Professional Documents
Culture Documents
Analysis of Soil Nailed Earth Slope by Discrete Element Method
Analysis of Soil Nailed Earth Slope by Discrete Element Method
I-14, 1997
0 1997 Elsevier Science Ltd
Printed in Great Britain. All rights reserved
PII: SO266-352X(96)00010-9 0266-352X/97 $17.00+ .OO
ELSEVIER
Department of Civil Engineering, Korea Advanced Institute of Science and Technology, Taejon, Korea
(Received 9 August 1995; revised version received 8 July 1996; accepted 24 July 1996)
ABSTRACT
Soil nailing has been widely used during the last two decades, to stabilize
steep excavated slopes in several countries. In this study, the discrete element
method (DE&f) has been applied to evaluate the stability of reinforced slopes.
This method is capable of not only estimating tensile and shear stresses
mobilized in nails but also providing individual safety factors for soil and nails.
It has been assumed that the nailed slope is composed of slices connected
together with elastoplastic Winkler springs. In replacing nails by spring
elements, a function is proposed for evaluating shear and tensile forces in nails
which are induced by relative displacements between nail and adjacent soil.
Taking into account for the sequence of construction, the developed method
can predict the measured tensile forces in nails and hence it properly evaluates
both local and overall stabilities of the reinforced slope. 0 1997 Elsevier
Science Ltd. All rights reserved.
INTRODUCTION
Shear force
F = 2EIA3 . u, (1)
Tensile force
where a = ds
(2) For case II: u, > up at X = L (BC’s: E = 0 at X = 0 & u = up at
x = X,)
4 J. S. Kim et al.
The X, is the position in which the peak frictional stress starts to develop.
The distribution of shear stresses along the nail is assumed to be as shown in
Fig. 2(b). The tensile force developed at X = L can be obtained as follows.
FT ~DlrtX
u’-up=~- o AdX
EA
J-
(5)
= (LiAxp) JEAD75k tanh(aXp)up + DxrprEi *p)2
The behavior of normal and shear springs at the sides of slices is assumed to
be elastoplastic and defined by the Mohr-Coulomb criterion. The normal
springs do not yield in compression but they yield in tension. The shear
springs yield when the shear strength is reached for the soil. After the peak
strength is reached, the strength approaches the residual shear strength.
F
~f”‘““sul~
..:
.. ‘. x
.:’
/’
./ I4 X=L
,...
,...‘.....
(4 ut< up 03 Ut’ %
METHOD OF ANALYSIS
(6)
(7)
where cP and & are maximum strength parameters, and c, and & are
residual strength parameters.
The relative displacement between slices including the nail can be trans-
formed from the x-y coordinates system to a specific coordinates system
(normal and tangent to the slope of nail), as shown in Fig. 4. Then, the
displacements in the specific coordinates system are related with the dis-
placements in the x-y coordinate system by
1Sa?]=a+m
a : ground spring
m : ground - nail spring
NORMAL
(4 (W
Fig. 3. Discrete element modeling of the reinforced slope by Winkler springs.
J. S. Kim et al.
where the superscript q represents the number of element sides that the nail
crosses the potential failure line.
The formulation of the present method follows a similar procedure to the
previous research by Chang [9]. Let P be the mid point of the interface
between two slices as shown in Fig. 5. The displacement of a slice B relative
to a slice A at point P is then expressed as the following matrix form.
dP = RPhUb _ RPaUa
slice A slice B
Fig. 5. Shear and normal stresses between slices due to relative displacement.
&’ = APdP
(11)
Then, the normal and shear stresses at the slice interface are generated in
terms of the normal spring constant (k,), the shear spring constant (k,), and
components of d P. The resultant forces and moment can be obtained by
integrating these stresses over the interface.
For convenience, the side forces in the local coordinate system are trans-
formed into forces in the global coordinate system.
F; = (Ap)TFp (13)
$ = K,,$
(14)
where K, is a diagonal matrix for representing the effect of nail and its
components are krr = FT/ur (FT in eqns (3) or (4)) and k22 = 2EIh3. The
tilde (“) symbol stands for the nail coordinates system. With eqn (13) the
nail forces in the nail coordinate system may be transformed into forces in
the global coordinate system.
