FULL WIDTH OVERHEAD GANTRY

Nos Length Width Height Qty Rate Amount


1 EXCAVATION IN SOIL (STRUCTURE) Cum 2 2.5 3.7 2.1 38.85 ₹ 88.60 3,442.21
2 SIGN BOARD (6 M X 1.5 M) SQM 1 6 1.5 9.00 ₹ 6,500.00 58,500.00
3 STRUCTURAL STEEL - -
4 STRUCTURAL STEEL-PLATES/ANGLE-10% extra for Achor M.T 1 388.575 0.39 ₹ 66,350.00 25,781.95
5 STRUCTURAL STEEL FABRICATION & ERECTION(pipe) M.T 1 40.628 -
5.9mm thk pipe M.T 1 16.5 39.72 kg/Rm 0.66 ₹ 44,000.00 28,838.38
6.3mm thk pipe M.T 1 24.128 50.18 kg/Rm 1.21 ₹ 44,000.00 53,276.61
5.4mm thk pipe M.T 2 0.15 15.18 kg/Rm 0.00 ₹ 44,000.00 200.40
6 15-20% extra for fastener M.T 1 20% - ₹ 44,000.00 -
7 M-15 CONCRETE CUM 2 2.5 3.7 0.1 1.85 ₹ 4,653.37 8,608.73
8 M-25 CONCRETE CUM 10.75 ₹ 6,192.38 66,568.04
2 2.3 3.5 0.5 8.05 -
2 0.6 1.5 1.5 2.70 -
9 HYSD steel for foundation MT 1 80.00kg/cum 10.75 0.86 ₹ 62,628.37 53,860.40
299,076.70