BLDG PLAN APPROVAL High Rise Buildings
BLDG PLAN APPROVAL High Rise Buildings
Application:
Submission:
If the Industrial building /IT building proposed is falling in the Industrial Local
Authority Area( IALA) then submit the application with the following check list
given below.
1. Site Plan to the scale of 1:200 duly showing setbacks, Tot-lot area,
Parking area and internal circulation pattern, Building
Plans/Section/Elevation/Utilities Plan/Rain Water Harvesting Plan etc., to
the scale of 1:100 as per the G.O.Ms.No168MA dt 07.04.2012 (Original
+5Prints) by licensed architect. All these documents duly signed by
licensed architect, signed by the owner/proprietor/developer.
2. Please down load the Land use map from the website of HMDA,
www.hmda.gov.in if the plot is not approved layout.
3. please show in the Google Map showing the site proposed for industry, if
the plot is not in the approved layout.
6. If the total built up area is more than 20000 Sq.mtrs or if the site area is
more than 50 Hectares Environment Clearance from State Environment
Impact Assessment Authority (SEIAA).
7. If the site is uneven terrain then Contour plan in regular intervals certified
by a licensed Engineer along with AMSL certificate obtained from the
reputed surveyor.
V. Location Specific:
a) If the site is located within 200 mts from the boundary of a water body(as
per master plan ) NOC issued by the Irrigation Department not below rank
of Executive Engineer and NOC from concerned revenue authority not
below the rank of Joint Collector showing the site under reference and
distance from the FTL boundary.
b) If the site is located within the vicinity of Oil/Gas pipeline NOC from the
competent authority.
c) If the site is located within 500 mtrs distance from the boundary of
Defense Area/Military Airport NOC from Defense Authority.
d) If the part of the site is falling within 30 mtrs from the Railway boundary
same shall be shown as green belt /openspace.
e) If the site is falling within 100 mtrs distance from Heritage Sites, NOC
from Heritage Conservation Committee.
3. Scrutiny:
On receipt of the application in full shape the detail scrutiny shall be carried
out and demand notice will be issued within 10(Ten) days.
5. Validity :
The permission is valid for 5 years in case of High Rise Buildings & Group
Development Schemes subject to condition that the construction shall be
commenced within 18 months. The permission can be revalidated for another
2 years on payment of building permit fee.
9. Copy of the previous approval building plan and upto date property tax
receipt.
11. NOC from the competent authority if the site is located within the vicinity
of Oil/Gas pipeline.
12. NOC from Defense Authority if the site is located within 500 mtrs distance
from the boundary of Defense Area/Military Airport.
13.If the part of the site is falling within 30 mtrs from the Railway boundary
same shall be shown as green belt /openspace.
14.NOC from Heritage Conservation Committee if the site is falling within 100
mtrs distance from Heritage Sites,.