1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
3.1 Grounding 3.2 AC GRID and UPS output connection
1.Front panel 2.Double color LED 3.LCD screen 4.Push button 5.Wall hole
1 2 3
6.Magnetic devices 7.Heat sink 8.PV switch 9.PV connector 10.Grounding screw
11.EPS connector 12.Reserved hole 13.AC grid connector 14.USB port 15.communication ports
16.DIP and Dry connector 17.Batterypower terminal
Pressure Seal Ring Threaded
screw Connection
Note: sleeve
terminal
1. This file will be updated from time to time due to product upgrades or other reasons. Unless otherwise agreed, this document is intended
as a guide only. All information and suggestions do not constitute an express or implied warranty. The final interpretation of the content is at 4 5
Growatt.
2. This document is for quick guidance installation only. For details, please refer to the User Manual.
3. Machine damage caused by failure to follow the content is not covered by the warranty.
2. Installation
1 2 3
System Overiew 2.1 Installation requirements
The following diagram shows the AC
Hybrid Inverter output terminal of the Australian machine
PV Array
connection steps, EPS output terminal
Battery
≥300mm 565 connection steps consistent with the
188
above steps.
138 532
E PS Grid
4 5 6
mm
DC
≥300mm ≥300 ≥300mm
DC
Breaker
AC
Breaker Breaker 461.5
200
588
AC
Breaker Electrical Gri 16.5
AC
Breaker
Sensor
E PS AC
Load Load ≥300mm
3.3 DC connection
2.2 Wall mounting
L line
CT
5m
3.3.1 PV input terminal installation
10m
1 2 3 Positive metal terminal
L,N
5m
L,N
Positive metal terminal
Electic meter
8- 10 mm
Notes:
Note: Be careful : Avoid water
1.The installation of this hybrid system needs and electricity pipes
to comprehensively consider the position of when punching holes in
the battery and the power collector. the wall, otherwise it may
2.You can choose CT or electric meter to be dangerous. Negative metal terminal
connect to the inverter. If there are strict 8-10 mm Please make sure cable can't put out
Negative metal terminal from terminal after pressing. Pull the PV cable make sure there
requirements on the limited output power, it is
is no loosen or shaking.
recommended to use an electric meter.
4 5
Note: Note:
This diagram A is an example for grid system without special This diagram B is an example for Australian and New Zealand
requirement on electrical wiring connection. grid system where neutral line can't be switched.
Note: Note:
CT1/MERTER1 We suggest you choice the AC breaker of specification You must choose a Type A RCD breaker with the rating residual
40A/230V and the DC breaker of specification 25A/780V(PV) or current more than 300mA.
120A/70V(BAT).
4. Post-installation check
5 All switches off 6 All wires are correct and securely connected. Download Growatt New Energy
Manual
7 Cable tie port trimming, no sharp corners, etc. 8 All exposed terminals are well protected, no vacant ports.