BILL OF QUANTITY (BQ)


PEKERJAAN : PENGADAAN INSTALASI SYSTEM FIRE HYDRANT STASIUN DAN STABLING KA DI DAOP 9 STA. JEMBER

HARGA SATUAN (Rp) NILAI PEKERJAAN (Rp)


NO VOL SAT URAIAN PEKERJAAN
UPAH BAHAN UPAH BAHAN
A.1. PEKERJAAN PERALATAN UTAMA
1 1.00 bh Memasang 1 bh pompa diesel (pemadam kebakaran), - - - - ###
Pekerjaan Instalasi Diesel Fire Pump (Double Starter), 500 USGPM, Horisontal end Suction,
head 100 Meter, Daya 75 HP, 3000 rpm (External Heat Exchanger), Kontrol Panel NFPA 20 c/w
Pressure Switch, pressure gauge, casing relief valve dan automatic air release valve, main relief
valve, tangki solar 250 liter, pressure tank, serta pipa knalpot (BS) lengkap dengan isolasi
ceramic fibre density 100 kg/m3 thickness 25 mm, Silencer, serta alat bantu sesuai gambar dan
spesifikasi.
Casing : Grey Cast Iron, Impellers : Grey Cast Iron, Pump Shaft : Stainless Steel, Shaft Seal :
Gland Packing

2 1.00 bh Memasang 1 bh pompa electric (pemadam kebakaran), - - - -


Pekerjaan Instalasi Electric Fire Pump (TEFC, Class F Insulation), 500 USGPM, Horisontal end
Suction, head 100 Meter, Daya 75 Kw, 2900 rpm, Kontrol Panel NFPA 20 standart, isolator
breaker, c/w Pressure Switch, pressure gauge, casing relief valve dan automatic air release
valve, serta alat bantu sesuai gambar dan spesifikasi.
Casing : Grey Cast Iron, Impellers : Grey Cast Iron, Pump Shaft : Stainless Steel, Shaft Seal :
Gland Packing

3 1.00 bh Memasang 1 bh jockey pump (pemadam kebakaran), - - - -


Pekerjaan Instalasi Jockey Fire Pump, 10 USGPM, Vertical In-Line Multi Stage, head 110 Meter,
Daya 4 Kw, 2900 rpm, Kontrol Panel NFPA 20 standart, isolator Breaker, c/w Pressure Switch,
pressure gauge, casing relief valve dan automatic air release valve, serta alat bantu sesuai
gambar dan spesifikasi.
Casing : Grey Cast Iron, Impellers : Grey Cast Iron, Pump Shaft : Stainless Steel, Shaft Seal :
Single Mechanical Seal

Pengkabelan Power dan Kontrol dari LCP ke Pompa Pemadam Kebakaran


4 10.00 m Memasang Rak Kabel 400 x 100 x 300, - - - -
5 3.00 bh Memasang Pressure Switch 8-16 Bar - - - -

Instalasi Pemipaan Ruang Pompa


Pekerjaan Pipa Header
6 4.00 m Memasang Pipa BSP sch. 40 ø 200 mm2 - - - -
7 12.00 m Memasang Pipa BSP sch. 40 ø 100 mm2 - - - - ###
8 10.00 m Memasang Pipa BSP sch. 40 ø 50 mm2 - - - -
9 8.00 m Memasang Pipa BSP sch. 40 ø 40 mm2 - - - -

Peralatan & Katup - Katup Ruang Pompa


10 2.00 bh Memasang Vortex Plate diameter 100 mm2, - - - -
11 1.00 bh Memasang Vortex Plate diameter 50 mm2, - - - -
12 6.00 bh Memasang Check Valve diameter 100 mm 10 K, - - - -
13 2.00 bh Memasang Check Valve diameter 50 mm 10 K, - - - -
14 4.00 bh Memasang Flexible Joint diameter 100 mm 10 K, - - - -
15 2.00 bh Memasang Flexible Joint diameter 50 mm 10 K, - - - -
16 5.00 bh Memasang Gate Valve diameter 100 mm 10 K, - - - -
17 2.00 bh Memasang Gate Valve diameter 80 mm 10 K, - - - -
18 3.00 bh Memasang Gate Valve diameter 50 mm 10 K, - - - -
19 2.00 bh Memasang Y Strainer diameter 100 mm 10 K, - - - -
20 1.00 bh Memasang Y Strainer diameter 50 mm 10 K, - - - -
21 2.00 bh Memasang Foot Valve 100 mm - - - -
22 1.00 bh Memasang Foot Valve 50 mm - - - -
23 1.00 bh Memasang Safety Valve 50 mm - - - -

A.2. PEKERJAAN INSTALASI PEMADAM KEBAKARAN


Pekerjaan Instalasi Pemipaan Hydrant, pipa pemadam kebakaran dari bahan Black Steel Pipe
(BSP) SCH.40 termasuk Zinchromate dan cat finish dipasang pada posisinya lengkap dengan
seluruh penyangga, gantungan lengkap dengan alat bantu dan perlengkapan pemasangan
Instalasigambar
sesuai Pipa Dalam dan luar Gedung
dan spesifikasi.
24 330.00 m Memasang Pipa BSP sch. 40 ø 100 mm2 - - - -
25 170.00 m Memasang Pipa BSP sch. 40 ø 80 mm2 - - - -
26 36.00 m Memasang Pipa BSP sch. 40 ø 65 mm2 - - - -
27 12.00 m Memasang Pipa BSP sch. 40 ø 40 mm2 - - - -
28 11.00 bh Memasang Gate Valve diameter 100 mm 10 K, - - - -
29 2.00 bh Memasang Check Valve diameter 100 mm 10 K, - - - -

Peralatan dan Katup - Katup Hydrant


30 3.00 bh Memasang PFE 3 Kg type Dry Chemical Powder c/w Box, - - - -
31 7.00 bh Memasang Indoor Hydrant Box, - - - -
Pekerjaan Indoor Hydrant Box, terbuat dari bahan steel plate setebal 1,2 mm, dengan ukuran 750
mm x 180 mm x 1250 mm , Hose dia 40 mm (rubber), Panjang 30 m, Hose-nozzle dia. 40 mm ,
Hydrant Valve dia. 40 mm, Landing Valve dia. 65 mm , dicat akhir dengan cat duco warna merah
dengan tulisan HYDRANT berwarna putih, dilengkapi dengan kunci serta kaca, pelubangan untuk
Manual Push Button, Indicator Lamp, Jack phone, Alarm bell lengkap dengan alat bantu dan
accessories sesuai gambar dan spesifikasinya.

32 3.00 bh Memasang Outdoor Hydrant Box, - - - -


Pekerjaan Outdoor Hydrant Box , terbuat dari bahan steel plat setebal 1,2 mm, dengan ukuran
33 3.00 bh 660 x 950 xPillar
Memasang 250 mm , Linetype
Hydrant Hose
twodiaway
65 100x65x65
mm panjangmm,30 m (rubber), di cat akhir dengan cat duco - - - -
warna merah dengan tulisan HYDRANT berwarna putih lengkap dengan kaca, kunci, pondasi,
Pekerjaan Pillar Hydrant
serta dilengkapi alat bantutype
dantwo way ukuran
accessories 100 xgambar
sesuai 65 x 65dan
mmspesifikasinya.
dengan gate valve, pondasi, bak
34 2.00 bh kontrol,
Memasang danSiamesse
alat bantuConnection,
sesuai gambar dan spesifikasinya - - - -
Pekerjaan Siamesse Connection type two way c/w Check Valve, Gate Valve pondasi, bak kontrol
disertai alat bantu lainnya sesuai gambar dan spesifikasinya.
A.3. PEKERJAAN PEMASANGAN DEEPWELL
35 1.00 Ls Pengurusan izin pemasangan Deep Well - - - -
Pekerjan Deep Well
36 1.00 ls Pompa Deep Well - - - -
10 m³/jam head 100 m motor 4 kw
Pipa Casing
37 60.00 m Pipa Gip Class Bs 1387 150 mm - - - -
38 90.00 m Pipa Gip Class Bs 1387 100 mm - - - -
Pipa Discharge
39 61.00 m Pipa Gip Class Bs 1387 50 mm - - - -
40 1.00 bh Chek Valve 50 mm 10k - - - -
41 10.00 bh Coupling Joint 50 mm - - - -
42 1.00 bh Gate Valve 50 mm 10 k - - - -
43 1.00 bh Presure Gauge - - - -
44 1.00 Ls Quantity Meter 20 mm 10 k - - - -
45 1.00 bh Automatik Air Vent 25 mm - - - -

A.4. PEKERJAAN INSTALASI KELISTRIKAN


46 1.00 un Pek. Memasang panel PP - UTAMA, - - - -
47 1.00 un Pek. Memasang panel PP - Hydrant, - - - -
48 1.00 un Pek. Memasang panel PP - Deep Well - - - -
49 3.00 m Memasang Kabel Power PLN - PP Utama, - - - -
50 5.00 m Memasang Kabel Power PP Utama - PC Hydrant, - - - -
51 30.00 m Memasang Kabel Power PP Utama - PC Deep Well - - - -
52 10.00 m Memasang Kabel Power Panel Hydrant - Panel PC EFP, - - - -
53 10.00 m Memasang Kabel Power Panel Hydrant - Panel PC JFP, - - - -
54 40.00 m Memasang Kabel Power Panel Hydrant - Panel Control Diesel, - - - -
55 40.00 m Memasang Kabel Power Panel PP Deep Well - Pompa Deep Well, - - - -

