Engineering cost Estimation for Construction of Under Ground Cable

ITEM DESCRIPTION UNIT QTY Unit price TOTAL PRICE


1.EARTH WORKS

1.1 Clear of the site to remove top soil to an average depth of 200mm m2 7,564.00 125.00 945,500.00
1.2 Trench excavation to a depth of 1500mm
a) Soft soil inrespective of depth plus tranch excavation for retaining m3 7,989.00 456.00 3,642,984.00
wall 3
b) Intermediate soil inrespective of depth m 3,750.00 570.00 2,137,500.00
1.4 Back fill with excavated material to a required level with non expansive
excavated material and well compacted in layer of 200mm thick m3 3,191.55 826.54 2,637,935.76
including for retaining wall
1.5 Cart away excavated surplus material to the area approved by engineer (
minimum distance not less than 5km) away from the site, spread and m3 7,091.25 287.06 2,035,598.71
level it as the site requires.
1.6 250 mm thick basaltic or equivalent stone hard core well rolled and
consolidated and blinded with crushed stone.(optional or as approved by m2 4,104.00 482.63 1,980,693.00
engineer around Swamp area)
Total to summary Birr 13,380,211.47
2.CONCRETE WORK
2.1 Lean Conete
a 50mm thick lean concrete in C-5 with minimum cement content of
m2 5,673.00 4,250.00 24,110,250.00
150kg/m3
2.2 Structural Concrete
Reinforced concrete in class C-25/30, with minimum cement content of
400 kgs/m3 filled into formwork and vibrated around steel reinforcement
and formwork shall be measured separately:
a In cable duct, cover and road crossing at T junction m3 1,930.13 9,263.23 17,879,228.04
2.3 Provide cut and fix in position swan zigba wood formwork to:
a For cable duct including cover as well road crossing at T junction with
m2 16,784.80 612.00 10,272,297.60
its cover
2.4 Steel reinforcement according to structural drawing, price shall include
cutting ,bending, placing in position and tying wire.
a Ø 8 mm deformed kg 58,607.91 174.98 10,255,211.70
b Ø 10 mm deformed kg 47,508.91 174.98 8,313,109.71
c Ø 12 mm deformed kg 6,622.09 174.98 1,158,733.53
Total to summary Birr 71,988,830.57
3.MASONRY WORK
3.1 Construction of Masonry wall with cement sand mortal of 1:4 ratio
m3 1,456.20 6,580.00 9,581,796.00
where the depth of backfill is greater than depth of cable duct as per
indicated on the drawings Total to summary Birr 9,581,796.00
Grand Summary 94,950,838.04