini windmill power generation for homes Project Title: Mini windm
Project Manager: Thai Nguyen Thanh Dat Project Manager: Thai N
Date: 31-July-22 Date: 31-July-22

Task/ Activity ID Task / Activity Estimated Duration (Weeks) 1. Product Planning


1. Product Planning 1 0
2. Market Research 1
3. List of Needs 1 0
4. Correlation 1
5. Proposed Specs 1
6. Concept Mapping + Draft 1 6. Concept Mapping + Draft
7. Concept Block 1 5
8. Concept Draft 1
9. Concept CAD 1 5
10. Low-tech Model 1
11. Prototyping 1
12. Concept Screening 1 11. Prototyping
13. Concept Scoring 1 10
14. Concept Test 1
15. Presentation 1 10
16. Reporting 1

16. Reporting
15

15

* Note: Estimate uses a minimum of one hour per activity


EF
Activity
LF

Project Schedule: Network Diagram – Critical Path


Project Title: Mini windmill power generation for homes
Project Manager: Thai Nguyen Thanh Dat
Date: 31-July-22

1. Product Planning 2. Market Research 3. List of Needs


0 1 1 0 2 2 0 3
1 2 3
0 1 1 0 2 2 0 3

6. Concept Mapping + Draft 7. Concept Block 8. Concept Draft


0 6 6 0 7 7 0 8
6 7 8
0 6 6 0 7 7 0 8

11. Prototyping 12. Concept Screening 13. Concept Scoring


0 11 11 0 12 12 0 13
11 12 13
0 11 11 0 12 12 0 13

16. Reporting
0 16
16
0 16
4. Correlation 5. Proposed Specs
3 0 4 4 0 5
4 5
3 0 4 4 0 5

9. Concept CAD 10. Low-tech Model


8 0 9 9 0 10
9 10
8 0 9 9 0 10

14. Concept Test 15. Presentation


13 0 14 14 0 15
14 15
13 0 14 14 0 15