56 105,000 VA Pek. Kwh Meter Baru, - - - -

A.5. PEKERJAAN SIPIL


57 54.56 m³ Pek . Galian tanah, - - - -
58 39.00 m³ Pek . Urugan pasir area pipa tertanam, - - - -

Pekerjan Pengaspalan
59 24.40 m² Pekerjan Pengaspalan dengan sandsheet tebal 3cm - - - -

Pekerjan Pembobokan dan perapian keramik


60 60.00 m² pembobokan keramik - - - -
61 60.00 m² Pekerjan Keramik 50 x 50 cm - - - -

Pekerjaan Pondasi Pilar Hydrant, Outdoor Hydrant Box dan Siamesse Connection ###
62 4.73 m³ Pek. Pembuatan beton mutu f'c = 7.4 Mpa (k100) slump (3-6) cm w/c = 0.87, - - - -
63 1.51 m² Pek. Pemasangan bekisting, - - - -

64 1.00 ls Boring Deep Well kedalaman 80 m - - - -

Pekerjan WF 150 X 75
65 700.00 ls WF 150 X 75 - - - -
66 1.13 m³ Pek . Galian tanah, - - - -
67 33.00 kg Pek. Pembesian dengan besi polos atau besi ulir, - - - -
68 1.13 m³ Pek. Pembuatan beton mutu f'c = 26.4 Mpa (k300). slump (12±2) cm .w/c = 0.52, - - - -

Pekerjaan Tangki Air & Rumah Pompa


69 6,879.00 kg Pek. Pembesian dengan besi polos atau besi ulir, - - - -
70 60.00 m³ Pek. Pembuatan beton mutu f'c = 26.4 Mpa (k300). slump (12±2) cm .w/c = 0.52, - - - -
71 180.00 m² Pek. Pemasangan bekisting, - - - -
72 120.00 m³ Pek. Integral Waterproofing, setara SIKA, - - - -
73 262.50 m² Pek. Pengecatan Eksterior (Cat setara Dulux Pofessional Weathershield Sealer E1000), - - - -
74 1.00 bh Pek. Pemasangan Pintu Besi 2 daun, - - - -
75 2.00 bh Pek. Pemasangan Tangga Besi, - - - -
76 1.00 bh Pek. Pembuatan Manhole - - - -
77 2.00 bh Pek. Pemasangan Exhaust Fan Dinding 350 CFM, - - - -
78 3.00 ttk Pek. Titik Lampu - - - -
79 2.00 bh Pek. Saklar Tunggal - - - -
80 3.00 bh Pek. Memasang Lampu - - - -

A.6. PEKERJAAN LAIN-LAIN


81 1.00 ls Pek. testing & commissioning berikut kebutuhan lainya, - - - -
Pelaksanaan testing & commissioning, berikut penyediaan kebutuhan daya listrik, kebutuhan air,
penyediaan bahan bakar soalar untuk paket pekerjaan ini, penyediaan perlengkapan dan
instalasi lain serta pengukur yng dianggap perlu sampai mendapatkan hasil keseluruhan instalasi
dapat berfungsi dengan baik dan dapat memenuhi semua persaratan yang diminta. Pelaksanaan
testing & commisioning harus disaksikan dan ditandatangani oleh konsultan perencana

82 1.00 ls - - - -
Biaya pengurusan izin sampai diterbitkannya surat rekomendasi dari Dinas pemadam Kebakaran,
83 1.00 ls Pengurusan semua izin-izin termasuk pengeboran dan SIPA untuk pemsangan serta - - - -
pengoprasian instalasi yang terpasang
84 1.00 ls Pengisian bahan bakar solar untuk pompa diesel setelah testing commisioning (Full Tank), - - - -
85 12.00 m2 Pembuatan direksi keet, - - - -

JUMLAH TOTAL - - ###


PPN 10% - -
JUMLAH TOTAL+PPN10% - -
JUMLAH RAYA -
JUMLAH RAYA (PEMBULATAN) - ###
TERBILANG : ###
###
###
......................................., ... - ... - ...................... ###
PT. .................................................
Jabatan

materai
Rp 6.000,-

..........................................................
.......................................
ANALISA HARGA SATUAN

PENGADAAN INSTALASI SYSTEM FIRE HYDRANT STASIUN DAN STABLING KA DI DAOP 9 STA. JEMBER

1 bh Memasang 1 bh pompa diesel (pemadam kebakaran) -


Bahan An. SNI ( Revisi ) 6.33.1
1.0000 bh Diesel Fire Pump 500 USGPM Rp. 0.00 = -
1.0000 % Perlengkapan(Spring Mounting, sewa Forklift) Rp. 0.00 = -
Upah An. SNI ( Revisi ) 6.32.2
3.0000 Oh Pekerja Rp. 0.00 = -
3.0000 Oh Tukang Rp. 0.00 = -
2.0000 Oh Kepala tukang Rp. 0.00 = -
1.0000 Oh Mandor Rp. 0.00 = - +
JUMLAH = - -
2 bh Memasang 1 bh pompa electric (pemadam kebakaran)
Bahan An. SNI ( Revisi ) 6.33.1
1.0000 bh Electric Fire Pump 500 USGPM Rp. 0.00 = -
5.0000 % Perlengkapan(Spring Mounting, sewa Forklift) Rp. 0.00 = -
Upah An. SNI ( Revisi ) 6.32.2
3.0000 Oh Pekerja Rp. 0.00 = -
3.0000 Oh Tukang Rp. 0.00 = -
2.0000 Oh Kepala tukang Rp. 0.00 = -
1.0000 Oh Mandor Rp. 0.00 = - +
JUMLAH = - -

3 bh Memasang 1 bh jockey pump (pemadam kebakaran)


Bahan An. SNI ( Revisi ) 6.33.1
1.0000 bh Jockey Fire Pump 10 USGPM Rp. 0.00 = -
15.0000 % Perlengkapan Rp. 0.00 = -
Upah An. SNI ( Revisi ) 6.32.2
2.0000 Oh Pekerja Rp. 0.00 = -
2.0000 Oh Tukang Rp. 0.00 = -
1.0000 Oh Kepala tukang Rp. 0.00 = -
1.0000 Oh Mandor Rp. 0.00 = - +
JUMLAH = - -

4 m Memasang Rak Kabel 400 x 100 x 300


Bahan
1.0000 m Rak Kabel 400x100x300 Rp. 0.00 = -
5.0000 % Perlengkapan instalasi Rp. 0.00 = -

Upah An. SNI ( Revisi ) 6.32.2


0.166 Oh Pembantu Tukang Listrik Rp. 0.00 = -
0.166 Oh Tukang Listrik Rp. 0.00 = -
0.033 Oh Kepala Tukang Listrik Rp. 0.00 = -
0.017 Oh Mandor Rp. 0.00 = - +
JUMLAH = - -

5 bh Memasang Pressure Switch 8-16 Bar


Bahan An. SNI ( Revisi ) 6.33.1
1.0000 bh Pressure Switch Rp. 0.00 = -
10.0000 % Perlengkapan instalasi Rp. 0.00 = -

Upah
An. SNI ( Revisi ) 6.32.2
0.2000 Oh Pekerja Rp. 0.00 = -
0.2000 Oh Tukang Rp. 0.00 = -
0.0200 Oh Kepala tukang Rp. 0.00 = -
0.0200 Oh Mandor Rp. 0.00 = - +
JUMLAH = - -
6 m Memasang Pipa BSP sch. 40 ø 200 mm
Bahan
1.0000 m Pipa BSP sch. 40 ø 200 mm Rp. 0.00 = -
35.0000 % Perlengkapan instalasi : Rp. 0.00 = -
- Dynabolt uk. 20 x 151 mm
- Besi Kanal
- U-Bolt
- Round Steel dia. 15 mm
- Las
- Zinc chromate
- Cat Finish
- Fitting Cabang Dia 200mm2
- Fitting Cabang Dia 100 mm2
- Support
Upah An. SNI ( Revisi ) 6.19.2
0.1350 Oh Pekerja Rp. 0.00 = -
0.2250 Oh Tukang Rp. 0.00 = -
0.0225 Oh Kepala tukang Rp. 0.00 = -
0.0068 Oh Mandor Rp. 0.00 = - +
JUMLAH = - -
7 m Memasang pipa BSP sch. 40 ø 100 mm
Bahan An. SNI ( Revisi ) 6.19.1
1.0000 m Pipa BSP sch. 40 ø 100mm Rp. 0.00 = -
35.0000 % Perlengkapan instalasi : Rp. 0.00 = -
- Dynabolt uk. 20 x 151 mm
- Besi Kanal
- U-Bolt
- Round Steel dia. 15 mm
- Las
- Zinc chromate
- Cat Finish
- Fitting Cabang Dia 100 mm2
- Support

Upah An. SNI ( Revisi ) 6.19.2


0.1350 Oh Pekerja Rp. 0.00 = -
0.2250 Oh Tukang Rp. 0.00 = -
0.0225 Oh Kepala tukang Rp. 0.00 = -
0.0068 Oh Mandor Rp. 0.00 = - +
JUMLAH = - -