The forces acting on all sides of a slice should satisfy the equilibrium
requirement given by
J. S. Kim et al.
where N = side number of a slice, andf” = body force at the mass center of
element A. Combining eqns (9)-(16) the relationship between force and
moment of a slice and those of a nail can be obtained as follows:
where
Cap = - (RP") ‘(AP)TK&‘, and Da4 = -(Rr)T(p)TKnp (17)
In applying the DEM, the nailed slope is modeled by slices connected toge-
ther with springs as shown in Fig. 3. To consider the installation procedure
of nails according to each excavation step, a nail is installed as the spring of
the excavated face is eliminated. That is, at the initial ground condition, both
self weight and external loads are applied without any nails. After the first
nail is installed, the first spring Si is eliminated as the ground is excavated up to
the level. The simulation process for installing nails is incorporated by eqn (8).
This consideration of real excavation steps is more reasonable since only the
relative displacement of nail-ground after the installation of a nail is allowed
to have an effect on the computation of tensile force developed in the nail.
In the passive zone of soil mass, the resisting force developed in the nail
along the length is considered as a spring force at the expected failure sur-
face. When the resulting displacement is smaller than the pull-out displace-
ment of the nail, the pull-out spring constant is defined as in eqn (3).
However, when it is larger, it is defined as the displacement function of
eqn (14) with eqn (4). Therefore, in obtaining the global nonlinear equation
an iterative numerical computation is required. Furthermore, an inner part
non-linear solution scheme is necessary to calculate the value of XP.
The residual force which is computed during the solution process of the
nonlinear equation by DEM is defined as follows.
Analysis by discrete element method 9
R =fext
-fint(U) (18)
In a slope reinforced by soil nails, an external loadf,,, is composed of the
self weight of the ground and any external loads applied on the ground sur-
face, and may be assumed to remain constant during an excavation stage.
The internal load vector & is computed by eqn (17). The check on con-
vergence was carried out by setting a criterion as the relative ratio of the
norm of the residual force vector to the norm of the external load vector.
II R II
(19)
IlfextII < &
where generally E= 10e2 - 1O-5 is applied.
TABLE 1
Local and total safety factors
Ground Nail
Local SF.
Total S.F.
a = element No., q = zP or TV,T,,,,, = min [T, (pull-out strength), T, (tensile strength of nail)].
10 J. S. Kim et al.
yield state. Thus, the safety factor for nails is selected as a criterion in
determining the critical plane. However, there are cases where the magnitude
and the location of the maximum stress in nails have been measured in many
real field sites. Therefore, in analyzing these data, the expected failure surface
is selected as the plane on which the sum of tensile forces acting on nails is
the maximum.
Cl 35 1 15
TN
To have more confidence in using the proposed method a small scale test has
been carried out. An outline of the test is given in Fig. 8. The grain-size-dis-
tribution of the sand used in the small scale test is shown in Fig. 9. To reduce
the wall friction, the bentonite slurry is coated on the wall. The design para-
meters used were as follows; height of vertical wall = 2 m, number of nails
= 4, nail length = 1.5 m, inclination angle of nail = lo”, unit weight of soil
= 18.2 kN/m3, $ = 39”, c = 0, Young’s modulus of soil = 25,000 kN/m2
(assumed), diameter of nail hole = 0.06 m, diameter of steel = 0.01 m,
horizontal and vertical spaces of nail = 0.5 m x 0.5 m, maximum frictional
resistance of nail = 34.9 kN/m2, and up = 0.0065 m. The comparison
between the predicted and measured values of maximum tensile forces is
given in Fig. 10.
In the above examples, predictions for the axial tensile strength display
approximately the same trends of parabolic type as measured. In the case of
Cumberland Gap wall the magnitude of tensile forces is predicted relatively
15
q-N-
Y~WSd3"
6.0 M
GROUND
I
04
0 05 1 1: 2
TN
CONCLUSION
In this study, the DEM which has been used for a general stability analysis
was extended to be applicable to a nail reinforced steep slope. For this pur-
pose, a mechanism to simulate characteristics of interactive behavior of nail
and surrounding ground was established, and it was replaced by elastoplastic
springs. By utilizing the developed method, tensile forces mobilized in nails
could be predicted to some degree of accuracy, and local safety factors can
also be calculated. The results give assistance for the stability analysis of a
reinforced structure. The excavation steps followed for the real sequence of
construction were also considered in the analysis. The main feature of the
developed method is the ability to consider the real sequence of construction
and to appropriately take into account the observed interface behavior
between nails and the adjacent ground.
REFERENCES