Progress Report - No. 35 DAWASA OFFGRID UP TO 1st November, 2022
Progress Report - No. 35 DAWASA OFFGRID UP TO 1st November, 2022
1
Table of content
1 CONTRACT DETAILS
2 EXECUTIVE SUMMARY
3 STATUS OF WORK
4 LOOK AHEAD AUGUST 2022
5 MANPOWER ON SITE
6 MACHINARY ON SITE
7 FINANCIAL REPORT
8 CHALLENGES
9 IMPORTANT EVENTS
10 HSE IMPLEMENTATION
11 PROGRESS PHOTOGRAPH
2
CLIENT:
CONSULTANT: CONTRACT:
3
800mm pipes.
MAIN CONTRACTOR:
1. PROJECT SUMMARY
Construction of Offgrid Water Supply Distribution Network in Ilala and Part of
Kigamboni Municipalities. The Project entails construction of distribution network
for total of 69km; which involves Yangeyange distribution 28.km, Nzasa distribution
15.116km, Kibada distribution 23.714km, Distribution main from Kimbiji reservoir to
Kibada junction 2.5km, Nzasa transmission 1.7km, Construction of 1 reservoirs
2000cum at Nzasa, Installation of Nzasa Pump, Transformer 100KVA, Construction
Guard House, Chlorination room, Panel House, Valve Chambers, and Construction of
Offtakes and allied works.
SITE WORKS
4
iv. OD 110mm dia UPVC pipes delivered = 1287.6m (222 Nos)
v. OD 90mm dia UPVC pipes delivered = 2412.8m (416 Nos)
vi. OD 75mm dia UPVC pipes delivered = 37618.8m (6486Nos)
b. Pipes Layed at site
i. OD 200mm dia UPVC pipes = 5475.2m
ii. OD 160mm dia UPVC pipes = 4843m
iii. OD 110mm dia UPVC pipes = 0m
iv. OD 90mm dia UPVC pipes = 1299.2m
v. OD 75mm dia UPVC pipes = 36569m
vi. OD 800mm dia, MS pipes = 780m
5
i. Mix design results for concrete, steel tests and blocks were submitted to
consultant for approval. Steel tests and Concrete Class 10, 15, and 25 were
approved. Class 35 test done. Results already obtained and approved by
consultant.
ii. Survey work is completed.
iii. All Distribution drawings are approved
iv. Soil investigation: 100%, done and approved
v. Route surveying: 100 %, total 69.9km done and submitted.
vi. Hoarding Works: Completed in Mgeule and Nzasa sites respectively.
vii. Signboards installation 8 nos done.
viii. Temporary facilities: Offices, stores, laboratory, toilets done by 100%
I. Delivery of first batch 1km MS pipes 800mm dia from TSP completed and
pipe laying for 600m is done. Another order of 1.4Km MS pipes already
placed production to start the end of this week. VAT Exemption in follow-ups
in progress.
II. Delivery of uPVC pipes 19km batch from Simba DPI completed.
III. The water investigation report for the 2 bore wells is submitted. Decision
have been made as explained above. We are proceeding with Nzasa GSR and
Mgeule ESR was discarded and removed from scope
IV. Pipeline hydraulic design is submitted and approved for distribution networks
Nzasa and Kibada and Yangeyange
V. Pipeline distribution drawings and LS Profiles completed, submitted and
approved.
VI. Soil investigation report is APPROVED.
VII. Baseline report was approved by WAPCOS. Specific ESMP report submitted
and approved. Monthly reports also submitted on a monthly basis.
VIII. CRB Project registration: done
6
IX. OSHA registration for project: done
X. Work Programme/Schedule already approved by consultant
XI. Project vehicle procurement: On process with DAWASA for approval of
addendum. We are waiting for official instruction in writing.
XII. Mobilization of key staff: 97%.
XIII. Structural design for reservoirs: Submitted and approved by Consultant.
Approved drawings already printed and submitted to consultant.