8 m Memasang Pipa BSP sch. 40 ø 50mm


Bahan An. SNI ( Revisi ) 6.19.1
1.0000 m Pipa BSP sch. 40 ø 50mm Rp. 0.00 = -
35.0000 % Perlengkapan instalasi : Rp. 0.00 = -
- Dynabolt uk. 20 x 151 mm
- Besi Kanal
- U-Bolt
- Round Steel dia. 15 mm
- Las
- Zinc chromate
- Cat Finish
- Fitting Cabang Dia 50 mm2
- Support

Upah An. SNI ( Revisi ) 6.19.2


0.1350 Oh Pekerja Rp. 0.00 = -
0.2250 Oh Tukang Rp. 0.00 = -
0.0225 Oh Kepala tukang Rp. 0.00 = -
0.0068 Oh Mandor Rp. 0.00 = - +
JUMLAH = - -
9 m Memasang Pipa BSP sch. 40 ø 40 mm
Bahan An. SNI ( Revisi ) 6.19.1
1.0000 m Pipa BSP sch. 40 ø 40mm Rp. 0.00 = -
35.0000 % Perlengkapan instalasi : Rp. 0.00 = -
- Dynabolt uk. 20 x 151 mm
- Besi Kanal
- U-Bolt
- Round Steel dia. 15 mm
- Las
- Zinc chromate
- Cat Finish
- Fitting Cabang Dia 40 mm2
- Support

Upah An. SNI ( Revisi ) 6.19.2


0.1350 Oh Pekerja Rp. 0.00 = -
0.2250 Oh Tukang Rp. 0.00 = -
0.0225 Oh Kepala tukang Rp. 0.00 = -
0.0068 Oh Mandor Rp. 0.00 = - +
JUMLAH = - -

10 un Memasang Vortex Plate diameter 100 mm


Bahan
1.0000 bh Anti Vortex diameter 100 mm Rp. 0.00 = -
1.0000 bh Flange dia. 100 mm Rp. 0.00 = -
1.0000 % Perlengkapan instalasi : Rp. 0.00 = -
Upah
4.0000 % Instalasi Rp. 0.00 = - +
JUMLAH = - -

11 un Memasang Vortex Plate diameter 50 mm


Bahan
1.0000 bh Anti Vortex diameter 50 mm Rp. 0.00 = -
1.0000 bh Flange dia. 50 mm Rp. 0.00 = -
1.0000 % Perlengkapan instalasi : Rp. 0.00 = -

Upah
4.0000 % Instalasi Rp. 0.00 = - +
JUMLAH = - -

12 bh Memasang Check Valve diameter 100 mm 10 K


Bahan
1.0000 bh Check Valve diameter 100 mm 10 K Rp. 0.00 = -
1.0000 bh Flange dia. 100 mm Rp. 0.00 = -
10.0000 % Perlengkapan instalasi Rp. 0.00 = -
upah
An. SNI ( Revisi ) 6.32.2
0.4000 Oh Pekerja Rp. 0.00 = -
0.4000 Oh Tukang Rp. 0.00 = -
0.0400 Oh Kepala tukang Rp. 0.00 = -
0.0400 Oh Mandor Rp. 0.00 = - +
JUMLAH = - -
13 bh Memasang Check Valve diameter 50 mm 10 K
Bahan
1.0000 bh Check Valve diameter 50 mm 10 K Rp. 0.00 = -
1.0000 bh Flange dia. 50 mm Rp. 0.00 = -
10.0000 % Perlengkapan instalasi Rp. 0.00 = -
upah
An. SNI ( Revisi ) 6.32.2
0.4000 Oh Pekerja Rp. 0.00 = -
0.4000 Oh Tukang Rp. 0.00 = -
0.0400 Oh Kepala tukang Rp. 0.00 = -
0.0400 Oh Mandor Rp. 0.00 = - +
JUMLAH = - -
14 bh Memasang Flexible Joint diameter 100 mm 10 K
Bahan
1.0000 bh Flexible Joint diameter 100 mm 10 K Rp. 0.00 = -
1.0000 bh Flange dia. 100 mm Rp. 0.00 = -
10.0000 % Perlengkapan instalasi Rp. 0.00 = -

Upah An. SNI ( Revisi ) 6.32.2


0.4000 Oh Pekerja Rp. 0.00 = -
0.4000 Oh Tukang Rp. 0.00 = -
0.0400 Oh Kepala tukang Rp. 0.00 = -
0.0400 Oh Mandor Rp. 0.00 = - +
JUMLAH = - -

15 bh Memasang Flexible Joint diameter 50 mm 10 K


Bahan
1.0000 bh Flexible Joint diameter 50 mm 10 K Rp. 0.00 = -
1.0000 bh Flange dia. 50 mm Rp. 0.00 = -
10.0000 % Perlengkapan instalasi Rp. 0.00 = -

Upah An. SNI ( Revisi ) 6.32.2


0.1000 Oh Pekerja Rp. 0.00 = -
0.1000 Oh Tukang Rp. 0.00 = -
0.0100 Oh Kepala tukang Rp. 0.00 = -
0.0018 Oh Mandor Rp. 0.00 = - +
JUMLAH = - -

16 bh Memasang Gate Valve diameter 100 mm 10 K


Bahan
1.0000 bh Gate Valve diameter 100 mm 10 K Rp. 0.00 = -
1.0000 bh Flange dia. 100 mm Rp. 0.00 = -
10.0000 % Perlengkapan instalasi Rp. 0.00 = -

Upah An. SNI ( Revisi ) 6.32.2


0.1000 Oh Pekerja Rp. 0.00 = -
0.1000 Oh Tukang Rp. 0.00 = -
0.0100 Oh Kepala tukang Rp. 0.00 = -
0.0020 Oh Mandor Rp. 0.00 = - +
JUMLAH = - -

17 bh Memasang Gate Valve diameter 80 mm 10 K


Bahan
1.0000 bh Gate Valve diameter 80 mm 10 K Rp. 0.00 = -
1.0000 bh Flange dia. 80 mm Rp. 0.00 = -
10.0000 % Perlengkapan instalasi Rp. 0.00 = -

Upah An. SNI ( Revisi ) 6.32.2


0.1000 Oh Pekerja Rp. 0.00 = -
0.1000 Oh Tukang Rp. 0.00 = -
0.0100 Oh Kepala tukang Rp. 0.00 = -
0.0020 Oh Mandor Rp. 0.00 = - +
JUMLAH = - -

18 bh Memasang Gate Valve diameter 50 mm 10 K


Bahan An. SNI ( Revisi ) 6.33.1
1.0000 bh Gate Valve diameter 50 mm 10 K Rp. 0.00 = -
1.0000 bh Flange dia. 50 mm Rp. 0.00 = -
10.0000 % Perlengkapan instalasi Rp. 0.00 = -

Upah An. SNI ( Revisi ) 6.32.2


0.1000 Oh Pekerja Rp. 0.00 = -
0.1000 Oh Tukang Rp. 0.00 = -
0.0100 Oh Kepala tukang Rp. 0.00 = -
0.0020 Oh Mandor Rp. 0.00 = - +
JUMLAH = - -

19 bh Memasang Y Strainer diameter 100 mm 10 K


Bahan
1.0000 bh Y Strainer diameter 100 mm 10 K Rp. 0.00 = -
1.0000 bh Flange dia. 100 mm Rp. 0.00 = -
10.0000 % Perlengkapan instalasi Rp. 0.00 = -

Upah An. SNI ( Revisi ) 6.32.2


0.1000 Oh Pekerja Rp. 0.00 = -
0.1000 Oh Tukang Rp. 0.00 = -
0.0100 Oh Kepala tukang Rp. 0.00 = -
0.0020 Oh Mandor Rp. 0.00 = - +
JUMLAH = - -

20 bh Memasang Y Strainer diameter 50 mm 10 K


Bahan
1.0000 bh Y Strainer diameter 50 mm 10 K Rp. 0.00 = -
1.0000 bh Flange dia. 50 mm Rp. 0.00 = -
10.0000 % Perlengkapan instalasi Rp. 0.00 = -

Upah An. SNI ( Revisi ) 6.32.2


0.1000 Oh Pekerja Rp. 0.00 = -
0.1000 Oh Tukang Rp. 0.00 = -
0.0100 Oh Kepala tukang Rp. 0.00 = -
0.0020 Oh Mandor Rp. 0.00 = - +
JUMLAH = - -

21 bh Memasang Foot Valve 100 mm


Bahan
1.0000 bh Foot Valve 100 mm Rp. 0.00 = -
1.0000 bh Flange dia. 100 mm Rp. 0.00 = -
10.0000 % Perlengkapan instalasi Rp. 0.00 = -

Upah An. SNI ( Revisi ) 6.32.2


0.1500 Oh Pekerja Rp. 0.00 = -
0.1500 Oh Tukang Rp. 0.00 = -
0.0150 Oh Kepala tukang Rp. 0.00 = -
0.0100 Oh Mandor Rp. 0.00 = - +
JUMLAH = - -

22 bh Memasang Foot Valve 50 mm


Bahan
1.0000 bh Foot Valve 50 mm Rp. 0.00 = -
1.0000 bh Flange dia. 50 mm Rp. 0.00 = -
10.0000 % Perlengkapan instalasi Rp. 0.00 = -

Upah An. SNI ( Revisi ) 6.32.2


0.1500 Oh Pekerja Rp. 0.00 = -
0.1500 Oh Tukang Rp. 0.00 = -
0.0150 Oh Kepala tukang Rp. 0.00 = -
0.0100 Oh Mandor Rp. 0.00 = - +
JUMLAH = - -
23 bh Memasang Safety Valve diameter 50 mm
Bahan An. SNI ( Revisi ) 6.33.1
1.0000 bh Safety Valve diameter 50 mm Rp. 0.00 = -
10.0000 % Perlengkapan instalasi Rp. 0.00 = -

