FBS02 WORK PROGRAM

MIGRATION FOR CS2.6 - CS3.5A SIPPYTL 19-Aug-21 20-Sep-21


PROJECT NAME CLIENT NAME START DATE END DATE

24/08/2021

25/08/2021
26/08/2021

27/08/2021
28/08/2021
29/08/2021

30/08/2021
31/08/2021

01/09/2021
02/09/2021
03/09/2021

04/09/2021
05/09/2021

06/09/2021
07/09/2021
08/09/2021
09/09/2021

10/09/2021
11/09/2021
12/09/2021
13/09/2021
14/09/2021

15/09/2021
16/09/2021
17/09/2021
18/09/2021
19/09/2021

20/09/2021
21/09/2021
22/09/2021
23/09/2021
24/09/2021

25/09/2021
26/09/2021
27/09/2021
28/09/2021
29/09/2021
Task Duration
Task Name Start Date End Date
ID (In Days)

T01 Loc. 1 - CH654.100 - CH659.200


T03 2nd Round Tamping 24-Aug-21 26-Aug-21 3 1 1 1
T04 3rd Round Tamping/Final Level 27-Aug-21 1-Sep-21 3 1 1 1
T05 Dynamic Track Stabilising 7-Sep-21 8-Sep-21 2 1 1
T06 Correction Tamping 9-Sep-21 10-Sep-21 3 1 1
T07 Loc.2 - CH646.600 - CH647.600 (PL10)
T08 Final Tamping & Correction 2-Sep-21 3-Sep-21 2 1 1
T09 Loc. 3 - CH659.200 - CH660.200
T10 Initial Tamping 4-Sep-21 4-Sep-21 1 1
T11 2nd Round Tamping 6-Sep-21 6-Sep-21 1 1
T12 3rd Round Tamping/Final Level 7-Sep-21 7-Sep-21 1 1
T13 Dynamic Track Stabilising 7-Sep-21 7-Sep-21 1 1
T14 Correction Tamping 20-Sep-21 20-Sep-21 1 1
T15 Loc. 4 - CH652.750 - CH654.100
T16 Initial Tamping 13-Sep-21 13-Sep-21 1 1
T17 2nd Round Tamping 14-Sep-21 14-Sep-21 1 1
T18 3rd Round Tamping/Final Level 15-Sep-21 15-Sep-21 1 1
T19 Dynamic Track Stabilising 16-Sep-21 16-Sep-21 1 1
T20 Correction Tamping 17-Sep-21 17-Sep-21 1 1
Remarks:
This program subject to site amendment base on requirements: such as Saturday working and extra hours works to achieve a production target.