National Power Corporation

Small Power Utilities Group-WMOD


Zamboanga City

COMPUTATION OF TRANSFORMER LOSS FACTOR FOR TAWI TAWI ELECTRIC COOPERATIVE


(Based on the submitted MOR from Sibutu Diesel Power Plant)
Period : OCTOBER 25, 2021 to NOVEMBER 25, 2021

The Transformer Loss (TL) in kwh is defined as

TL = Gross Generation, kwhr - Net Generation, kwhr (Billing Meter) - Station w/ Generation, kwhr

1. Gross Generation, kwhr 84,886.00

2. Net Generation, kwhr ( Billing Meter) 80,897.79

3. Station Used , kwhr 2,619.00

4. Transformer Loss, kwhr 1,369.21

Prepared by: Approved by :

JAAPAR H. HASSAN SALI A. DIMAN


Engineer II PEC-Sibutu DPP