Professional Documents
Culture Documents
Lecture 5
Lecture 5
Evaluation
[MPM6133]
Lecture 4
4 November 2021
Cost-Time Trade-Offs and Project Crashing
3
Cost-Time Trade-Offs and Project Crashing
5
Example
Suppose the plant manager at Milwaukee Paper Manufacturing has been given
only 13 weeks (instead of 16 weeks) to install the new pollution control
equipment. As you recall, the length of critical path was 15 weeks, but she must
now complete the project in 13 weeks.
6
Example
7
Crashing Project Steps
8
Example
9
Crashing Project Steps
10
Example
11
Example
12
Example
✓ A–C–E–G–H
✓ B–D–G–H
13
Example
14