TB-HB CANNABIS/TOBACCO Incinerator

TB Animal Incinerator Machine Machine


Proposal
Proposal for:
for:
STAR SAFETY
Seagull - DUBAI
Investments

International leaders in
Manufacturing world-class
Incineration solutions
Data: Monday, 06 June 2022

Addfield Environmental Systems Ltd Proposal for:


Addfield TB-HB General waste Incinerator

Quotation Reference: TB06/06/22/01

Thank you for contacting Addfield Environmental Systems Ltd, it was great to hear from you. From the
information you have provided, please find enclosed our commercial quotation for the Addfield TB.

Should you require any further assistance. You can reach me my details below

Yours Sincerely,

Mr Abraham Bah
International Sales Manager
Email: addfieldinternational@gmail.com
Tel: +44 (0) 7530058260

'The most robust, reliable and efficient incinerators on the market' Page | 2

Addfield Environmental Systems Limited


Unit 9 | Zone 4 | Burntwood Business Park
Staffordshire | WS7 3XD | United Kingdom
www.addfield.com
t: +44 (0)1543 571 280 f: +44 (0)1543 571 173 e: sales@addfield.com VAT No. 933 588393 | Company Reg. No: 6516522
1. PRICING SCHEDULE

Equipment Quantity Unit Price Total

Addfield TB-HB Incinerator - Diesel 1 £36,800.00 £36,800.00

Addfield TB Incinerator – Gas 1 £38,900.00 -


Incidental and Consumable Spares 1 year - Diesel
1 £1,290 £1,290
More information below
Incidental and Consumable Spares 1 year - Gas
1 £1729.69 -
More information below
Recommended Options 0

Additional Chimney Sections


3 £600/m £1,800
More information below

Filter scrubber system


1 £25.000 £25,000
For clean air

Hydraulic Bin Tipper System


1 £6500.00 0
More information below
Fuel Tank 2000L
1 £2,875.00 £2,875.00
More information below
Delivery and Commissioning 0
Delivery
CIF to Port 1 - -
Customer to supply on site lifting equipment
Training & Commissioning On Site
1 £6,800.00 £6,800.00
More information below
Alternatively: Training & Commissioning
1 Free of charge 0
Attendance to a seminar held at Addfield, UK
Total
£49,565.00

Manufacturing time: 2 Weeks


Country of Origin: Great Britain
Payment Terms: Payment Terms 50% on order, 50% prior to dispatch
Quote Validity: 30 days

'The most robust, reliable and efficient incinerators on the market' Page | 3

Addfield Environmental Systems Limited


Unit 9 | Zone 4 | Burntwood Business Park
Staffordshire | WS7 3XD | United Kingdom
www.addfield.com
t: +44 (0)1543 571 280 f: +44 (0)1543 571 173 e: sales@addfield.com VAT No. 933 588393 | Company Reg. No: 6516522
2. ADDITIONAL COMPONETS
2.1. Additional Chimney Extensions.
Where required the chimney can be extended further according to the customer’s requirements. The
standard height of the machine with a suppled chimney is 3470mm from floor.
Price: £600/ per 1200mm

2.2. Waste Loading – Bin Tipper – 240L


One hydraulically operated bin tipper unit being designed to introduce waste contained in 240L wheelie
bins in to the primary chamber via an automatic control system quantity of loose waste material into the
incinerator via a single sequenced cycle. It would be complete with:

Fabricated mild steel assembly mounted upon a substantial framework


One infeed reception hopper having a nominal capacity of 0.24L (240L wheelie bin)
Price - Bin Tipper: £6500.00

2.3. Fuel Tank (Diesel/Oil Powered Only)


A 2000 litre bunded (double skinned to 110%) fuel tank. Supplied complete with:
• Lockable fill point with screw cap.
• Vent point.
• Oil tank contents level indicator.
• Overfill prevention capability.
• Bottom outlet.
This fuel tank satisfies or exceeds all applicable oil storage tank requirements detailed within:
• The Control of Pollution (Oil Storage) (England) Regulations 2001
• The Control of Pollution (Silage, Slurry and Agricultural Fuel Oil) Regulations 1991
• Environmental Alliance Pollution Prevention Guidelines PPG 2
Price: £2,875.00

'The most robust, reliable and efficient incinerators on the market' Page | 4

Addfield Environmental Systems Limited


Unit 9 | Zone 4 | Burntwood Business Park
Staffordshire | WS7 3XD | United Kingdom
www.addfield.com
t: +44 (0)1543 571 280 f: +44 (0)1543 571 173 e: sales@addfield.com VAT No. 933 588393 | Company Reg. No: 6516522
3. SPARES AND SERVICING PARTS
The following lists give an indication of the required level of spares that would be required for a twelve-month
operating period and which should be held by the client.

