Professional Documents
Culture Documents
Ascecf 1943-5509 0000381
Ascecf 1943-5509 0000381
net/publication/273405597
CITATIONS READS
15 2,236
6 authors, including:
Chung-Yue Wang
National Central University
116 PUBLICATIONS 1,045 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
Higher Education Project-Core Research Group Project [Development of Performance Evaluation Technology of Bridge Foundation under Earthquake Action] View project
All content following this page was uploaded by Helsin Wang on 21 July 2015.
Abstract: The exposure of pier foundations owing to scour significantly reduces the foundation-bearing capacity and diminishes the flood-
resistant capacity of a bridge. This paper proposes a nonlinear quasi-static analysis procedure for the performance of bridges with pile founda-
Downloaded from ascelibrary.org by National Taiwan University on 01/22/14. Copyright ASCE. For personal use only; all rights reserved.
tions under flow-induced loads for the evaluation on the flood-resistant capacity of scoured bridges. The Winkler beam model is adopted for the
modeling of the pile-soil system, and the distributed hinge model is utilized to simulate the possible flexural failure of the piles. Soil springs with
nonlinear p-y curves are used to represent the nonlinearity of the supporting soil. To demonstrate this procedure, a case study on the Shuang-
Yuan Bridge in Taiwan was performed for various flood and scour conditions. This bridge was partially demolished in a major flood event
caused by Typhoon Morakot in 2009. According to the analysis results, a possible scenario for the failure of the Shuang-Yuan Bridge is
presented, and the proposed method is shown to give a reasonable assessment of the flood-resistant capacity of bridges with scoured pile
foundations. DOI: 10.1061/(ASCE)CF.1943-5509.0000381. © 2014 American Society of Civil Engineers.
Author keywords: Bridge scour; Foundation exposure; Flood-resistant capacity; Winkler beam model; Distributed hinge model; Nonlinear
p-y curve.
Fig. 1. Major highway bridge failures attributable to foundation scour in Taiwan: (a) Kao-Ping Bridge in 2000; (b) Hou-Fong Bridge in 2008;
(c) Shuang-Yuan Bridge in 2009 (images by Cheng-Hsing Chen and Yung-Yen Ko)
and evidence may not be sufficient to reveal the actual failure mode, Thus, the stability of the pier-soil system against a flood will be
flood condition, and scour level when the failure was initiated. Using reduced, and the pier may even be tilted if its stability is lower than
the proposed procedures, the performance of the Shuang-Yuan the allowance. If the scour becomes severe and the piles are exposed,
Bridge can be evaluated under various flood conditions and scour the vertical bearing capacity of the foundation, as well as the lateral
levels. The analysis results will help to speculate the possible sce- capacity, will be lowered, which might cause the settlement of the
nario for the failure of the Shuang-Yuan Bridge. pier. In addition, when the pile is significantly exposed, a lack of
lateral confinement could result in flexural failure of the pile at-
tributable to the flow-induced load and even cause the buckling of
Flood-Resistant Capacity of Scoured Bridge the pile under the axial load arising from the weight of the
superstructure.
Influence of Pier Foundation Scour
Analysis for Performance of Bridges under
As shown in Fig. 2, for a bridge pier located in a river, the lateral
Flow-Induced Loads
resistance of the pier-soil system will be decreased when the sup-
porting soil body around the pier and its foundation is partially Utilizing any structural-analysis software that is capable of non-
removed by scouring. Furthermore, scour will degrade the level of linear analysis, the soil-structure model of a bridge that consists of
the riverbed, leading to larger flow-induced loads applied on the pier. plastic hinges set in the pile and nonlinear soil springs distributed
Fig. 2. Influence of scour on stability mechanism of pier foundation (adapted from Chen et al. 2009)
Modeling of Superstructure
In the evaluation on the flood-resistant capacity of a scoured bridge,
the focus is on the stability of the scoured foundation under the effect
of a flow-induced load. Therefore, the modeling of the superstruc-
ture of a bridge is generally similar to that in ordinary bridge
structural analysis, and the nonlinearity is neglected to reduce the
analysis cost. However, to include the P-D effect of the structure as
well as possible buckling of the exposed piles in analysis, the vertical
load from the superstructure must be treated appropriately.