XIV. Simba Pipes procurement: QAP of UPVC and HDPE pipes have been approved
for Simba DPI.
XV. For valves export details have been approved for RGI. QAPs and data sheets
for valves have been approved by the consultant. Procurement is arranging to
place orders for Valves from RGI India.
XVI. Pump 60cum/hr and control panel procurement. Approved for Genvik pump
make. Mr. Tamish is arranging to place final Purchase order for the pump.
XVII. Transformer for Nzasa borehole already purchased and delivered at the site.
XVIII. We received confirmation to proceed with procurement for all types of pipes.
XIX. Method statement for uPVC and HDPE pipe laying already submitted to
consultant and approved. Hydro test method statement is also submitted
waiting for approval.
XX. Designs drawings for Guard House, Chlorine Building, Panel House, All valve
chambers, and Thrust block submitted. We are working on comments.
XXI. Procurement of all types of fittings for UPVC, HDPE and MS is with
Procurement department. Samples for uPVC fittings submitted by supplier.
Already RFI sent to consultant for inspection notes and approval.
3. LOOK AHEAD NEXT WEEK FROM 2ND NOVEMBER TO 7TH NOVEMBER 2022
Continuing with pipe laying, joining, welding and backfilling works at Kimbiji
transmission main
Finalizing delivery of materials for concrete casting for Raft foundation work for
Nzasa GSR
Receiving machines and final preparation for concrete (Raft foundation) at Nzasa
GSR.
Casting concrete for the raft foundation at Nzasa GSR.
Finalizing excavation, pipe laying and backfilling for Nzasa distribution system uPVC
pipes.
Finalizing measurements for completed trenches for 3rd IPC preparation.
7
2 Project Coordinator 1
3 Site Engineer 4
4 Land surveyor 1
5 HSE Representative 2
6 Environmental officer 1
7 Social officer 1
8 Site supervisor 1
9 Plant operator 2
10 Mechanics 0
11 Storekeeper 2
12 Auto electrician 1
13 Driver 3
14 Mason 2
15 Steel fixer 8
16 Carpenters 2 5
17 Casual Labors 4 (subcontract) 3 (subcontract)
18 Foremen 6 (subcontract)
19 Plumbers 2 (subcontract)
20 Consultant staff WAPCOS 5
21 Counterpart staff Counterpart 3
22 MS Welders 3
23 MS Pipe Fitter 1
24 Machine Operators 2
25 Grinder man 1
26 Electrician 1
27
Re
Qty mar Qty
Description ks Description Remarks
8
Mixer Machine 1 Vibrator & Poker 2
Generators 2 Excavator 1
6. FINANCIAL STATUS
Advanced payment already paid.
IPC No. 1 submitted and approved by WAPCOS. Already sent to DAWASA for
payment processing. This IPC is already paid.
IPC No. 2 Submitted and approved by WAPCOS. Already sent to DAWASA since 23 rd
September 2022.
IPC No. 3 is under preparation, only waiting for measurement sheets for
submission.
7. CHALLENGES
Delays from our Head office in delivering ordered materials for Raft in time
Challenge on obtaining in time of required documentations from the suppliers and
manufacturers
Absence of our supervision vehicle (Pickup) which is under repair for more than one
month up to now.
Delay in delivery of required materials on time.
Transport at Kibada site is a big challenge as it is lowering the production and making
slow progress.
8. IMPORTANT EVENTS
Delivery of materials for concrete (Raft foundation) is ongoing. Only few materials
and machines are pending.
9. HSE IMPLEMENTATION
Site HSE induction and tool box meeting is being done every Monday at site
Baseline report and specific ESMP/HSMP, revised reports submitted accordingly.
Specific ESMP report approved.
9
SITE PROGRESS PHOTOS
10
Welding of MS Pipes at Kimbiji transmission main.
11
Trench excavation and pipe laying at Nzasa areas.
Shuttering works for raft foundation at Nzasa GSR at the scour and outlet puddle pieces
Prepared by:
12