Professional Documents
Culture Documents
1 - Field Development Planning - Intro + FDP Team
1 - Field Development Planning - Intro + FDP Team
G. Moricca
Senior Petroleum Engineer
May 2017
moricca.guiseppe@libero.it
G. Moricca 1
Integrated Field Development Plan
Content
Oil and gas project plan refers to the unique
requirements of managing science, technology,
engineering aspects and economical topics of projects
in the upstream oil and gas industry.
Once the basic organizational structure has been selected, all positions should be
identified, coded and a personnel mobilization schedule selected.
Time
Cost control can be no better than the project control budget with which
actual costs are compared.
Reservoir Drilling
structure Completion Production
Reservoir Flow Lines Injection
Where connectivity Facilities Disposal Decom
Reserves Delivering
is the mission
field? ing
1 2 3 4 5
Discovery Appraisal Development Production Abandonment
NPV
($)
Develop without
[B]
appraisal information
Cost of appraisal
$[A]
Develop with appraisal
[C]
information
Procurement of materials
Installation of facilities
Time Frame - Offshore drilling often takes much longer to complete than onshore drilling.
An onshore well typically takes only a matter of days to drill, meaning production can begin
much faster. An offshore well can take months or years to build. This means an onshore
project is up and running much faster than offshore facilities.
Offshore drilling presents much more of a challenge due to the shear depth of the water
just to reach the earth’s surface. The force the waves, especially in deep, rough waters,
presents major stability issues. This activity requires a manmade working surface to hold
the drilling equipment and facilities with some type of anchoring to the ocean floor.
Onshore drilling rigs are the more classic drilling equipment and come in different sizes
and strengths. They are generally classified by their maximum drilling depth and their
mobility. Conventional land rigs cannot be moved as a whole unit and are typically used in
the petroleum industry while mobile rigs are drilling systems that are mounted on wheeled
trucks and come in two different types, jackknife and portable mast.
May 2017 G. Moricca 25
Offshore vs Onshore Drilling Cost
The costs for onshore versus offshore drilling are much different. Offshore drilling tends to
cost much more due to the increased difficulty of drilling in deep water. The specific cost
depends on a number of variables, including the specific location, any special
circumstances, well size, design and drilling depth.
On average, an onshore oil well costs between $5.0 MM and $10.0 MM in total well
capital costs. Additional lease operating expenses between $1 MM and $3.5 MM may also
play into the cost over the life span of the well. The following breakdown shows a general
explanation of where those costs are dispersed:
- Drilling – 30 to 40% of costs: This category encompasses any tangible and intangible
costs associated with actually drilling the well.
- Completion - 55 to 70% of costs: The completion costs include both tangible and
intangible aspects of things like well perforations, fracking, water supply and disposal.
- Facilities - 7 to 8% of costs: Onshore drilling activities require storage and other facilities
and the associated expenses. This might include the equipment itself, site preparation
and road construction.
- Operations: The operations cost often come from the additional lease operation
expenses, which include well maintenance and delivery cost.
May 2017 G. Moricca 26
Offshore vs Onshore Drilling Rigs
Offshore drilling rigs are classified differently, mainly based on their movability and how
deep the sea bed is. There are two types of offshore drilling rigs:
1. Bottom-supported units are rigs that have contact with the seafloor. There are
submersible bottom-supported units and also jack up units that are supported by
structured columns.
2. Floating units do not come in direct contact with the ocean floor and instead float
on the water. Some are partially submerged and anchored to the sea bed while
others are drilling ships which can drill at different water depths.
- Drilling – 60% of costs: Drilling takes up a much larger portion of the costs for offshore
drilling activities.
- Completion - 40% of costs: The completion activities take up the remaining costs, which
include well perforations, rig hiring, transportation and well head equipment.
- Facilities - 7 to 8% of costs: Onshore drilling activities require storage and other facilities
and the associated expenses. This might include the equipment itself, site preparation
and road construction.
- Operations: Like onshore drilling activities, the operation costs fall into the lease
operating expenses for the well.
G G G
1 2 3
FEL-1 FEL-2 FEL-3 Detailed Operations
Conceptual Preliminary Eng. Design Eng. Design Support
Engineering Engineering Fully define Implement Monitor
scope. execution plan. performance.
Clear frame Generate
goal. alternatives.
Develop detailed Final design Final design
Identify Reduce execution plans.
opportunities. uncertainty and Implement Benchmark
quantify Refine estimates execution plan. performance
Preliminary associated risks. and economic against objectives
assessment of analysis to A/R Collect, analyze, and competitors.
uncertainties, Develop expected level. and share metrics
potential return, value for selected and lessons Share results and
and associated alternatives. Confirm expected learned. lessons learned.
risks. value meets
Identify preferred
business Continue
alternative(s).
