Department of Computer Science, CUI Lahore Campus

Assignment = Quiz 2

Name: Section: Course Title: Software Project Management Date:


Reg.#: Instructor: Sana Rizwan Marks: 5 Class/Batch:

Instructions

 DO NOT copy the assignment, marks will be graded on originality of work, zero mark
will be for copied one. Assignment will be checked by Plagiarism software
 Each question has 01 mark
 Submission date is 19th April 2020 (Sunday)
 Submit the assignment using MS Word individually. Image file is not acceptable.
 Submit the assignment before closing date on Microsoft Teams.

Question 1:

Draw the Network Diagram shown activities on arrows (AOA).

Question 2:
Draw the ADN Diagram shown activities on arrows (AOA).

Question 3:
Activity Preceding Activity Normal Time (Days)
1-2 -- 20
1-3 -- 25
2-3 1-2 10
2-4 1-2 12
3-4 1-3 , 2-3 5
4-5 2-4 , 3-4 10

Draw activity network diagram and identify the time allocation.

Question 4:
Activity Optimistic Time Mostly Likely Time Pessimistic Time
A 4 10 16
B 3 6 9
C 4 7 16
D 5 5 5
E 8 11 32
F 4 10 16
G 2 5 8

Calculate Expected Mean Duration, variance and Standard Deviation of each activity.

Question 5:
Activities Predecessors to tm tp
A -- 6 9 12
B A 14 17 20
C A 7 10 13
D A 3 5 9
E -- 4 7 8
F E 9 11 12
G C,F 10 14 16
H F,G 17 20 25
I C 12 15 18
J B 13 18 25

a) Draw the ADN network diagram for Pert.


b) Find the Expected mean duration and variance for each activity

THE END