RAS AL HADD DEVELOPMENT PROJECT – OMAN

Al Jaber Engineering Company, LLC


QDRH22302: Construction of 200 Keys 5* Luxury Hotel, 50 Keys Chedi
Villas, Luxury Spa, Beach Club & Associated Infrastructure Work

AssAssociated Infrastructure Works


Interim Cost Claims for Additional Cost Incurred by the Contractor due to COVID19
Pandemic and its Consequences where the Employer not taken Sufficient measures or
Participated in such events to support the Contractor

SR.NO INDEX Pages


1 Narrative for the Cost Claims ( Annexure – 01 ) 21
Correspondence as Referred in the Narrative Attached
2 The Flow Chart for Additional cost Incurred by the contractor due to 1
delay & cash shortage ( Annexure - 02 )
3 Summary for Cost Claims ( Annexure – 03 ) 4
4 Supporting Documents
A Claims by subcontractors related to subject claim
1.1 Additional prelims to Adhi Oman ( Appendix – 01 ) File 1
1.2 Additional amounts to be paid to Adhi Oman for Material File 1
( Appendix – 01 )
1.3 Adhi Oman Claims for prolongation Cost ( Appendix – 02 ) File 1
2 Additional Amounts paid in Al- Rawdha Settlement & Legal Fees File 1
( Appendix – 03 )
3.1 MEP Works – Additional Prelims to be paid to OSCO File 2
( Appendix – 04 )
3.2 MEP works – Additional amount to be Paid to OSCO for Materials File 2
( Appendix – 04 )
B1 Additional Cost to Contractor’s works to change in Price of
Subcontractors
1 Difference between Adhi Oman & AL -Rawdha rates File 1
( Appendix – 05 )
13 Kitchen, Laundry & waste Management Equipment ( INOX) – File 3
Subcontractor variation ( Appendix – 17 )
RAS AL HADD DEVELOPMENT PROJECT – OMAN
Al Jaber Engineering Company, LLC
QDRH22302: Construction of 200 Keys 5* Luxury Hotel, 50 Keys Chedi
Villas, Luxury Spa, Beach Club & Associated Infrastructure Work

AssAssociated Infrastructure Works


Interim Cost Claims for Additional Cost Incurred by the Contractor due to COVID19
Pandemic and its Consequences where the Employer not taken Sufficient measures or
Participated in such events to support the Contractor

SR.NO INDEX Pages


1 Narrative for the Cost Claims ( Annexure – 01 ) 22
Correspondence as Refer in the Narrative ( Enclose Quantum )
2 The Flow Chart for Additional cost Incurred by the contractor due to 1
delay & cash shortage since ( Annexure - 02 )
3 Summary for Cost Claims ( Annexure – 03 ) 4
4 Supporting Documents
A Claims by subcontractors related to subject claim
1.1 Additional prelims to Adhi Oman ( Appendix – 01 ) File 1
1.2 Additional amounts to be paid to Adhi Oman for Material File 1
( Appendix – 01 )
1.3 Adhi Oman Claims for prolongation Cost ( Appendix – 02 ) File 1
2 Additional Amounts paid in Al- Rawdha Settlement & Legal Fees File 1
( Appendix – 03 )
3.1 MEP Works – Additional Prelims to be paid to OSCO File 2
( Appendix – 04 )
3.2 MEP works – Additional amount to be Paid to OSCO for Materials File 2
( Appendix – 04 )
B1 Additional Cost to Contractor’s works to change in Price of
Subcontractors
1 Difference between Adhi Oman & AL -Rawdha rates File 1
( Appendix – 05 )
13 Kitchen, Laundry & waste Management Equipment ( INOX) – File 3
Subcontractor variation ( Appendix – 17 )
RAS AL HADD DEVELOPMENT PROJECT – OMAN
Al Jaber Engineering Company, LLC
QDRH22302: Construction of 200 Keys 5* Luxury Hotel, 50 Keys Chedi
Villas, Luxury Spa, Beach Club & Associated Infrastructure Work

AssAssociated Infrastructure Works


Interim Cost Claims for Additional Cost Incurred by the Contractor due to COVID19
Pandemic and its Consequences where the Employer not taken Sufficient measures or
Participated in such events to support the Contractor

SR.NO INDEX Pages


1 Narrative for the Cost Claims ( Annexure – 01 ) 22
Correspondence as Refer in the Narrative ( Enclose Quantum )
2 The Flow Chart for Additional cost Incurred by the contractor due to 1
delay & cash shortage since ( Annexure - 02 )
3 Summary for Cost Claims ( Annexure – 03 ) 4
4 Supporting Documents
A Claims by subcontractors related to subject claim
1.1 Additional prelims to Adhi Oman ( Appendix – 01 ) File 1
1.2 Additional amounts to be paid to Adhi Oman for Material File 1
( Appendix – 01 )
1.3 Adhi Oman Claims for prolongation Cost ( Appendix – 02 ) File 1
2 Additional Amounts paid in Al- Rawdha Settlement & Legal Fees File 1
( Appendix – 03 )
3.1 MEP Works – Additional Prelims to be paid to OSCO File 2
( Appendix – 04 )
3.2 MEP works – Additional amount to be Paid to OSCO for Materials File 2
( Appendix – 04 )
B1 Additional Cost to Contractor’s works to change in Price of
Subcontractors
1 Difference between Adhi Oman & AL -Rawdha rates File 1
( Appendix – 05 )
13 Kitchen, Laundry & waste Management Equipment ( INOX) – File 3
Subcontractor variation ( Appendix – 17 )