During the warranty/defects liability period any incidental spares used, required due to justified failure of the
original item, would be replaced without charge to the client. However, the client would be responsible for
replacing any consumable spares.

Consumable Spares (1 year) - Diesel (AG-3B-CD)


Recommended Stock Level
Item
Per Annum
Thermocouples
1
TC225210BM
Burner Blast Tubes
3
MAX12BTTL
Burner Diffusers
3
DIFFMAX12
Burner Nozzles
1
NOZZLE1.25X60
Burner Nozzles
2
NOZZLE1.50X60
Fuel Filter
1
FILTERCART

Incidental Spares (1 year) - Diesel (AG-2B-IG)


Item Recommended Stock Level
Combustion Burner
1
MAX12DB
Control Box
1
CBOXLOA24

Consumable Spares (1 year) – Gas (AG-3B-CG)


Recommended Stock Level
Item
Per Annum
Thermocouples
1
TC225210BM
Burner Blast Tubes
3
MAXGAS120BTTC
Burner Diffusers (Brake Plate)
3
DIFFMAXGAS120
Ignition Electrodes
1
ELECTAD0029
Ionization Probes
1
ELECTMGION

Incidental Spares (1 year) - Gas (AG-2B-IG)


'The most robust, reliable and efficient incinerators on the market' Page | 5

Addfield Environmental Systems Limited


Unit 9 | Zone 4 | Burntwood Business Park
Staffordshire | WS7 3XD | United Kingdom
www.addfield.com
t: +44 (0)1543 571 280 f: +44 (0)1543 571 173 e: sales@addfield.com VAT No. 933 588393 | Company Reg. No: 6516522
Item Recommended Stock Level
Combustion Burner
1
MAXGAS120TC
Control Box
1
CBOXMG120

4. COMMISSIONING, DELIVERY & AVAILABILITY


4.1. Time On Site & Commissioning:

We anticipate that it will take up to 4 days to commission and train personnel on how to use the incinerator.
This includes two days travel time to and from site. We have allowed for commissioning costs within the
quotation.

Alternatively this training can be provided free of charge at a seminar held at Addfield’s premises in
Staffordshire, United Kingdom. Please ask for further information if interested.

On site commissioning is subject to foreign travel advice for the region.

Where applicable please ensure lifting equipment is available on site for construction of the chimney stack (If
you are unsure please ask). Please refer to the pre-site check list for this machine, prior to its arrival. This can
be found here: https://addfield.com/wp-content/uploads/2017/11/Pre-site-Checklist-English.pdf)

4.2. Delivery Information

The unit will be delivered in a container, CIF (Incoterms 2010) to port. The customer will need adequate
lifting equipment to unload the machine and to site it.

Delivery options to be confirmed.


5. PLANT DUTY & UTILITIES
5.1. Plant Duty

Incinerator type: Addfield TB Incinerator


Solid Waste types: General waste
Whole plants & woods
Agriculture waste
Cannabis, tobacco waste

Solid Waste C.V. range: 3MJ/Kg to 15MJ/Kg


Solid Waste Design C.V: 14 MJ/Kg
Design throughput: Upto 150 Kgs/hour solid waste
Batch Capacity: Upto 1300kg
Thermal capacity: 480Kw
Operating regime:
Upto 7 days per week
Upto 52 weeks per year
Maintenance regime: 15 minutes every 10th burn
Overall availability: 90%
Design criteria: BS3316

'The most robust, reliable and efficient incinerators on the market' Page | 6

Addfield Environmental Systems Limited


Unit 9 | Zone 4 | Burntwood Business Park
Staffordshire | WS7 3XD | United Kingdom
www.addfield.com
t: +44 (0)1543 571 280 f: +44 (0)1543 571 173 e: sales@addfield.com VAT No. 933 588393 | Company Reg. No: 6516522
Secondary Chamber residence time
2 seconds at 850°C

Operational Data: Primary Chamber


Temperature range: 700°C to 950°C

Secondary Chamber
Temperature range: 850°C to 1050°C
Oxygen Content: 6% to 12%
Residence Time: Minimum 2 seconds