Upah
An. SNI ( Revisi ) 6.32.2
0.2000 Oh Pekerja Rp. 0.00 = -
0.2000 Oh Tukang Rp. 0.00 = -
0.0200 Oh Kepala tukang Rp. 0.00 = -
0.0200 Oh Mandor Rp. 0.00 = - +
JUMLAH = - -

24 m Memasang Pipa BSP sch. 40 ø 100 mm


Bahan An. SNI ( Revisi ) 6.17.1
1.0000 m Pipa BSP sch. 40 ø 100mm Rp. 0.00 = -
35.0000 % Perlengkapan instalasi : Rp. 0.00 = -
- Dynabolt uk. 20 x 151 mm
- Besi Kanal
- U-Bolt
- Round Steel dia. 15 mm
- Las
- Zinc chromate
- Cat Finish
- Fitting Cabang Dia 100 mm2
- Support
- Isolasi aspal plus karung (untuk Pipa tertanam)

Upah An. SNI ( Revisi ) 6.17.2


0.1350 Oh Pekerja Rp. 0.00 = -
0.2250 Oh Tukang Rp. 0.00 = -
0.0225 Oh Kepala tukang Rp. 0.00 = -
0.0068 Oh Mandor Rp. 0.00 = - +
JUMLAH = - -

25 m Memasang Pipa BSP sch. 40 ø 80mm


Bahan
1.0000 m Pipa BSP sch. 40 ø 80mm Rp. 0.00 = -
35.0000 % Perlengkapan instalasi : Rp. 0.00 = -
- Dynabolt uk. 20 x 151 mm
- Besi Kanal
- U-Bolt
- Round Steel dia. 15 mm
- Las
- Zinc chromate
- Cat Finish
- Fitting Cabang Dia 80 mm2
- Support
- Isolasi aspal plus karung (untuk Pipa tertanam)

Upah An. SNI ( Revisi ) 6.16.2


0.1350 Oh Pekerja Rp. 0.00 = -
0.2250 Oh Tukang Rp. 0.00 = -
0.0225 Oh Kepala tukang Rp. 0.00 = -
0.0068 Oh Mandor Rp. 0.00 = - +
JUMLAH = - -

26 m Memasang Pipa BSP sch. 40 ø 65mm


Bahan An. SNI ( Revisi ) 6.19.1
1.0000 m Pipa BSP sch. 40 ø 65mm Rp. 0.00 = -
35.0000 % Perlengkapan instalasi : Rp. 0.00 = -
- Dynabolt uk. 20 x 151 mm
- Besi Kanal
- U-Bolt
- Round Steel dia. 15 mm
- Las
- Zinc chromate
- Cat Finish
- Fitting Cabang Dia 65 mm2
- Support
- Isolasi aspal plus karung (untuk Pipa tertanam)
Upah An. SNI ( Revisi ) 6.19.2
0.1350 Oh Pekerja Rp. 0.00 = -
0.2250 Oh Tukang Rp. 0.00 = -
0.0225 Oh Kepala tukang Rp. 0.00 = -
0.0068 Oh Mandor Rp. 0.00 = - +
JUMLAH = - -

27 m Memasang Pipa BSP sch. 40 ø 40 mm


Bahan An. SNI ( Revisi ) 6.13.1
1.0000 m Pipa BSP sch. 40 ø 40mm Rp. 0.00 = -
35.0000 % Perlengkapan instalasi : Rp. 0.00 = -
- Dynabolt uk. 20 x 151 mm
- Besi Kanal
- U-Bolt
- Round Steel dia. 15 mm
- Las
- Zinc chromate
- Cat Finish
- Fitting Cabang Dia 40 mm2
- Support
- Isolasi aspal plus karung (untuk Pipa tertanam)

Upah An. SNI ( Revisi ) 6.13.2


0.108 Oh Pekerja Rp. 0.00 = -
0.180 Oh Tukang Rp. 0.00 = -
0.018 Oh Kepala tukang Rp. 0.00 = -
0.0054 Oh Mandor Rp. 0.00 = - +
JUMLAH = - -

28 bh Memasang Gate Valve diameter 100 mm 10 K


Bahan
1.0000 bh Gate Valve diameter 100 mm 10 K Rp. 0.00 = -
1.0000 bh Flange dia. 100 mm Rp. 0.00 = -
10.0000 % Perlengkapan instalasi Rp. 0.00 = -

Upah An. SNI ( Revisi ) 6.32.2


0.1000 Oh Pekerja Rp. 0.00 = -
0.1000 Oh Tukang Rp. 0.00 = -
0.0100 Oh Kepala tukang Rp. 0.00 = -
0.0020 Oh Mandor Rp. 0.00 = - +
JUMLAH = - -
29 bh Memasang Check Valve diameter 100 mm 10 K
Bahan
1.0000 bh Check Valve diameter 100 mm 10 K Rp. 0.00 = -
1.0000 bh Flange dia. 100 mm Rp. 0.00 = -
10.0000 % Perlengkapan instalasi Rp. 0.00 = -
upah
An. SNI ( Revisi ) 6.32.2
0.4000 Oh Pekerja Rp. 0.00 = -
0.4000 Oh Tukang Rp. 0.00 = -
0.0400 Oh Kepala tukang Rp. 0.00 = -
0.0400 Oh Mandor Rp. 0.00 = - +
JUMLAH = - -
30 bh Memasang PFE 3 Kg type Dry Chemical Powder c/w Box
Bahan
1.0000 bh PFE 3 Kg type Dry Chemical Powder c/w Box Rp. 0.00 = -
10.0000 % Perlengkapan instalasi Rp. 0.00 = -

Upah
An. SNI ( Revisi ) 6.32.2
0.2000 Oh Pekerja Rp. 0.00 = -
0.2000 Oh Tukang Rp. 0.00 = -
0.0200 Oh Kepala tukang Rp. 0.00 = -
0.0200 Oh Mandor Rp. 0.00 = - +
JUMLAH = - -

31 bh Memasang Indoor Hydrant Box


Bahan
1.0000 bh Indoor Hydrant Box Rp. 0.00 = -
10.0000 % Perlengkapan instalasi Rp. 0.00 = -
- Baut+mur
-Dynabolt uk 20x151 mm
-Trolyy
Upah An. SNI ( Revisi ) 6.32.2
0.5000 Oh Pekerja Rp. 0.00 = -
0.5000 Oh Tukang Rp. 0.00 = -
0.0500 Oh Kepala tukang Rp. 0.00 = -
0.0500 Oh Mandor Rp. 0.00 = - +
JUMLAH = - -

32 bh Memasang Outdoor Hydrant Box


Bahan
1.0000 bh Outdoor Hydrant Box Rp. 0.00 = -
10.0000 % Perlengkapan instalasi Rp. 0.00 = -
- Baut+mur
-Dynabolt uk 20x151 mm
-Trolyy
Upah An. SNI ( Revisi ) 6.32.2
0.5000 Oh Pekerja Rp. 0.00 = -
0.5000 Oh Tukang Rp. 0.00 = -
0.0500 Oh Kepala tukang Rp. 0.00 = -
0.0500 Oh Mandor Rp. 0.00 = - +
JUMLAH = - -

33 bh Memasang Pillar Hydrant type two way 100x65x65 mm


Bahan
1.0000 bh Twin Siamesse Connection 100 x 65 x 65 Rp. 0.00 = -
1.0000 bh Gate Valve Valve diameter 100 mm Rp. 0.00 = -
1.0000 bh Flange dia. 150 mm Rp. 0.00 = -
10.0000 % Perlengkapan instalasi Rp. 0.00 = -
- Baut+mur
-Dynabolt uk 20x151 mm
-Trolyy
- pondasi
- bak kontrol
Upah An. SNI ( Revisi ) 6.32.2
0.5000 Oh Pekerja Rp. 0.00 = -
0.5000 Oh Tukang Rp. 0.00 = -
0.0500 Oh Kepala tukang Rp. 0.00 = -
0.0500 Oh Mandor Rp. 0.00 = - +
JUMLAH = - -

34 bh Memasang Siamesse Connection


Bahan
1.0000 bh Twin Siamesse Connection Rp. 0.00 = -
1.0000 bh Check Valve Valve diameter 100 mm Rp. 0.00 = -
1.0000 bh Gate Valve Valve diameter 100 mm Rp. 0.00 = -
3.0000 bh Flange dia s. 100 mm Rp. 0.00 = -
10.0000 % Perlengkapan instalasi Rp. 0.00 = -
- Baut+mur
-Dynabolt uk 20x151 mm
-Trolyy
- pondasi
- bak kontrol
Upah An. SNI ( Revisi ) 6.32.2
0.5000 Oh Pekerja Rp. 0.00 = -
0.5000 Oh Tukang Rp. 0.00 = -
0.0500 Oh Kepala tukang Rp. 0.00 = -
0.0500 Oh Mandor Rp. 0.00 = - +
JUMLAH = - -

35 ls Pengurusan izin pemasangan Deep Well


Upah
1.000 LS Biaya Pengurusan izin pemasangan Deep Well Rp. 0.00 = -
JUMLAH = - -