In Eq. (2), kh acts as the secant modulus of the p-y curve to simulate
the stiffness degradation of the soil attributable to large displace-
ment. This equation is similar to those specified by Architectural
Institute of Japan (AIJ) (1988) and Ministry of Transport (MOT)
(1989), which are widely used in foundation engineering practice in
Japan.
Fig. 8. Hydrograph at Kao-Ping Weir during Typhoon Morakot (adapted from CECI 2011)
Fig. 9. Location of target units for analysis of Shuang-Yuan Bridge; base photograph was taken June 19, 2010, when temporary bridge had been
constructed (Google Earth; DigitalGlobe 2013)
action of loads induced by the huge water flow. However, the failure P10–P13, where the foundations of the four piers had been ret-
mode of the foundation and the position of the initially damaged pier, rofitted in 2003, and the unit P13–P16, in which piers P13 and
as well as the scour depth at the moment the damage commenced, P14 had been retrofitted (piers P15 and P16 had not), were chosen
still need to be clarified. as the targets of interest in this study, as shown in Fig. 9. The
finite-element (FE) structural analysis software SAP2000 11.0
was employed. For each bridge unit, a soil-structure model
Analysis Model and Conditions
considering the nonlinearity of the pile-soil system was estab-
Because the initial failure of the Shuang-Yuan Bridge could lished (as shown in Fig. 10) according its structural design, the
possibly have occurred at the section from P10–P16, the unit of soil profile of the site (obtained from investigation data), and the
Fig. 10. Analysis model of Shuang-Yuan Bridge: (a) unit P10–P13; (b) unit P13–P16
possible scour condition of the riverbed. The details of the exposure attributable to scour is represented by removing the soil
analysis model are given subsequently. springs.
The distributed hinge model was adopted to simulate the possible
Modeling of Superstructure and Piers flexural failure of the piles (see Fig. 5). The layouts of the original
For the superstructures, the deck is modeled by plate elements, and foundation and the retrofitted foundation with additional piles and an
the girder and the diaphragm are modeled by beam elements. The enlarged pile cap are as shown in Figs. 11(a and b), respectively. The
pier is also modeled by beam elements. The higher rigidity at the former is composed of six bored piles with a length of 33–44 m, and
beam-beam and beam-column joints is considered in the model for the latter has four additional bored piles with a length of 50 m. The
a more realistic simulation of the structural behavior. For the support design details are as listed in Table 1. Using the cross-section
conditions of the girders, the two piers at both ends of the three-span analysis software XTRACT 3.0, the moment-curvature curves of
unit had moving supports on their tops, which are regarded in the all the representative cross sections of the piles (seven sections for
model as rollers in the horizontal longitudinal direction (HL-DIR) the original piles and two sections for the additional piles) were
and as hinges in the horizontal transverse direction (HT-DIR), obtained, as shown in Fig. 12. The amount of longitudinal re-
whereas the other two piers in the middle part of the unit had fixed inforcement has a great beneficial influence on the flexural stiffness
supports, which are modeled as hinges in both the HL-DIR and HT- and strength of the piles, and thus the additional piles of the ret-
DIR. rofitted foundation show a much better flexural capacity than the
For the adjacent units, because the supports at both ends of the original ones. These moment-curvature envelopes can be simplified
bridge unit are moving supports, their constraint effect is not con- into bilinear curves by the equal area method, and thus the properties
sidered. However, the self-weights of their superstructures are of the flexural plastic hinges are specified accordingly.
simulated by mass points added to the top of each pier at both ends of
the unit to enable realistic modeling of the P-D effect.
