Professional Documents
Culture Documents
Respondent 1
Respondent 1
Issue 1: Whether setting aside the arbitration award under Section 34 is valid?
The setting aside of the arbitration under Section 34 is valid by the reasoning that the arbitrator is
a direct party to the main contract and the Arbitration Agreement is valid.
Clause 12.1 of the Settlement of Dispute Clause clearly states that upon any kind of disputes or
differences arising out of or in connection with the contract, whether during the progress of work
or after its completion, and whether before or after determination of the contract shall be referred
by the Claimant to the “Chief Engineer” through ‘Notice of Dispute’. Through this the parties
shall try to achieve an amicable solution to the dispute.
Clause 12.2 of the Settlement of Dispute Clause on the other hand states that in the event of any
dispute or difference between the parties hereto as to the construction or operation of this
contract, or the respective rights and liabilities of the parties on any matter in question, shall
demand in writing by means of Notice of Arbitration.
Upon examining Settlement of Dispute Clauses 12.1 and 12.2, it is evident that the arbitration
agreement in the instant case shows on it that the authors have expressed alternative intentions
upon the arising of a dispute, without deciding in favor of either[1].
Ambiguity is therefore patent and Clauses 12.1 and 12.2 of the Contract must be held to be void
for uncertainty, unless the ambiguity can be cured by election. However, in the instant case, it is
not curable by election where there is nothing to indicate who is to have the option.
In the counsel’s judgment, the arbitration agreement is void for uncertainty.
Therefore, on the grounds of the contentions made above, the settlement of the award under
Section 34(ii) as the Arbitration Agreement is valid in the instant case.
The competence of the arbitrator in the instant case can be challenged on the grounds that he is a
direct party to the main contract.
The genesis of this lies in the principle of equal treatment of parties, which is one of the core
principles of justice deliverance.
The landmark judgment of the French Cour De Cassation in Societes BKMI & Siemens v.
Societe Dutco (hereinafter “DUTCO”) has clarified and strengthened its applicability to
arbitrations.
Perkins Eastman Architects DPC v. HSCC (India) Ltd.[2] The Court relied upon the observations
in DUTCO case that, an independent mind is indispensable in the exercise of judicial power,
whatever the source of that power may be, and it is one of the essential qualities of an arbitrator.
Clause 12.4 of The Settlement of Dispute states that the parties may waive off the applicability
of Section 12(5) of The Arbitration and Conciliation Act, 1996 (which deals with the
ineligibilities of an arbitrator), if they agree for such waiver in writing, after dispute have arisen
between them, in the format given under Annexure XV of these conditions.
In the instant case, no such agreement agreeing for such waiver of the applicability of the act has
been signed by both the parties indicating the significance of the applicability of the act in the
appointment of the arbitrator.
The arbitrator being a direct party to the main contract and a vicariously interested party in the
completion of the main contract violates Section 12(5) read along with the Seventh Schedule of
The Arbitration and Conciliation Act, 1996, ultimately making the appointment of the arbitrator
invalid.
The counsel further takes precedence from the case of Bharat Broadband Network Ltd. v. United
Telecoms Ltd[3], where the said procedure of appointment was challenged on the ground of
violation of Section of the amended Arbitration Act in 2015, read with Seventh Schedule thereto.
The Supreme Court in this case held that under the new provision of Section what is clear is that
where under any agreement between the parties, a person falls within any of the categories set
out in the Seventh Schedule, he is, as a matter of law, ineligible to be appointed as an arbitrator.
In such a scenario, the party can straightaway apply under Section for declaration of the same
and for a declaration that the mandate of the arbitrator stands terminated under Section of the Act
itself.
Furthermore, the respondent in the instant case has violated the Settlement of Dispute Clause
(12.1 and 12.5) by not referring the dispute between SPL and Moonlit to either the Chief
Engineer as mentioned in clause 12.1 or sending a Notice of Arbitration as under clause 12.2 but
rather imposing an arbitrary fine on the petitioner, Moonlit.
To establish a breach, it has to be adjudicated upon, and not merely decided by the parties[4].
Hence, imposing the penalty without any scope of amicable solution is violative of Settlement of
Dispute Clause.
The dispute between the two parties arose once Moonlit refused to further continue the work
until the full payment was done by SPL. At this point in the case, SPL must have either invoked
clause 12.1 or 12.2 with the intention of amicably solving the dispute.