36 bh Memasang 1 bh Pompa Deep Well -


Bahan An. SNI ( Revisi ) 6.31.1
1.0000 bh Pompa Sumersible Rp. 0.00 = -
25.0000 % Perlengkapan instalasi : Rp. 0.00 = -
Upah An. SNI ( Revisi ) 6.32.2
30.0000 Oh Pekerja Rp. 0.00 = -
30.0000 Oh Tukang Rp. 0.00 = -
10.0000 Oh Kepala tukang Rp. 0.00 = -
10.0000 Oh Mandor Rp. 0.00 = - +
JUMLAH = - -
37 m Pemasangan Pipa Gip Class Bs 1387 150 mm
Bahan
1.0000 m Pipa Gip Class Bs 1387 150 mm Rp. 0.00 = -
35.0000 % Perlengkapan instalasi : Rp. 0.00 = -
Fiting 150 mm

Upah An. SNI ( Revisi ) 6.7.2


0.135 Oh Pekerja Rp. 0.00 = -
0.225 Oh Tukang Rp. 0.00 = -
0.025 Oh Kepala tukang Rp. 0.00 = -
0.0068 Oh Mandor Rp. 0.00 = - +
JUMLAH = - -
38 m Pemasangan Pipa Gip Class Bs 1387 100 mm
Bahan
1.0000 m Pipa Gip Class Bs 1387 100 mm Rp. 0.00 = -
35.0000 % Perlengkapan instalasi : Rp. 0.00 = -
Fiting 100 mm

Upah An. SNI ( Revisi ) 6.7.2


0.135 Oh Pekerja Rp. 0.00 = -
0.225 Oh Tukang Rp. 0.00 = -
0.025 Oh Kepala tukang Rp. 0.00 = -
0.0068 Oh Mandor Rp. 0.00 = - +
JUMLAH = - -
39 m Pipa Gip Class Bs 1387 50 mm
Bahan
1.0000 m Pipa Gip Class Bs 1387 50 mm Rp. 0.00 = -
35.0000 % Perlengkapan instalasi : Rp. 0.00 = -
Fiting 100 mm

Upah An. SNI ( Revisi ) 6.7.2


0.135 Oh Pekerja Rp. 0.00 = -
0.225 Oh Tukang Rp. 0.00 = -
0.025 Oh Kepala tukang Rp. 0.00 = -
0.0068 Oh Mandor Rp. 0.00 = - +
JUMLAH = - -
40 bh Memasang Check Valve diameter 50 mm 10 K
Bahan
1.0000 bh Check Valve diameter 50 mm 10 K Rp. 0.00 = -
1.0000 bh Flange dia. 50 mm Rp. 0.00 = -
1.0000 % Perlengkapan instalasi Rp. 0.00 = -
upah
An. SNI ( Revisi ) 6.32.2
0.4000 Oh Pekerja Rp. 0.00 = -
0.4000 Oh Tukang Rp. 0.00 = -
0.0400 Oh Kepala tukang Rp. 0.00 = -
0.0400 Oh Mandor Rp. 0.00 = - +
JUMLAH = - -
41 bh Memasang Coupling Joint 50 mm
Bahan
1.0000 bh Coupling Joint 50 mm Rp. 0.00 = -
10.0000 % Perlengkapan instalasi Rp. 0.00 = -

Upah An. SNI ( Revisi ) 6.32.2


0.1000 Oh Pekerja Rp. 0.00 = -
0.1000 Oh Tukang Rp. 0.00 = -
0.0100 Oh Kepala tukang Rp. 0.00 = -
0.0018 Oh Mandor Rp. 0.00 = - +
JUMLAH = - -
42 bh Memasang Gate Valve diameter 50 mm 10 K
Bahan
1.0000 bh Gate Valve diameter 50 mm 10 K Rp. 0.00 = -
1.0000 bh Flange dia. 50 mm Rp. 0.00 = -
10.0000 % Perlengkapan instalasi Rp. 0.00 = -

Upah An. SNI ( Revisi ) 6.32.2


0.1000 Oh Pekerja Rp. 0.00 = -
0.1000 Oh Tukang Rp. 0.00 = -
0.0100 Oh Kepala tukang Rp. 0.00 = -
0.0020 Oh Mandor Rp. 0.00 = - +
JUMLAH = - -
43 bh Memasang Presure Gauge
Bahan An. SNI ( Revisi ) 6.33.1
1.0000 bh Presure Gauge Rp. 0.00 = -
10.0000 % Perlengkapan instalasi Rp. 0.00 = -

Upah
An. SNI ( Revisi ) 6.32.2
0.2000 Oh Pekerja Rp. 0.00 = -
0.2000 Oh Tukang Rp. 0.00 = -
0.0200 Oh Kepala tukang Rp. 0.00 = -
0.0200 Oh Mandor Rp. 0.00 = - +
JUMLAH = - -
44 bh Pek. Quantity Meter 20 mm 10 k
bahan An. SNI ( Revisi ) 6.21.1
1.0000 bh Quantity Meter 20 mm 10 k Rp. 0.00 = -
5.0000 % Perlengkapan instalasi Rp. 0.00 = -

Upah An. SNI ( Revisi ) 6.32.1


0.1660 oh Pembantu Tukang Listrik Rp. 0.00 = -
0.1660 oh Tukang Listrik Rp. 0.00 = -
0.0330 oh Kepala Tukang Listrik Rp. 0.00 = -
0.0166 oh Mandor Rp. 0.00 = -
JUMLAH = - -
45 bh Pek. Automatik Air Vent 25 mm
bahan An. SNI ( Revisi ) 6.21.1
1.0000 bh Automatik Air Vent 25 mm Rp. 0.00 = -
5.0000 % Perlengkapan instalasi Rp. 0.00 = -

Upah An. SNI ( Revisi ) 6.32.1


0.1660 oh Pembantu Tukang Listrik Rp. 0.00 = -
0.1660 oh Tukang Listrik Rp. 0.00 = -
0.0330 oh Kepala Tukang Listrik Rp. 0.00 = -
0.0166 oh Mandor Rp. 0.00 = -
JUMLAH = - -
46 un Pek. Memasang panel PP - UTAMA
Bahan
2.0000 Bh MCCB 3P In 320-630 A Rp. 0.00 -
1.0000 Bh MCCB 3P In 40 A Rp. 0.00 -
1.0000 Bh MCB 3P 25 A Rp. 0.00 -
1.0000 M MCB 3P 16 A Rp. 0.00 -
1.0000 Bh MCB 1P 16 A Rp. 0.00 -
3.0000 Bh Pilot Lamp Rp. 0.00 -
2.0000 set Fuse 2A Rp. 0.00 -
3.0000 set ampere meter 30/5 Rp. 0.00 -
2.0000 set volt meter 96x96. Rp. 0.00 -
1.0000 Bh selektor auto man Rp. 0.00 -
3.0000 Bh CT300/5 A Rp. 0.00 -
1.0000 Bh Box Panel 50x70x20 (minimum) Rp. 0.00 -
1.0000 Bh Busbar CU 4x40 Rp. 0.00 -
24.0000 Set. Kabel BC 50 mm Rp. 0.00 -
5.0000 % Perlengkapan Inastalasi Rp. 0.00 -
Upah
5.0000 % Instalasi Rp. 0.00 - +
JUMLAH = - -
47 un Pek. Memasang panel PP - Hydrant
Bahan
1.0000 Bh MCCB 3P In 320-630 A Rp. 0.00 -
1.0000 Bh MCCB 3P In 40 A Rp. 0.00 -
1.0000 Bh MCCB 30 A Rp. 0.00 -
1.0000 M MCB 3P 16 A Rp. 0.00 -
1.0000 Bh MCB 1P 16 A Rp. 0.00 -
3.0000 Bh Pilot Lamp Rp. 0.00 -
3.0000 Bh CT300/5 A Rp. 0.00 -
3.0000 set ampere meter 30/5 Rp. 0.00 -
2.0000 set volt meter 96x96. Rp. 0.00 -
1.0000 Bh selektor auto man Rp. 0.00 -
3.0000 Bh Pilot Lamp Rp. 0.00 -
2.0000 set Fuse 2A Rp. 0.00 -
1.0000 Bh Box Panel 50x70x20 (minimum) Rp. 0.00 -
1.0000 Bh Busbar CU 4x40 Rp. 0.00 -
1.0000 Bh Star Delta Starter 7.5 HP Rp. 0.00 -
24.0000 Set. Kabel BC 50 mm Rp. 0.00 -
5.0000 % Perlengkapan Inastalasi Rp. 0.00 -
Upah
5.0000 % Instalasi Rp. 0.00 - +
JUMLAH = - -
48 un Pek. Memasang panel PP - Deepwell
Bahan
1.0000 Bh Box Panel 400x400x200 Rp. 0.00 -
1.0000 Bh MCCB 3P In 30-40 A setara ABB, scheneider Rp. 0.00 -
1.0000 Bh Contactor 7.5 KW setara scheneider Rp. 0.00 -
3.0000 Bh Pilot Lamp Rp. 0.00 -
1.0000 Bh selektor auto man Rp. 0.00 -
1.0000 set PFR setara GAE Rp. 0.00 -
2.0000 Bh Fuse 2A Rp. 0.00 -
1.0000 Bh Busbar CU 4x12x2 Rp. 0.00 -
1.0000 Set. Kabel BC 50 mm Rp. 0.00 -
5.0000 % Perlengkapan Inastalasi Rp. 0.00 -
Upah
5.0000 % Instalasi Rp. 0.00 - +
JUMLAH = - -
49 m Memasang Kabel Power PLN - PP Utama
Bahan
1.0000 m KABEL NYY 4X185 Rp. 0.00 = -
0.0000 m Conduit pipa dia. 20 Rp. 0.00 = -
5.0000 % Perlengkapan instalasi Rp. 0.00 = -

