NEW YORKER TP 13-Dec-21 16:41

Activity ID Activity Name Original Duration Start Finish January 2022 February 2022 March 2022 April 2022
26 02 09 16 23 30 06 13 20 27 06 13 20 27 03 10 17 24
66 27-Dec-21 28-Mar-22 28-Mar-22, NY-TABUK PARK NEW YORKER TP
NY-TABUK PARK NEW YORKER TP
10 27-Dec-21 07-Jan-22 07-Jan-22, NY-TABUK PARK.1 PROJECT INITIATION
NY-TABUK PARK.1 PROJECT INITIATION
999 Intiation Phase Start 0 27-Dec-21 Intiation Phase Start, 27-Dec-21
A1000 Site Mobilization 4 27-Dec-21 30-Dec-21 Site Mobilization
A1010 ARCH Drawings Submittals & Approvals 5 27-Dec-21 31-Dec-21 ARCH Drawings Submittals & Approvals
A1011 ARCH Drawings Flooring Submittal &Approval 5 27-Dec-21 31-Dec-21 ARCH Drawings Flooring Submittal &Approval
A1012 ARCH Drawings Ceiling Submittal &Approval 5 27-Dec-21 31-Dec-21 ARCH Drawings Ceiling Submittal &Approval
A1013 ACRH Drawings Walls Submittal & Approval 5 27-Dec-21 31-Dec-21 ACRH Drawings Walls Submittal & Approval
A1014 ARCH Drawings Facades Submittal & Approval 5 27-Dec-21 31-Dec-21 ARCH Drawings Facades Submittal & Approval
A1020 ELEC Power Drawings Submittal & Approval 5 03-Jan-22 07-Jan-22 ELEC Power Drawings Submittal & Approval
A1030 ELEC FA Drawings Submittal & Approval 5 03-Jan-22 07-Jan-22 ELEC FA Drawings Submittal & Approval
A1040 ELEC CCTV Drawings Submttals & Approval 5 03-Jan-22 07-Jan-22 ELEC CCTV Drawings Submttals & Approval
A1050 ELEC PA Drawings Submittal & Approvals 5 03-Jan-22 07-Jan-22 ELEC PA Drawings Submittal & Approvals
A1060 ELEC DATA Drawings & Approvals 5 03-Jan-22 07-Jan-22 ELEC DATA Drawings & Approvals
A1070 ELEC Lighting Drawings Submittal & Approvals 5 03-Jan-22 07-Jan-22 ELEC Lighting Drawings Submittal & Approvals
A1080 MECH HVAC Submittal & Approvals 5 03-Jan-22 07-Jan-22 MECH HVAC Submittal & Approvals
A1090 MECH FF Drawings Submittal & Approvls 5 03-Jan-22 07-Jan-22 MECH FF Drawings Submittal & Approvls
A1100 MECH HVAC DRAIN Drawings Submittal & Approval 5 03-Jan-22 07-Jan-22 MECH HVAC DRAIN Drawings Submittal & Approval
A1105 Intiation Phase Finish 0 07-Jan-22 Intiation Phase Finish,
48 10-Jan-22 16-Mar-22 16-Mar-22, NY-TABUK PARK.2 EXCUTION PHASE
NY-TABUK PARK.2 EXCUTION PHASE
A1107 Execution Phase Start 0 10-Jan-22 Execution Phase Start, 10-Jan-22
A1110 ARCH Material Purchasing 10 10-Jan-22 21-Jan-22 ARCH Material Purchasing
A1120 ELEC Material Purchasing 10 10-Jan-22 21-Jan-22 ELEC Material Purchasing
A1130 MECH Material Purchasing 10 10-Jan-22 21-Jan-22 MECH Material Purchasing
NY-TABUK PARK.2.1 ARCH WORK PACKAGES 26 09-Feb-22 16-Mar-22 16-Mar-22, NY-TABUK PARK.2.1 ARCH WORK PACKAGES
A1140 Install Gypsum Ceiling 7 09-Feb-22 17-Feb-22 Install Gypsum Ceiling
A1150 Install Metal Ceiling 7 09-Feb-22 17-Feb-22 Install Metal Ceiling
A1160 Install Porcelain Tile Flooring 12 18-Feb-22 07-Mar-22 Install Porcelain Tile Flooring
A1170 Supply & Install Shutter door 5 08-Mar-22 14-Mar-22 Supply & Install Shutter door
A1180 Supply & Install Glass for facade 7 08-Mar-22 16-Mar-22 Supply & Install Glass for facade
NY-TABUK PARK.2.2 ELEC WORK PACKAGES 29 24-Jan-22 03-Mar-22 03-Mar-22, NY-TABUK PARK.2.2 ELEC WORK PACKAGES
A1190 Power First Fix 4 24-Jan-22 27-Jan-22 Power First Fix
A1200 Power Second Fix 8 28-Jan-22 08-Feb-22 Power Second Fix
A1210 Power Third Fix 10 18-Feb-22 03-Mar-22 Power Third Fix
A1220 Lighting First Fix 4 24-Jan-22 27-Jan-22 Lighting First Fix
A1230 Lighting Second Fix 8 28-Jan-22 08-Feb-22 Lighting Second Fix
A1240 Lighting Third Fix 10 18-Feb-22 03-Mar-22 Lighting Third Fix
A1250 Low Current First Fix 4 24-Jan-22 27-Jan-22 Low Current First Fix
A1260 Low Current Second Fix 8 28-Jan-22 08-Feb-22 Low Current Second Fix
A1270 Low Current Third Fix 10 18-Feb-22 03-Mar-22 Low Current Third Fix
NY-TABUK PARK.2.3 MECHANICAL WORK PACKAGES 38 24-Jan-22 16-Mar-22 16-Mar-22, NY-TABUK PARK.2.3 MECHANICAL WORK PACKAGES
A1280 AC Ducting Fabrication 7 24-Jan-22 01-Feb-22 AC Ducting Fabrication
A1290 AC Ducting Installation 5 02-Feb-22 08-Feb-22 AC Ducting Installation
A1300 AC Units Supply & install 5 09-Feb-22 15-Feb-22 AC Units Supply & install
A1305 Execution Phase Finish 0 16-Mar-22 Execution Phase Finish,
8 17-Mar-22 28-Mar-22 28-Mar-22, NY-TABUK PARK.4 CLOSURE PHASE
NY-TABUK PARK.4 CLOSURE PHASE
A1310 AS BUILT Drawings Submittal 5 17-Mar-22 23-Mar-22 AS BUILT Drawings Submittal
A1320 Site Handover 3 24-Mar-22 28-Mar-22 Site Handover

Actual Level of Effort Actual Work Critical Remaining Work Page 1 of 1 TASK filter: All Activities
Primary Baseline Remaining Work Milestone © Oracle Corporation