for Concrete pipe foundation
KEGIATAN : Pembangunan SBM biogas Plant
Client : PT. Agro Bukit Central Kalimantan KONTRAKTOR : PT. KIS
Location : Pipe Support for Feeding , Recirrculation , Gas Line pipe
No. Pekerjaan Tambah /VO
Mata Uraian Satuan Penambahan Pengurangan
Harga Satuan Remarks
(Rupiah) Jumlah Harga
Kwantitas Kwantitas Jumlah Harga (Rupiah)
(Rupiah)
Pembayaran
a b c g h i = (gxh) j k = (gxj) n
1 Pipe Support Foundation Tipe F ( Qty = 13)
Concrete ,rebar ,formwork etc M3 4.000.000,00 6,05 24.192.000,00 ‐ ‐
Footing size(1.2x1.2) ‐ ‐ ‐ ‐ Used for pipe
overflow Dia
Column size(0.30x0.30) ‐ ‐ ‐ ‐ 315 mm
P.C.C 100mm thk. M3 1.250.000,00 2,74 3.430.000,00
Earthwork M3 45.000,00 2,35 105.840,00 ‐ ‐
Sandfilling M3 400.000,00 1,61 644.000,00 ‐
2 Pipe Support Foundation Tipe K ( Qty = 140)
Concrete ,rebar ,formwork etc M3 4.000.000,00 11,20 44.800.000,00 ‐ ‐
Footing size(0,5x 0,4x 0,4) ‐ ‐ ‐ ‐ ‐ Used for Gas
P.C.C 100mm thk. M3 1.250.000,00 11,20 14.000.000,00 pipe line ,
feeding &
Earthwork M3 45.000,00 2,80 126.000,00 ‐ ‐ recirrculation
Sandfilling M3 400.000,00 5,60 2.240.000,00 ‐ pipe line
(D) Pembulatan
Approved By
Calculated by Checked by
Yan Sinulingga
PM CM …....................
Illustration Drawing & Reference drawing 354/KIS/ZPHB/SBM/ME/PRL/015