Upah An. SNI ( Revisi ) 6.8.2


0.1660 Oh Pembantu tukang listrik Rp. 0.00 = -
0.1660 Oh Tukang listrik Rp. 0.00 = -
0.0330 Oh Kepala tukang listrik Rp. 0.00 = -
0.0166 Oh Mandor Rp. 0.00 = - +
JUMLAH = - -

50 m Memasang Kabel Power PP Utama - PC Hydrant


Bahan
1.0000 m KABEL FRC 4X185 Rp. 0.00 = -
0.0000 m Conduit pipa dia. 20 Rp. 0.00 = -
5.0000 % Perlengkapan instalasi Rp. 0.00 = -

Upah An. SNI ( Revisi ) 6.8.2


0.1660 Oh Pembantu tukang listrik Rp. 0.00 = -
0.1660 Oh Tukang listrik Rp. 0.00 = -
0.0330 Oh Kepala tukang listrik Rp. 0.00 = -
0.0166 Oh Mandor Rp. 0.00 = - +
JUMLAH = - -

51 m Memasang Kabel Power PP Utama - PC Deepwell


Bahan
1.0000 m Kabel NYFGBY 4x6 Rp. 0.00 = -
0.0000 m Conduit pipa dia. 20 Rp. 0.00 = -
5.0000 % Perlengkapan instalasi Rp. 0.00 = -

Upah An. SNI ( Revisi ) 6.8.2


0.1660 Oh Pembantu tukang listrik Rp. 0.00 = -
0.1660 Oh Tukang listrik Rp. 0.00 = -
0.0330 Oh Kepala tukang listrik Rp. 0.00 = -
0.0166 Oh Mandor Rp. 0.00 = - +
JUMLAH = - -

52 m Memasang Kabel Power Panel Hydrant - Panel PC EFP


Bahan
1.0000 m KABEL FRC 4X6 Rp. 0.00 = -
0.0000 m Conduit pipa dia. 20 Rp. 0.00 = -
5.0000 % Perlengkapan instalasi Rp. 0.00 = -

Upah An. SNI ( Revisi ) 6.8.2


0.1660 Oh Pembantu tukang listrik Rp. 0.00 = -
0.1660 Oh Tukang listrik Rp. 0.00 = -
0.0330 Oh Kepala tukang listrik Rp. 0.00 = -
0.0166 Oh Mandor Rp. 0.00 = - +
JUMLAH = - -

53 m Memasang Kabel Power Panel Hydrant - Panel PC JFP


Bahan
1.0000 m KABEL FRC 4X6 Rp. 0.00 = -
0.0000 m Conduit pipa dia. 20 Rp. 0.00 = -
5.0000 % Perlengkapan instalasi Rp. 0.00 = -

Upah An. SNI ( Revisi ) 6.8.2


0.1660 Oh Pembantu tukang listrik Rp. 0.00 = -
0.1660 Oh Tukang listrik Rp. 0.00 = -
0.0330 Oh Kepala tukang listrik Rp. 0.00 = -
0.0166 Oh Mandor Rp. 0.00 = - +
JUMLAH = - -
54 m Memasang Kabel Power Panel Hydrant - Panel Control Diesel
Bahan
1.0000 m KABEL FRC 4X6 Rp. 0.00 = -
0.0000 m Conduit pipa dia. 20 Rp. 0.00 = -
5.0000 % Perlengkapan instalasi Rp. 0.00 = -

Upah An. SNI ( Revisi ) 6.8.2


0.1660 Oh Pembantu tukang listrik Rp. 0.00 = -
0.1660 Oh Tukang listrik Rp. 0.00 = -
0.0330 Oh Kepala tukang listrik Rp. 0.00 = -
0.0166 Oh Mandor Rp. 0.00 = - +
JUMLAH = - -
55 m Memasang Kabel Power PP DW - Pompa Deepwell
Bahan
1.0000 m Kabel NYY 4x4 Rp. 0.00 = -
1.0000 m Kabel NYA 6 mm Rp. 0.00 = -
1.0000 m Kabel NYYHY 4 x 1.5 mm Rp. 0.00 = -
5.0000 % Perlengkapan instalasi Rp. 0.00 = -

Upah An. SNI ( Revisi ) 6.8.2


0.1660 Oh Pembantu tukang listrik Rp. 0.00 = -
0.1660 Oh Tukang listrik Rp. 0.00 = -
0.0330 Oh Kepala tukang listrik Rp. 0.00 = -
0.0166 Oh Mandor Rp. 0.00 = - +
JUMLAH = - -
56 VA Pek. Kwh Meter Baru
Bahan
1.0000 VA Biaya Penyambungan (BP) Rp. 0.00 = -
1.0000 VA Uang Jaminan Langganan (UJL) Rp. 0.00 = -
1.0000 VA Sertifikat Laik Oprasi (SLO) Rp. 0.00 = - +
JUMLAH = - -

57 m³ Pek . Galian tanah


Upah An. SNI ( Revisi ) 6.1.1
0.7500 Oh Pekerja Rp. 0.00 = -
0.0000 Oh Tukang Rp. 0.00 = -
0.0000 Oh Kepala tukang Rp. 0.00 = -
0.0250 Oh Mandor Rp. 0.00 = - +
JUMLAH = - -

58 m³ Pek . Urugan pasir area pipa tertanam


Bahan An. SNI ( Revisi ) 6.11.1
1.2000 m3 Pasir Urug Rp. 0.00 = -

Upah An. SNI ( Revisi ) 6.11.2


0.3000 Oh Pekerja Rp. 0.00 = -
0.0000 Oh Tukang Rp. 0.00 = -
0.0000 Oh Kepala tukang Rp. 0.00 = -
0.0100 Oh Mandor Rp. 0.00 = - +
JUMLAH = - -

59 m2 Pekerjan Pengaspalan dengan sandsheet tebal 3cm


Bahan
0.0300 m3 Pasir Pasang Rp. 0.00 = -
9.3900 kg Aspal Penetrasi 60/70 Rp. 0.00 = -
0.5000 ltr Solar Rp. 0.00 = -
0.0500 jam Peralatan Aspal + sewa baby roller Rp. 0.00 = -

Upah An. SNI ( Revisi ) 6.11.2


0.1000 Oh Pekerja Rp. 0.00 = -
0.2600 Oh Mandor Rp. 0.00 = - +
JUMLAH = - -

60 m³ Pek . Bobok Keramik


Upah An. SNI ( Revisi ) 6.1.1
0.1000 Oh Pekerja Rp. 0.00 = -
0.0000 Oh Tukang Rp. 0.00 = -
0.0000 Oh Kepala tukang Rp. 0.00 = -
0.0100 Oh Mandor Rp. 0.00 = - +
JUMLAH = - -

61 m² Pek. Pemasangan Lantai Keramik uk. 50 x 50 cm


Bahan An. SNI ( Revisi ) 6.47.1
1.0500 m² Keramik 50x50 Cm Rp. 0.00 = -
7.4539 kg Semen Portland Rp. 0.00 = -
3.9261 kg Kapur bubuk Rp. 0.00 = -
0.0420 m³ Pasir Pasang Rp. 0.00 = -
0.2000 kg Semen warna Rp. 0.00 = -

Upah An. SNI ( Revisi ) 6.47.2


0.2200 oh Pekerja Rp. 0.00 = -
0.1000 oh Tukang Batu Rp. 0.00 = -
0.0120 oh Kepala Tukang Rp. 0.00 = -
0.0125 oh Mandor Rp. 0.00 = -
JUMLAH = - -
62 m³ Pek. Pembuatan beton mutu f'c = 7.4 Mpa (k100) slump (3-6) cm w/c = 0.87
Bahan (SNI 7394:2008 6.2)
230.0000 kg Semen Portland Rp. 0.00 = -
893.0000 kg Pasir beton Rp. 0.00 = -
1027.0000 kg Kerikil Rp. 0.00 = -
200.0000 liter Air Rp. 0.00 = -

Upah (SNI 7394:2008 6.2)


1.6500 oh Pekerja Rp. 0.00 = -
0.2750 oh Tukang batu Rp. 0.00 = -
0.0280 oh Kepala tukang Rp. 0.00 = -
0.0830 oh Mandor Rp. 0.00 = - +
JUMLAH = - -
63 m² Pek. Pemasangan bekisting
Bahan An. SNI ( Revisi ) 6.28.1
0.040 m3 Kayu Terentang / Meranti Rp. 0.00 = -
0.3000 kg Paku 8-12cm Rp. 0.00 = -
0.1000 liter Minyak bekisting Rp. 0.00 = -

Upah An. SNI ( Revisi ) 6.28.2


0.3000 oh Pekerja Rp. 0.00 = -
0.2600 oh Tukang kayu Rp. 0.00 = -
0.0260 oh Kepala tukang Rp. 0.00 = -
0.0050 oh Mandor Rp. 0.00 = - +
JUMLAH = - -
64 LS Boring kedalaman 80 m untuk Deep Well
Upah
80.000 m Boring kedalaman 80 m Rp. 0.00 = -
JUMLAH = - -