But failing to do so, indicates that the condition precedents to seeking arbitration have not been
fulfilled and hence, the appointment of the arbitrator stemming out of such an arbitration can be
rejected as held in the case of Dharmdas Tirthdas Construction Pvt Ltd v. Government of India,
where the High Court of Madhya Pradesh held that if the conditions precedent to seeking
arbitration have not been complied with, then the appointment of the arbitrator can be rejected.
The contentions above establish the invalidity of the appointment of arbitrator in the instant case.
In the instant case, the award given by the arbitrator is invalid under the grounds that,
o The primary violation of obligation arising from the contract is on accord to SPL, when
the payment was not made to moonlit.
o The award stands in violation of the public policy of Isepor.
o The ineligibility of the arbitrator for the reasons of him being a vicariously interested
party in the completion of the main contract.
//
In Steel Authority of India Ltd. v. Primetals Technologies (2020), the award was partially set
aside as being against public policy because an extraordinarily high-interest rate of 14 percent
per annum was given without any justification in comparison to current interest rates.
Furthermore, the high interest rate looked to be punitive in character given the circumstances. As
a result, the interest rate was cut to 10% per year.
The Court concluded in Oil & Natural Gas Corporation Ltd. v. SAW Pipes Ltd., 2003, that in the
instance of an application under Section 34 to set aside an award, the Court’s position was seen
to be that of an appellate/revision court, giving it broad powers. Furthermore, it was mentioned
that the term “public policy” refers to something that concerns the public benefit and interest.
However, the award cannot be argued to be in the public interest because it is patently in breach
of legislative prohibitions. The administration of justice is likely to be harmed by such an award
or decision.
In Mohan Steels Ltd. v. Steel Authority of India (SAIL), (2017), the court set aside the arbitral
award because the Arbitrator construed the contract based on circumstances unrelated to contract
terms by relying on Regulator’s notifications, which were first brought on record after the
parties’ closing arguments. Even while it was clearly denied in its statement of claims, this was
done without giving the petitioner a chance to refute its application to the case.
In the case of Project Director, National Highway Authority of India v. M. Hakeem & Anr. ,
(2021), a division bench comprising Justice R.F. Nariman and Justice B.R. Gavai of the Supreme
Court of India decided in favor of minimum judicial intervention, declaring that courts cannot
amend, revise, or alter an arbitral judgment under Section 34 of the Arbitration Act. However,
under Article 142 of the Constitution of India, the Court has allowed awards to be modified in
the interest of comprehensive justice which clearly states that the court hasn’t retreated in
altering the award but is giving respect to Section 34 by representing minimum judicial
involvement.
//
//
Voestalpine Schienen GmbH v. Delhi Metro Rail Corpn. Ltd- The Supreme Court considered the
amendments made in the 2015 Act, as well as the recommendations of the Law Commission on
the subject of “Neutrality of Arbitrators”. At paras 15 to 23 of the judgment, the Supreme Court
discussed in detail, the principles regarding independence and impartiality of the arbitrators, and
it held that: (SCC pp. 687-88, para 20)
3. 20. Independence and impartiality of the arbitrator are the hallmarks of any arbitration
proceedings. Rule against bias is one of the fundamental principles of natural justice
which applied to all judicial and quasi-judicial proceedings. It is for this reason that
notwithstanding the fact that relationship between the parties to the arbitration and the
arbitrators themselves are contractual in nature, and the source of an arbitrator’s
appointment is deduced from the agreement entered between the parties, notwithstanding
the same non-independence and non-impartiality of such arbitrator (though contractually
agreed upon) would render him ineligible to conduct the arbitration. The genesis behind
this rationale is that even when an arbitrator is appointed in terms of contract and by the
parties to the contract, he is independent of the parties. Functions and duties require him
to rise above the partisan interests of the parties and not to act in, or so as to further, the
particular interest of either party. After all, the arbitrator has adjudicatory role to perform
and, therefore, he must be independent of parties as well as impartial.
Central Organisation for Railway Electrification v. ECI-SPIC-SMO-MCML (JV)
(Central Organisation for Railway Electrification case7, SCC pp. 731-32
[1]
Arbn. Seth Kerorimal Adwani vs Union of India (Uoi), AIR 1959 Cal 430
[2]
(2020) 20 SCC 760 : 2019 SCC OnLine SC 1517
[3]
. (2019) 5 SCC 755
P Radhakrishna Murthy v. NBCC Ltd. (2013) 3 SCC 747; J.G. Engineers (P) Ltd., v. Union of
[4]