Soil Profile and p-y Curves
Modeling of Group-Pile Foundation Available geological data include the boring logs coming from
The pile cap is relatively thick compared with its lateral size and a geological investigation conducted in 1972 for the first phase of the
therefore is modeled as a rigid plate. Utilizing the Winkler beam Shuang-Yuan Bridge (Directorate General of Highways 1974) and
model, the piles are simulated by beam elements, and the soil the geological investigation of the rebuilding project of the new
reactions are simulated by spring elements (see Fig. 4). The pile Shuang-Yuan Bridge (CECI 2010). Accordingly, soil properties in
Fig. 11. Layouts of (a) original foundation and (b) retrofitted foundation
the area neighboring the failure of the Shuang-Yuan Bridge can be Approximately five layers can be distinguished, which are (from top
deduced. to bottom) (1) a silt layer, (2) a coarse sand layer, (3) a fine sand layer,
Fig. 13(a) shows a soil profile based on the geological data in (4) a silty clay layer, and (5) a silty sand layer.
1972, in which the pier positions of the units to be analyzed are Fig. 13(b) shows a soil profile based on the geological data in
marked. The soil layers of this site consist mainly of recent allu- 2010, in which the boreholes were located approximately 30 m to
vium from the Kao-Ping River, including silt, clay, sands, and gravels. the upper river side from the old Shuang-Yuan Bridge. The soil
layers at this location also consist mainly of recent alluvium. On the investigation, assuming these data are better representations of the
convex bend side [the right side in Fig. 13(b)], five layers can be real situation at the time of failure.
distinguished, which are (from top to bottom) (1) a silt layer, (2) The soil profile in the bridge section from P10–P16 at a dep-
a coarse sand layer with gravels, (3) a silty fine sand layer, (4) a silty th range of 0–50 m (the depth range of the additional piles of
clay layer, and (5) a silty fine sand layer; this soil layer sequence is the retrofitted foundations) can be simplified into four repre-
similar to that described in the 1972 data. On the other hand, six sentative layers, which are (from top to bottom) the silt layer, the
layers can be distinguished in the main channel near the concave silty sand layer, the silty clay layer, and the silty sand layer, as
bend side [the left side in Fig. 13(b)], which are (from top to shown on the left side of Fig. 14. Based on the distribution of
bottom) (1) a silt layer, (2) a fine sand layer, (3) a coarse sand layer SPT-N values, the simplified soil layers can be further divided
with gravels, (4) a silty fine sand layer, (5) a silty clay layer, and (6) into six sublayers, as shown on the right side of Fig. 14. Thus, the
a silty fine sand layer. It was found that the soil layers 2 and 3 nonlinear p-y curves can be obtained for each sublayer using
(concave bend side) are different from the two previously men- Eqs. (1) and (2) according to the corresponding SPT-N values, as
tioned soil layer sequences, and therefore it is assumed that these shown in Fig. 15.
two layers are deposits formed after the flood brought by Typhoon
Morakot, not original ones.
Although the soil profiles based on the geological data in 1972 Scour Depth
and 2010 are generally similar except for the postflood deposit zone, Comparing Figs. 13(a and b), the scour-depth distribution of the
the detailed sublayer sequence and the SPT-N values in the shallow Shuang-Yuan Bridge in the section from P10–P16 at a distance of 30
layers still show some dispersion because of the influence of chan- m from the bridge to the upper river side can be approximately
nel changes in the more than 30-year-long interval. Therefore, the estimated according to the thickness of the postflood sediments, with
soil properties were estimated mainly from the 2010 geological a maximum value of approximately 16 m. This distribution can be
Fig. 13. Soil profile of Shuang-Yuan Bridge site: (a) based on geological data in 1972; (b) based on geological data in 2010
Fig. 14. Simplified soil profile and corresponding SPT-N values for analysis
regarded as the lower bound (LB) of the scour depth at the section However, whether there was further scour after the failure of the
P10–P16. piers cannot be affirmed because of insufficient data and evidence.