65 kg WF 150 X 75
Bahan An. SNI ( Revisi ) 6.28.1
1.100 kg Besi WF Rp. 0.00 = -
0.8000 kg Meni Besi Rp. 0.00 = -

Upah An. SNI ( Revisi ) 6.1.2


0.0060 oh Pekerja Rp. 0.00 = -
0.0600 oh Tukang kayu Rp. 0.00 = -
0.0060 oh Kepala tukang Rp. 0.00 = -
0.0003 oh Mandor Rp. 0.00 = - +
JUMLAH = - -

66 m³ Pek . Galian tanah


Upah An. SNI ( Revisi ) 6.1.1
0.7500 Oh Pekerja Rp. 0.00 = -
0.0000 Oh Tukang Rp. 0.00 = -
0.0000 Oh Kepala tukang Rp. 0.00 = -
0.0250 Oh Mandor Rp. 0.00 = - +
JUMLAH = - -
67 kg Pek. Pembesian dengan besi polos atau besi ulir
Bahan (SNI 7394:2008 6.17)
1.0500 kg Besi Beton Polos Rp. 0.00 = -
0.0150 kg Kawat beton Rp. 0.00 = -

Upah (SNI 7394:2008 6.17)


0.0070 oh Pekerja Rp. 0.00 = -
0.0070 oh Tukang besi Rp. 0.00 = -
0.0007 oh Kepala tukang Rp. 0.00 = -
0.0004 oh Mandor Rp. 0.00 = - +
JUMLAH = - -

68 m³ Pek. Pembuatan beton mutu f'c = 26.4 Mpa (k300). slump (12±2) cm .w/c = 0.52
Bahan (SNI 7394:2008 6.10)
413.0000 kg Semen Portland Rp. 0.00 = -
681.0000 kg Pasir Beton (kg) Rp. 0.00 = -
1021.0000 kg Kerikil Rp. 0.00 = -
215.0000 liter Air Rp. 0.00 = -

Upah (SNI 7394:2008 6.10)


1.6500 oh Pekerja Rp. 0.00 = -
0.2750 oh Tukang batu Rp. 0.00 = -
0.0280 oh Kepala tukang Rp. 0.00 = -
0.0830 oh Mandor Rp. 0.00 = - +
JUMLAH = - -
69 kg Pek. Pembesian dengan besi polos atau besi ulir
Bahan (SNI 7394:2008 6.17)
1.0500 kg Besi Beton Polos Rp. 0.00 = -
0.0150 kg Kawat beton Rp. 0.00 = -

Upah (SNI 7394:2008 6.17)


0.0070 oh Pekerja Rp. 0.00 = -
0.0070 oh Tukang besi Rp. 0.00 = -
0.0007 oh Kepala tukang Rp. 0.00 = -
0.0004 oh Mandor Rp. 0.00 = - +
JUMLAH = - -

70 m³ Pek. Pembuatan beton mutu f'c = 26.4 Mpa (k300). slump (12±2) cm .w/c = 0.52
Bahan (SNI 7394:2008 6.10)
413.0000 kg Semen Portland Rp. 0.00 = -
681.0000 kg Pasir Beton (kg) Rp. 0.00 = -
1021.0000 kg Kerikil Rp. 0.00 = -
215.0000 liter Air Rp. 0.00 = -

Upah (SNI 7394:2008 6.10)


1.6500 oh Pekerja Rp. 0.00 = -
0.2750 oh Tukang batu Rp. 0.00 = -
0.0280 oh Kepala tukang Rp. 0.00 = -
0.0830 oh Mandor Rp. 0.00 = - +
JUMLAH = - -
71 m² Pek. Pemasangan bekisting
Bahan An. SNI ( Revisi ) 6.28.1
0.040 m3 Kayu Terentang / Meranti Rp. 0.00 = -
0.3000 kg Paku 8-12cm Rp. 0.00 = -
0.1000 liter Minyak bekisting Rp. 0.00 = -

Upah An. SNI ( Revisi ) 6.28.2


0.3000 oh Pekerja Rp. 0.00 = -
0.2600 oh Tukang kayu Rp. 0.00 = -
0.0260 oh Kepala tukang Rp. 0.00 = -
0.0050 oh Mandor Rp. 0.00 = - +
JUMLAH = - -

72 m² Pek. Integral Waterproofing


Bahan
0.3500 kg Waterproofing Integral (component 2 lt/m3) Rp. 0.00 = -

Upah
0.0500 oh Pekerja Rp. 0.00 = -
0.0700 oh Tukang Cat Rp. 0.00 = -
0.0070 oh Kepala Tukang Rp. 0.00 = -
0.0030 oh Mandor Rp. 0.00 = - +
JUMLAH = - -

73 m² Pek. Pengecatan Eksterior (Cat setara Dulux Pofessional Weathershield Sealer E1000)
Bahan An. SNI ( Revisi ) 6.14.1
0.1000 kg Plamir Rp. 0.00 = -
0.2500 lbr Ampelas Rp. 0.00 = -
0.0200 bh Kuwas / roll Rp. 0.00 = -
0.1000 kg Cat Dasar Eksterior Dulux Professional Weathershield Sealer E1000Rp. 0.00 = -
0.2600 kg Cat Eksterior Dulux Professional Weathershield E1000 Rp. 0.00 = -

Upah An. SNI ( Revisi ) 6.14.2


0.0200 oh Pekerja Rp. 0.00 = -
0.0630 oh Tukang Cat Rp. 0.00 = -
0.0063 oh Kepala Tukang Rp. 0.00 = -
0.0025 oh Mandor Rp. 0.00 = -
. JUMLAH = - -

74 bh Pek. Pemasangan Pintu Besi


Bahan An. SNI ( Revisi ) 6.2.1
1.0000 m² Pintu Besi uk. 1900 x 600 Rp. 0.00 = -
0.8000 kg Meni Besi Rp. 0.00 = -
5.0000 % Perlengkapan instalasi Rp. 0.00 = -

Upah An. SNI ( Revisi ) 6.2.2


0.6500 oh Tukang Besi Rp. 0.00 = -
0.6500 oh Pekerja Rp. 0.00 = -
0.0650 oh Kepala Tukang Rp. 0.00 = -
0.0320 oh Mandor Rp. 0.00 = -
JUMLAH = - -

75 bh Pek. Pemasangan Tangga Besi


Bahan
1.0000 bh Tangga Besi Rp. 0.00 = -
0.8000 kg Meni Besi Rp. 0.00 = -
5.0000 % Perlengkapan instalasi Rp. 0.00 = -

Upah
10.0000 % upah Rp. 0.00 = -
JUMLAH = - -

76 bh Pek. Pembuatan Manhole


Bahan
1.0000 bh Plat Besi plus handle Rp. 0.00 = -
0.8000 kg Meni Besi Rp. 0.00 = -
5.0000 % Perlengkapan instalasi Rp. 0.00 = -

Upah
10.0000 % upah Rp. 0.00 = -
JUMLAH = - -
77 bh Pek. Pemasangan Exhaust Fan Dinding 350 CFM
1.0000 bh Exhaust Fan 350 CFM Rp. 0.00 = -

Upah An. SNI ( Revisi ) 6.35.2


0.1660 oh Pembantu Tukang Listrik Rp. 0.00 = -
0.1660 oh Tukang Listrik Rp. 0.00 = -
0.0330 oh Kepala Tukang Listrik Rp. 0.00 = -
0.0166 oh Mandor Rp. 0.00 = -
JUMLAH = - -

78 titik Pek. Titik Lampu


bahan An. SNI ( Revisi ) 6.1.1
8.0000 m Kabel NYM 3 x 2.5 mm² Rp. 0.00 = -
8.0000 m Conduit pipa dia. 20 Rp. 0.00 = -

Upah An. SNI ( Revisi ) 6.1.2


0.1660 oh Pembantu Tukang Listrik Rp. 0.00 = -
0.1660 oh Tukang Listrik Rp. 0.00 = -
0.0330 oh Kepala Tukang Listrik Rp. 0.00 = -
0.0166 oh Mandor Rp. 0.00 = -
JUMLAH = - -
79 bh Pek. Saklar Tunggal
bahan An. SNI ( Revisi ) 6.21.1
1.0000 bh saklar tunggal Rp. 0.00 = -
5.0000 % Perlengkapan instalasi Rp. 0.00 = -

Upah An. SNI ( Revisi ) 6.21.2


0.1660 oh Pembantu Tukang Listrik Rp. 0.00 = -
0.1660 oh Tukang Listrik Rp. 0.00 = -
0.0330 oh Kepala Tukang Listrik Rp. 0.00 = -
0.0166 oh Mandor Rp. 0.00 = -
JUMLAH = - -
80 bh Pek. Memasang Lampu
bahan An. SNI ( Revisi ) 6.21.1
1.0000 bh lampu setara bn 12c led 20/1200 Rp. 0.00 = -
5.0000 % Perlengkapan instalasi Rp. 0.00 = -

Upah An. SNI ( Revisi ) 6.32.1


0.1660 oh Pembantu Tukang Listrik Rp. 0.00 = -
0.1660 oh Tukang Listrik Rp. 0.00 = -
0.0330 oh Kepala Tukang Listrik Rp. 0.00 = -
0.0166 oh Mandor Rp. 0.00 = -
JUMLAH = - -
81 ls Pek. testing & commissioning berikut kebutuhan lainya
Upah
1.000 ls Testing & commissioning berikut kebutuhan lainya Rp. 0.00 = -
JUMLAH = - -

