Milestone Task Timeline Note

Collection of Dataset of Asphalt images need from client


Image Preprocessing preparing raw images from dataset 2
training images processing to reduce time computation 2 step useful to reduce time at end of patching
finding small grids on image 2
Patch Division images segmentation for any other object 3 need only if image consist other elements except pavement
resize the patch image & variable patching 2
find patches for crack & non-crack images 2
will going to try Global and Lower Quartile Average Intensity 5
trial of different threshold values and find optimal thresholding
Patch Thresholding 2
value
Setup
solving over-segmentation problem 3
labelling process based on GLQAI 2
generating json as per requirements 2
manual visual examinations and labelling on testing images 2 will going to select small set of complex images
Evaluation of results comparison of manual result and proposed method result 2
quantitative evaluation result 2
create functionalities of select and load the image 2
Creation of GUI this includes automatically create patches and perform
GUI back processing code 4
MATLAB or PyQT thresholding using proposed method
result of back processing 2 this will assign the labels to all patches and solves the labels
Testing Test the pipeline for proper error handling 2
Speedup and evaluate analysis of working model for expected output as per
3
final model requirements
Checking the model include all constraints 2
E2E Delivery
End-to-end testing on the whole AI module 2
50