5.2. Plant Utilities


Electricity Consumption:
Supply: 240v, single phase, 50 Hz
Capacity: 16 Amps
Anticipated usage: 1 kW/hour

Diesel Consumption:
Fuel supply Light Fuel Oil
Fuel usage (average) 7-9 litres/hr

LPG Consumption:
Fuel Type: LPG
Fuel usage (average) 8-10 litres/hr

Note: Usage rates are estimated and are based on a calorific value of the waste loaded

'The most robust, reliable and efficient incinerators on the market' Page | 7

Addfield Environmental Systems Limited


Unit 9 | Zone 4 | Burntwood Business Park
Staffordshire | WS7 3XD | United Kingdom
www.addfield.com
t: +44 (0)1543 571 280 f: +44 (0)1543 571 173 e: sales@addfield.com VAT No. 933 588393 | Company Reg. No: 6516522
Industry Leading Unrivalled Three Layers 40% Fuel Saving
Brick refractory insulation of thick thermal insulation Save 5000-15000 litres/year

20+ Years Robust Construction Modular Construction


Long service life 8 and 10mm thick steel Maintainable long term

35+ Years’ Experience Manufactured in ISO 9001 & 14001


Building incinerators Great Britain Certified

'The most robust, reliable and efficient incinerators on the market' Page | 8

Addfield Environmental Systems Limited


Unit 9 | Zone 4 | Burntwood Business Park
Staffordshire | WS7 3XD | United Kingdom
www.addfield.com
t: +44 (0)1543 571 280 f: +44 (0)1543 571 173 e: sales@addfield.com VAT No. 933 588393 | Company Reg. No: 6516522
6. PLANT OPERATION
The incineration machine is suitable for safe and economic disposal of a wide range of waste types. It
requires minimal user interaction and only a single operator throughout.

Waste is loaded via the primary chamber door into the main combustion chamber. The reliable design of
the primary chamber lends itself to a sealed, leak proof arrangement. When the door is closed, the
progressive latching system creates a tight window frame seal that minimises thermal heat loss and
maximises thermal efficiency.

Operation of the machine is performed via the simple-to-use, plug-and-play Addfield controller. The
machine can be set to perform a previously prepared cycle, or custom settings can be entered via the
interface.

Once the cycle has been initiated no further action is required. The machine will begin with preheating the
secondary after chamber to the required 850°C minimum. This chamber provides a turbulent and high
temperature environment for the thorough treatment and oxidation of the partially burnt flue gases,
offering a virtually smokeless, odourless operation.

Once above this minimum temperature threshold, the incineration process in the primary chamber can
commence. Real time temperatures from the primary and secondary chambers are displayed at all times
from the main controller display.

Our advanced, thick refractory linings are designed to insulate the machine, as such the burners will pulse
fire on-off to reduce fuel consumption to an industry leading minimum, whilst maintaining temperatures.

Once the cycle has completed, an automatic cool-down process will be enacted for the machine to be
safely de-ashed and reloaded. The resulting waste will have been reduced to approximately 3% of fine,
sterile, inert ash.

'The most robust, reliable and efficient incinerators on the market' Page | 9

Addfield Environmental Systems Limited


Unit 9 | Zone 4 | Burntwood Business Park
Staffordshire | WS7 3XD | United Kingdom
www.addfield.com
t: +44 (0)1543 571 280 f: +44 (0)1543 571 173 e: sales@addfield.com VAT No. 933 588393 | Company Reg. No: 6516522
7. ADDITIONAL INFORMATION & TERMS
7.1. Exclusions
VAT, demurrage, duty and local taxes where applicable.
Any additional shipping certification or documentations that would be deemed chargeable from the freight
forwarders and/or official bodies
All civil and building works; these works would be inclusive of but not necessarily limited to any building
structure/housing for the incinerator, all foundations floor slabs and hard-standings, all roof and wall
penetrations and their sealing, all drainage requirements and all associated works.
The provision and connection of the electrical supply to the incinerator termination point
The provision and connection of the fuel supply to the incinerator termination point
Permitting and planning requirements
Additional chimney height if required
On site lifting equipment
All equipment quoted as optional
Anything not specified
We reserve the right to update and/or revote prices accordance to currency fluctuations when not quoted
British sterling.