82 ls Biaya pengurusan izin sampai diterbitkannya surat rekomendasi dari Dinas pemadam Kebakaran
Upah
1.000 LS Biaya pengurusan izin sampai diterbitkannya surat rekomendasi dar Rp. 0.00 = -
JUMLAH = - -

83 ls Pengurusan semua izin-izin termasuk pengeboran dan SIPA untuk pemsangan serta pengoprasian instalasi yang terpasang
Upah
LS Biaya Pengurusan semua izin-izin termasuk pengeboran dan SIPA Rp. 0.00 = -
untuk pemsangan serta pengoprasian instalasi yang terpasang
1.000

JUMLAH = - -
84 ls Pengisian bahan bakar solar untuk pompa diesel setelah testing commisioning (Full Tank)
Upah
1.000 ls Pengisian bahan bakar solar untuk pompa diesel setelah testing Rp. 0.00 = -
commisioning (Full Tank)
JUMLAH = - -

85 m 2
Pembuatan direksi keet
Bahan (RSNI-T-12-2002 6.9.1)
1.2500 btg Dolken kayu galam Ø 8-10 / 4 m Rp. 0.00 = -
0.1860 m3 Kayu Rp. 0.00 = -
0.3000 kg Paku biasa 2" - 5" Rp. 0.00 = -
18.0000 kg Semen Portland Rp. 0.00 = -
0.0300 m3 Pasir beton Rp. 0.00 = -
0.0500 m3 koral beton Rp. 0.00 = -
1.5000 lbr Seng gelombang bwg32 Rp. 0.00 = -
1.5000 lbr Plywood 4mm Rp. 0.00 = -

Upah (RSNI-T-12-2002 6.9.2)


1.0000 oh Pekerja Rp. 0.00 = -
2.0000 oh Tukang kayu Rp. 0.00 = -
0.2000 oh Kepala Tukang Rp. 0.00 = -
0.0500 oh Mandor Rp. 0.00 = - +
JUMLAH = - -

......................................., ... - ... - ......................


PT. .................................................
Jabatan

..........................................................
.......................................
-
-
"Type equation here."
"Type equation here."
DAFTAR HARGA SATUAN

PENGADAAN INSTALASI SYSTEM FIRE HYDRANT STASIUN DAN STABLING KA DI DAOP 9 STA.
JEMBER

NO URAIAN SATUAN HARGA SATUAN


Jasa
Pekerja Oh
Tukang Oh
Kepala tukang Oh
Mandor Oh
Tukang besi Oh
Tukang batu Oh
Tukang kayu Oh
Tukang Cat Oh
Kepala Tukang Listrik Oh
Tukang Listrik Oh
Pembantu Tukang Listrik Oh
Biaya Penyambungan (BP) VA
Uang Jaminan Langganan (UJL) VA
Sertifikat Laik Oprasi (SLO) VA

Bahan
Diesel Fire Pump 500 USGPM bh
Electric Fire Pump 500 USGPM bh
Jockey Fire Pump 10 USGPM bh
Rak Kabel 400x100x300 m
Pressure Switch bh
Pipa BSP sch. 40 ø 200 mm m
Pipa BSP sch. 40 ø 100mm m
Pipa BSP sch. 40 ø 50mm m
Pipa BSP sch. 40 ø 40mm m
Anti Vortex diameter 100 mm bh
Flange dia. 100 mm bh
Anti Vortex diameter 50 mm bh
Flange dia. 50 mm bh
Check Valve diameter 100 mm 10 K bh
Flange dia. 100 mm bh
Check Valve diameter 50 mm 10 K bh
Flange dia. 50 mm bh
Flexible Joint diameter 100 mm 10 K bh
Flange dia. 100 mm bh
Flexible Joint diameter 50 mm 10 K bh
Flange dia. 50 mm bh
Gate Valve diameter 100 mm 10 K bh
Flange dia. 100 mm bh
Gate Valve diameter 80 mm 10 K bh
Flange dia. 80 mm bh
Gate Valve diameter 50 mm 10 K bh
Flange dia. 50 mm bh
Y Strainer diameter 100 mm 10 K bh
Flange dia. 100 mm bh
Y Strainer diameter 50 mm 10 K bh
Flange dia. 50 mm bh
Foot Valve 100 mm bh
Flange dia. 100 mm bh
Foot Valve 50 mm bh
Flange dia. 50 mm bh
Safety Valve diameter 50 mm bh
Pipa BSP sch. 40 ø 100mm bh
Pipa BSP sch. 40 ø 80mm bh
Pipa BSP sch. 40 ø 65mm bh
Pipa BSP sch. 40 ø 40mm bh
Gate Valve diameter 100 mm 10 K bh
Flange dia. 100 mm bh
Check Valve diameter 100 mm 10 K bh
Flange dia. 100 mm bh
PFE 3 Kg type Dry Chemical Powder c/w Box bh
Indoor Hydrant Box bh
Outdoor Hydrant Box bh
Twin Siamesse Connection 100 x 65 x 65 bh
Gate Valve Valve diameter 100 mm bh
Flange dia. 150 mm bh
Twin Siamesse Connection bh
Check Valve Valve diameter 100 mm bh
Gate Valve Valve diameter 100 mm bh
Flange dia s. 100 mm bh
Biaya Pengurusan izin pemasangan Deep Well LS
Pompa Sumersible bh
Pipa Gip Class Bs 1387 150 mm m
Pipa Gip Class Bs 1387 100 mm m
Pipa Gip Class Bs 1387 50 mm m
Check Valve diameter 50 mm 10 K bh
Flange dia. 50 mm bh
Coupling Joint 50 mm bh
Gate Valve diameter 50 mm 10 K bh
Flange dia. 50 mm bh
Presure Gauge bh
Quantity Meter 20 mm 10 k bh
Automatik Air Vent 25 mm bh
MCCB 3P In 320-630 A Bh
MCCB 3P In 40 A Bh
MCB 3P 25 A Bh
MCB 3P 16 A M
MCB 1P 16 A Bh
Pilot Lamp Bh
Fuse 2A set
ampere meter 30/5 set
volt meter 96x96. set
selektor auto man Bh
CT300/5 A Bh
Box Panel 50x70x20 (minimum) Bh
Busbar CU 4x40 Bh
Kabel BC 50 mm Set.
MCCB 3P In 320-630 A Bh
MCCB 3P In 40 A Bh
MCCB 30 A Bh
MCB 3P 16 A M
MCB 1P 16 A Bh
Pilot Lamp Bh
CT300/5 A Bh
ampere meter 30/5 set
volt meter 96x96. set
selektor auto man Bh
Pilot Lamp Bh
Fuse 2A set
Box Panel 50x70x20 (minimum) Bh
Busbar CU 4x40 Bh
Star Delta Starter 7.5 HP Bh
Kabel BC 50 mm Set.
Box Panel 400x400x200 Bh
MCCB 3P In 30-40 A setara ABB, scheneider Bh
Contactor 7.5 KW setara scheneider Bh
Pilot Lamp Bh
selektor auto man Bh
PFR setara GAE set
Fuse 2A Bh
Busbar CU 4x12x2 Bh
Kabel BC 50 mm Set.
KABEL NYY 4X185 m
Conduit pipa dia. 20 m
KABEL FRC 4X185 m
Kabel NYFGBY 4x6 m
Conduit pipa dia. 20 m
KABEL FRC 4X6 m
Kabel NYY 4x4 m
Kabel NYA 6 mm m
Kabel NYYHY 4 x 1.5 mm m
Pasir Urug m3
Pasir Pasang m3
Aspal Penetrasi 60/70 kg
Solar ltr
Peralatan Aspal + sewa baby roller jam
Keramik 50x50 Cm m²
Semen Portland kg
Kapur bubuk kg
Pasir Pasang m³
Semen warna kg
Semen Portland kg
Pasir beton kg
Kerikil kg
Air liter
Kayu Terentang / Meranti m3
Paku 8-12cm kg
Minyak bekisting liter
Boring kedalaman 80 m m
Besi WF kg
Meni Besi kg
Besi Beton Polos kg
Kawat beton kg
Waterproofing Integral (component 2 lt/m3) kg
Plamir kg
Ampelas lbr
Kuwas / roll bh
kg
Cat Dasar Eksterior Dulux Professional
Weathershield Sealer E1000
Cat Eksterior Dulux Professional Weathershield kg
E1000
Pintu Besi uk. 1900 x 600 m²
Meni Besi kg
Tangga Besi kg
Plat Besi plus handle bh
Exhaust Fan 350 CFM bh
Kabel NYM 3 x 2.5 mm² m
Conduit pipa dia. 20 m
saklar tunggal bh
lampu setara bn 12c led 20/1200 bh
LS
Testing & commissioning berikut kebutuhan lainya
Biaya pengurusan izin sampai diterbitkannya surat LS
rekomendasi dari DPK
Biaya Pengurusan semua izin-izin termasuk LS
pengeboran dan SIPA untuk pemsangan serta
pengoprasian instalasi yang terpasang
Pengisian bahan bakar solar untuk pompa diesel LS
setelah testing commisioning (Full Tank)
Dolken kayu galam Ø 8-10 / 4 m btg
Kayu m3
Paku biasa 2" - 5" kg
Semen Portland kg
Pasir beton m3
Pasir Beton (kg) kg
koral beton m3
Seng gelombang bwg32 lbr
Plywood 4mm lbr

......................................., ... - ... - ......................


PT. .................................................