Plan for next objectives. performance
phase. Plan for next assessment and
phase. identify
opportunities.
Cost accuracy Cost accuracy Cost accuracy
Cost accuracy
±40% ±25% ±15% ±5%
The oil and gas industry has consistently used the combination of both
methodologies of the PMI and IPA in the development of major projects,
with particular attention on the front-end loading methodology (FEL), which
combines an approach of so-called "rolling wave planning", with a vision of
technical and cost integration in the light of the IPA's empirical tools.
FEL 2: Conceptual engineering - This is the stage of development that includes the
evaluation and selection of conceptual alternatives. The main focus of this phase is
the development of conceptual engineering for options listed in FEL 1, in order to
compare the options and define, through the results of the financial-economic
assessment of each option, which alternative will make it through to the next phase.
FEL 3: Basic engineering - In this phase, the focus is the construction and the
preparation of the project for its corporate approval and future implementation. The
basic engineering of the selected option in FEL 2 is performed, allowing the
calculation of project capex with greater precision. The engineering solution
selected in FEL 2 is technically detailed and more value improving practices are
considered in the development of the basic engineering design.
May 2017 G. Moricca 35
Tasks to be accomplished for a reliable Field
Development Plan
1
• Set an Integrated FDP Team and Define a clear Target Feasibility
Front End Loading (FEL-1)
2
• Data Acquisition, Data Storing and Data Validation
Identify opportunities.
Preliminary assessment.
3
• Development of a robust Reservoir Model Conceptual Engineering
4
• Conceptual FDP Scenario – Qualitative evaluation
Selection
5
• Field Development Strategy Identification Front End Loading (FEL-2)
6
• Consolidation of FDP Scenario - Quantitative Generate alternatives
6A
• Economic Evaluation Identify preferred.
alternative.
6B
• Uncertainty Analysis
6D
• Health, Safety and Environmental
6E
• Final Selection Field Development alternative
7
• Field Development Plan Approval
May 2017 G. Moricca 36
Contents of final FDP document
Typical Contents of a Field Development Plan document:
1. Executive Summary
2. Introduction
3. Field History and Background
4. Reservoir Characterization & Geological Modelling
5. Reservoir Simulation & Performance Prediction
6. Techno-Economic Evaluation of Prediction Scenarios
7. Executive Prediction Scenario
8. Drilling & Completion Proposal
9. Project Scope of Work & Execution Schedule
10. Project Cost Estimation
11. Quality Management System
12. Health, Safety, and Environment
13. Governing Standards
May 2017 G. Moricca 37
•Set an
Integrated FDP
Team and
1 Define a clear
Target
G G G
1 2 3
FEL-1 FEL-2 FEL-3 Detailed Operations
Conceptual Preliminary Eng. Design Eng. Design Support
Engineering Engineering Fully define Implement Monitor
scope. execution plan. performance.
Clear frame Generate
goal. alternatives.
Develop detailed Final design Final design
Identify Reduce execution plans.
opportunities. uncertainty and Implement Benchmark
quantify Refine estimates execution plan. performance
Preliminary associated risks. and economic against objectives
assessment of analysis to A/R Collect, analyze, and competitors.
uncertainties, Develop expected level. and share metrics
potential return, value for selected and lessons Share results and
and associated alternatives. Confirm expected learned. lessons learned.
risks. value meets
Identify preferred business Continue
Plan for next alternative(s). objectives. performance
phase.
Plan for next assessment and
phase. identify
Cost accuracy Cost accuracy opportunities.
Cost accuracy Cost accuracy
±40% ±25% ±15% ±5%
Only this well can provide the certainty about whether crude oil
or natural gas really does exist in the explored area after the
seismic measurements have been conducted.
When evaluation of the well data and analysis of the drill cores
come to the clear conclusion that oil or gas has been found, this
means a potential development project has been identified. The
next phase, field development, can now begin.
Role:
Be custodian of the objectives of project
Identify priorities
Allocate the assigned human resources
Promote and facilitate the correct integration of permanent and
part-time team components
Avoid lack of communication among the team component and
management
May 2017 G. Moricca 48
FDP Target Identification
Identification of a clear target based on
the data collected during the field
appraisal and in line with company
strategy.
2. Reservoir Connectivity
- Reservoir Characterization and 3D Geologic Modeling
- Geological Inter-well Connectivity Evaluation
- Fluid and Saturation-Dependent Properties
- Initial Reservoir Pressure Estimation
- PVT Matching
- History Matching Reservoir Performance