In addition, the locations of the remains of RC members (such That is, the failure might occur before the maximum scour depth is
as piles) were located by the on-water electrical-resistivity to- reached. Therefore, seven states of scour depth of the riverbed at the
mography (ERT) investigations performed after the failure of the bridge section P10–P16 are specified for analysis, as shown in
Shuang-Yuan Bridge (CECI 2011). Accordingly, it was presumed Fig. 16. For scour state I (as the LB), the scour depth is 16 m at P10,
that the piles of the foundations of piers P4–P12 were all washed 12 m at P13, and 6 m at P16, according to the thickness of the
away and that the scour depth at this section might be up to 30 m. postflood sediments estimated from the bore data, whereas the scour
The investigations also indicated that the remains of depths at the other piers are linearly interpolated. At scour state VII
the foundation of pier P13 were located at a depth of approxi- (as the UB), the scour depths are 30 m at P10 and 20 m at P13 based
mately 15–20 m (Wang et al. 2011). This information can be on the ERT investigations, whereas the scour depth at the other piers
considered as setting the maximum value of the scour depth, or an are linearly interpolated or extrapolated. The other scour states are
upper bound (UB). intermediates between LB and UB. The flood-resistant capacity
Fig. 17. Flood-resistant capacity curves of unit P10–P13 at various scour states
curves in all the seven specified scour states will be evaluated, which can be transformed into equivalent nodal forces as the applied loads
will be helpful to speculate the possible scour state at the com- in the analysis.
mencement of the failure. First, the self-weight of the bridge unit is applied for a force-
control equilibrium analysis to check whether the exposed piles
will buckle owing to insufficient lateral confinement. Then,
Input Loads and Analysis Processes a displacement-control nonlinear quasi-static analysis is per-
According to the speculated water table and scour depths, the flow- formed under the action of the flow-induced load at each specified
induced loads as a function of the average flow velocity in terms of scour depth, enabling obtainment of the relationship between the
the pressure distribution form can be obtained using Eq. (3). For the total lateral load and the lateral displacement at the top of the pier,
elevation of the water table, a value of 5.94 m is adopted (Control which can be regarded as the flood-resistant capacity curve of the
Yuan 2010), and the scour depths are determined from Fig. 16. The bridge. On the capacity curve, each point represents a specific
hydraulic analysis (CECI 2011) indicated that the torrent acted on average flow velocity, and the damage state can be marked on it
the piers and piles at the bridge section P10–P16 with an attack angle for a judgment of the performance of the bridge at a specified flow
of approximately 10°. Accordingly, the flow pressure distribution velocity.
Fig. 19. Flood-resistant capacity curves of unit P13–P16 at various scour states
Analysis Results and Discussions displacement monitoring point. The flood-resistant capacity
Unit P10–P13 curves at the seven specified scour states are as shown in Fig. 17.
The foundations of all four piers of this unit had been retrofitted When the scour depth is larger, the slope of the capacity curve will
by adding piles and enlarging the pile cap. Because pier P10 be lower because of the lower stiffness of the pile-soil system.
had the greatest scour depth, the top of P10 was chosen as the Meanwhile, the corresponding yield load (at the yield point B on
flow velocity, equivelocity contours can be drawn, as shown by the reached the complete failure state.
dashed lines in Fig. 17. A higher flow velocity will lead the bridge Although only two piers had been retrofitted in this unit, it shows
to a higher damage level. The average flow velocity at the cross a better flood-resistant capacity than unit P10–P13 because of its
section of the main channel at the upper river side of the bridge is smaller scour depth at the same scour state. In addition, the de-
estimated to be 3:5 m=s during the flood (CECI 2011). Accordingly, velopment of the plastic hinges in unit P10–P13 during the analysis is
the authors conclude that the structure remains elastic if the max- very similar to that in unit P10–P13 (see Fig. 18). The foundation of
imum scour depth, which occurred at pier P10, is 16 m (scour state I). pier P13 reached the yield state first; the foundation of P14 yielded
If the maximum scour depth is 18 m (scour state II), the structure will second; and then P15, and finally P13 reached the failure state. Be-
be close to the yield (initial damage) state. If the maximum scour cause the foundations of piers P13 and P14 had been retrofitted, yet the
depth is 20 m (scour state III), the structure has gone beyond the yield scour depths at their locations were larger, and piers P15 and P16 were
state. If the maximum scour depth is 22.5 m (scour state IV), the nonretrofitted and less scoured, it is concluded that the foundation
structure will be close to the complete failure state. For more severe scour has great influence on the flood-resistant capacity of bridges. In
scour states, a convergent solution cannot be obtained for the this Shuang-Yuan Bridge case, the capacity loss attributable to scour
condition with an average flow velocity of 3:5 m=s. These results exceeds the reinforcing effects of the foundation retrofit.