Due to the on-going concern with COVID-19 virus, Addfield will continue to follow the latest UK Government guidelines and
advice regarding international travel for our employees and sub-contractors. This could result in our inability to travel to site as
requested. It could also result in our resources whilst away from our offices to be contained / isolated. In the event of arriving in
the destination country, should our staff be contained, we would seek to be paid for each day they remain in isolation until
released to continue to work. This would be charged at our normal working day 8 hour rates.

Should this quote be of interest, Addfield reserve the right to review our resources at the point of order and to advise a revised
start date. This is particularly required in the present working environment relating to COVID-19 ongoing issues.

In the event that we had to take our commissioning resources and place them into quarantine we will invoice for work
completed up to that point including any quarantine period.

7.2. Quality Assurance


The company operates an ISO 9001-2015 compliant Quality Assurance System.
(Certificate can be found here: http://www.addfield.com/pdf/Addfield-ISO9001-Certificate.pdf)

7.3. CE Compliance
Our machines are stamped and CE compliant to:
• BS E7N4 6-2:1997 (Industrial thermo processing equipment - part 2)
• 73/32/EEC Low voltage directive
• 89/336/EEC EMC Compatibility Regulations
• 89/392/EEC Machinery Directive.

7.4. Aftercare Support


We pride ourselves on the build quality of all of our machines. Every machine Addfield manufactures is
built on the foundations of robustness, reliability and efficiency. As such, every machine is supported with
a 12-month unlimited usage warranty.
Because we are available almost 24 hours day by various channels including onsite visits, telephone, email,
Skype and more, if you do require assistance, then we are readily available to help.
(For further information on warranties please refer to www.addfield.co.uk/warranty)

7.5. Health & Safety


The company has a complete Health and Safety Policy which covers the company responsibilities to its
employees. The system is updated on a regular basis and audited during the course of the year.

'The most robust, reliable and efficient incinerators on the market' Page | 10

Addfield Environmental Systems Limited


Unit 9 | Zone 4 | Burntwood Business Park
Staffordshire | WS7 3XD | United Kingdom
www.addfield.com
t: +44 (0)1543 571 280 f: +44 (0)1543 571 173 e: sales@addfield.com VAT No. 933 588393 | Company Reg. No: 6516522
7.6. Safety Training & Insurance
It is company policy to ensure that employees are properly trained in safety matters and understand the
importance of accident prevention methods. Addfield implements a training programme that is fully
reviewed annually in order to ensure that all of our Client’s requirements are met. Our insurance covers the
company for: Public Liability £5 million & Employers Liability £10 million.

7.7. Terms & Conditions


Our standard terms and conditions of sale apply to this quotation. A copy of which can be found here:
https://addfield.com/wp-content/uploads/2021/05/Addfield-Environmental-Systems-Terms-and-
Conditions-Web.pdf

'The most robust, reliable and efficient incinerators on the market' Page | 11

Addfield Environmental Systems Limited


Unit 9 | Zone 4 | Burntwood Business Park
Staffordshire | WS7 3XD | United Kingdom
www.addfield.com
t: +44 (0)1543 571 280 f: +44 (0)1543 571 173 e: sales@addfield.com VAT No. 933 588393 | Company Reg. No: 6516522
8. ADDFIELD ENVIRONMENTAL SYSTEMS LTD

8.1. About Addfield


Addfield are worldwide industry leaders in the design and manufacturing of thermal processing equipment.

With 60,000sq/ft. of production facility space Addfield manufacturer 100% of the machines on site and
employee a wide variety of highly skilled fabricators, welders, refractory mason, electricians and combustion
engineers. This allows us to ensure the quality of the product throughout the production line.

With over 30 years of experience within the Incineration industry, Addfield have the technical ability to
deliver the machine for your application.

An award-winning company that is ISO9001-2015 and 14001 certified, DEFRA type approved and CE
certified. We pride ourselves on building the most robust, reliable and efficiency machines on the market,
which are simply built better.

Assuring you of our close attention at all times,

For and Behalf of:


Addfield Environment Systems Limited

Abraham Bah
International Sales Manager

'The most robust, reliable and efficient incinerators on the market' Page | 12

Addfield Environmental Systems Limited


Unit 9 | Zone 4 | Burntwood Business Park
Staffordshire | WS7 3XD | United Kingdom
www.addfield.com
t: +44 (0)1543 571 280 f: +44 (0)1543 571 173 e: sales@addfield.com VAT No. 933 588393 | Company Reg. No: 6516522

You might also like