VO 

for Concrete pipe foundation 

KEGIATAN :  Pembangunan SBM biogas Plant 
Client :  PT. Agro Bukit Central Kalimantan KONTRAKTOR : PT. KIS
Location  :  Pipe Support for Feeding , Recirrculation , Gas Line pipe 

No. Pekerjaan Tambah /VO
Mata Uraian Satuan Penambahan Pengurangan
 Harga Satuan   Remarks 
(Rupiah)   Jumlah Harga 
Kwantitas Kwantitas  Jumlah Harga (Rupiah) 
(Rupiah) 
Pembayaran
a b c g h i = (gxh) j k = (gxj) n
1 Pipe Support Foundation Tipe F ( Qty = 13)
Concrete ,rebar ,formwork etc M3             4.000.000,00                6,05          24.192.000,00                  ‐                                       ‐
Footing size(1.2x1.2)                                ‐                               ‐                  ‐                                       ‐ Used for pipe 
overflow Dia 
Column size(0.30x0.30)                                ‐                               ‐                  ‐                                       ‐ 315 mm
P.C.C 100mm thk. M3             1.250.000,00                2,74             3.430.000,00
Earthwork M3 45.000,00                2,35                105.840,00                  ‐                                       ‐
Sandfilling M3                 400.000,00                1,61                644.000,00                                       ‐

2 Pipe Support Foundation Tipe K ( Qty = 140)
Concrete ,rebar ,formwork etc M3             4.000.000,00              11,20          44.800.000,00                  ‐                                       ‐
Footing size(0,5x 0,4x 0,4)                                ‐                  ‐                               ‐                  ‐                                       ‐ Used for Gas 
P.C.C 100mm thk. M3             1.250.000,00              11,20          14.000.000,00 pipe line , 
feeding & 
Earthwork M3 45.000,00                2,80                126.000,00                  ‐                                       ‐ recirrculation 
Sandfilling M3                 400.000,00                5,60             2.240.000,00                                       ‐ pipe line 

(A) Jumlah Harga Pekerjaan       89.537.840,00                                       ‐

(D) Pembulatan

Approved By 
Calculated by  Checked by 

Yan Sinulingga 
PM  CM …....................