imply that the scour depth at the Shuang-Yuan Bridge could possibly However, because the focus of this paper is on the stability of the
have been larger than 22.5 m during Typhoon Morakot. scoured foundation under the flow-induced loads, the nonlinearity of the
Fig. 18 depicts the development of the plastic hinges during the superstructure was neglected as mentioned. Thus, the possible structural
displacement control nonlinear quasi-static analysis, using the internal stability between P14 and P15 in terms such as the flexural or
following processes: torsion failures of the girders was not considered in the analysis.
1. First, the original piles of pier P10, where the scour depth is
larger, reached the yield state at segments near the riverbed
because of their smaller flexural strength and the larger Conclusions
experienced moment.
2. The yield zone near the riverbed of the original piles of pier In this study, procedures for the evaluation on the flood-resistant
P10 spread upward and downward, yet the downward- capacity of scoured bridges with pile foundations were proposed,
spreading range is smaller because the pile body below the including the establishment of a soil-structure model for bridges,
riverbed is confined by the supporting soil. Meanwhile, the a simulation of the nonlinearity of the pile-soil system, an estimation
original piles of pier P11 also reached the yield state at of flow-induced loads, analysis processes, and an interpretation of
segments near the riverbed. the analysis results.
3. The piles of pier P10 reached the yield state at segments below The failure of the Shuang-Yuan Bridge during Typhoon Morakot
the pile cap. in 2009 was chosen as a case study for the proposed procedures. The
4. The yield zone below the pile cap of the piles of pier P10 spread possible scour states when the failure occurred were estimated by
downward, and the pile segments below the pile cap of pier comparing the geological data in 1972 and in 2010, and from the
P11 reached the yield state as well. In addition, the piles of pier postfailure ERT investigations. Along with the design details of the
P12 yielded at segments near the riverbed. structure and the soil profile of the site, a FE model of the bridge unit
5. The pile segments near the riverbed of pier P10 reached the was generated for a nonlinear quasi-static analysis under the action
complete failure state. of flow-induced loads.
It was noted that the development of plastic hinges at the addi- According to the analysis results, unit P10–P13 showed a higher
tional piles of the retrofitted foundation is rather minor because of failure potential than unit P13–P16, although the foundations
their better flexural strength. Hence, the authors’ statement that the of all four piers of the former had been retrofitted, as opposed to
ductility of the piles might be insufficient is more conformable to the only two piers of the latter. This is because the scour depth at unit
original ones rather than the additional ones of retrofit work. P10–P13 was apparently larger than at unit P13–P16 in the same
Moreover, the development of the plastic hinges is less severe for the scour state.
piers with smaller scour depths, showing the influence of the scour If the average flow velocity was 3:5 m=s at the cross section of the
depth. main channel at the upper river side of the bridge, the result indicates
that the exposed foundations of unit P10–P13 might reach an initial
Unit P13–P16 damage state if the local scour depth is more than 18 m. If the local
For this unit, two of the four piers had been retrofitted at the foun- scour depth is more than 22.5 m, the unit P10–P13 would possibly
dations. The top of P13 was chosen as the displacement monitoring attain a complete failure state.
point owing to its larger scour depth. The flood-resistant capacity These results also show that, using the procedures proposed in
curves at different scour states are as shown in Fig. 19. The slope of this study, the scour depths at which the yield state and the failure