Professional Documents
Culture Documents
MOM Korra - DRAFFT RME
MOM Korra - DRAFFT RME
Meeting Description
A coordination top management meeting of was held at the Site of Sodic Eastown on 21st August,
2019 between Rowad Modern Engineering (RME) and Consukorra Co. S.A.E (KORRA), to discuss the
following:
Meeting Agenda:
I. Postponement/Delay of Submissions
a. Shop Drawings
b. Material submittals and delivery of Long lead items
c. Supplier Approval Request (SAR)
d. KORRA’S Proposal for Building 8
II. Difference between IFC and IFT
III. Slab On Grade
IV. KORRA’s Personnel
V. Cost Reduction of Request For Proposals (RFP)
VI. Logistics Plan
VII.KORRA’s progress
This meeting was held in the presence of the following:
For RME:
Eng. Mohamed Ragab (Chief Operation Officer)
Eng. Mahmoud Mahlab (Operations Manager)
Eng. Waleed Barakat (Projects Manager)
Eng. Sayed Othman (Project Director)
Eng. Ahmed Hassan (MEP Manager)
Eng. Safwat Moussa (Technical Office Manager)
Eng. Amr Dawood (Project Control Manager)
Eng. Mohamed Ehab (Project Control Section Head)
Eng. Amr Eldiwany (Project Control Team Leader)
Eng. Reem Oraby (Contracts Engineer)
Eng. Mahmoud Shafique (Planning Engineer)
Eng. Mohamed Abdelbaky (Senior Electrical Engineer)
Eng. Ahmed Montaser (Senior Mechanical Engineer)
For KORRA:
Eng. Ayman Korra (Chairman)
Eng. Samir Selim (Chief Executive Officer)
Eng. Ahmed El Barbary (Project Manager)
Eng. Mohamed Idris (Project Manager)
Eng. Abdel Rahman El Naggar (Technical Office Manager)
Eng. Mohamed Osama (Planning Engineer)
Minutes of Meetings:
I. Postponement/Delay of Submissions
a. Shop Drawings
1. Only 7 out of 35 shop drawings are submitted from KORRA’s side till date.
(mechanical/electrical).
2. Mechanical shop drawings are delayed from KORRA’s side as they focused on
submitting the Electrical shop drawings.
3. KORRA shall submit a recovery plan for shop drawings submittals by 22nd August,
2019 while considering the early start as a datum. KORRA shall consider that time
float are not for its sole use.
4. Periodical tracking sheets from RME’s side -in regards to shop drawing
submittals- shall be sent to KORRA’s side, so that parties can follow up with the
relevant submittals.
Page 2
4. Pipes
Letter from Supplier (Sigma) was supposed to be submitted on 1st August, 2019
in regards to the pipes with diameters larger than 12 inches. KORRA promised to
submit the relevant letter shortly.
5. The undetermined submission dates under this point (Point C) shall be clearly
stated in the recovery plan which will be submitted by KORRA on 22nd August,
2019.
6. KORRA shall submit a recovery plan in this regard on 22nd August, 2019 while
considering the early start as a datum. KORRA shall consider that time float are
not for its sole use.
Page 3
V. Cost Reduction of Request For Proposals (RFP) SAR
1. All the RFPs submitted by KORRA do not necessitate cost reduction
2. In case of any cost reduction requested by Employer, KORRA shall submit the
same for approval. In which case, KORRA shall be reimbursed with the
reduced cost/price after deducting RME’s lost mark up.
VI. Logistics Plan
1. KORRA raised its concern in regards to Logistics Plan (Rev.05)
2. Based on previous agreement, parties (RME and KORRA) has discussed the
matter of logistics plan. Parties have concluded that the aforementioned plan
shall result in modification for 2 loops all of which shall necessitate installation
of additional valves amounting to 120,000 EGP. Furthermore, the logistics
plan may necessitate further additional quantities and reduction of quantities
at other parts.
3. Further meeting was held on 25th June, 2019 between parties in this regard
wherein parties have agreed on completion dated of pouring, insulation and
backfilling from RME’s side so that KORRA can proceed accordingly.
4. KORRA shall submit a detailed study in this regard for RME’s assessment.
VII. KORRA’s progress
1. KORRA shall commence the 1st fix at Building No.1 (Offices) within 2 weeks
from this meeting (maximum by 3rd September, 2019) with its regular
manpower and installing scaffolding.
Page 4