Professional Documents
Culture Documents
Ir Sammy Cheung HKIE GD Workshop 2015
Ir Sammy Cheung HKIE GD Workshop 2015
Ir Sammy Cheung HKIE GD Workshop 2015
Sammy Cheung
Senior Geotechnical Engineer
GEO, CEDD
19 May 2015
OUTLINE OF PRESENTATION
Vertical Load
Horizontal Load
Pile Group
Negative Skin Friction
Foundations in marble areas
Objectives
Ground conditions in Hong Kong are complex and can pose major
challenge to piling design and construction (e.g. corestone-bearing
weathered profiles, karstic marble, deep and/or steeply inclined
rock head)
Piling design in Hong Kong is always criticized for overly
conservative design
Short pile scandals in Hong Kong (magic tape, etc.)
Simplified Borehole log Borehole B Borehole A Borehole log Simplified geology
geology B A
VI VI
Potential risk of using an
overly simplified
V
geological model
V (e.g. layered-model in
corestone-bearing saprolites)
IV
III
III
II
II
I I
submission
FOUNDATION DESIGN FOR PRIVATE PROJECTS
Buildings (Construction)
Regulations
AP/RSE Notes
Code of Practice for Foundations
(2004)
deemed-to-satisfy rules
more economic design may be
feasible by rational design method
Relevant PNAP for Foundation Submission for Private Projects
It is the behaviour of the ground after pile installation that controls pile
performance (pile soil interaction)
Varying ground conditions involve uncertainty and risk – opportunity
Completed works are buried; observations and supervision during the
installation process are important
In some cases, there may be time-dependent effects that could influence
the development of pile capacity in the long term
COMMON PILE TYPES IN HONG KONG
Bored piles & socketed H-piles – piles are usually designed as end-bearing
and limited shaft friction on rock. If depth of weathering is significant,
the piles behave as ‘friction piles’ instead.
PILE INSTALLATION
• Displacement piles
–“hammering steel or concrete into the ground with
sufficient energy to refusal"
• Replacement piles
–“dig a hole and fill with steel and concrete"
Sounds simple, but not so! Pile installation can affect pile material
(damage), the ground (disturbance) & surrounding facilities
EFFECTS OF PILE CONSTRUCTION ON GROUND
Deem-to-satisfy rules
Simplified rules
assumption
More economical design can be achieved!
RATIONAL PILE DESIGN APPROACH
Soil type 1
Qs = shaft capacity
Soil type 2
Qs = s x As
v
r
r
θ
s is interface friction
’ is effective angle of friction
Note - roughness of pile/ground interface is important, but difficult to
quantify in practice
TYPICAL VALUES IN SAPROLITES AND SANDS FOR METHOD 1
QB= qb x Ab
0.6
Pile Length Coarse sand
≥ 15
Ultimate End Bearing Capacity
Base diameter
0.4
SPT Nb Value
Fine sand
Normally consolidated silt
0.2
Coarse sand
Fine sand
0.0
0 5 10 15 20
Loose sand
0.75
Reduction Factor, fr
0.0
0 0.5 1.0 1.5 2.0 2.5
Total
Base
Pile Load
Shaft
Pile settlement
Ultimate QB typically develops at a pile settlement of @ 10% (clay) to 20%
(sand) pile diameter
Mobilisation Factors for Deriving Allowable Bearing Capacity
Qb Qs
Allowable Load Carrying Capacity, Qa = +
fb fs
Fluidity of concrete
10
15 2 hr
Depth (m)
20
2 hr
25
30 4 hr
4 hr
35
40 Set = 6 hr
Set = 6 hr
45
0 50 100 150 0 50 100 150 200 250 300
Concrete Pressure (kPa) Concrete Pressure (kPa)
Note: Faster concreting process will help to achieve higher wet concrete pressure, which
would help to achieve higher locked-in horizontal stresses in the ground
Swelling of granitic saprolite
due to stress
relaxation
* Important to ensure
sufficient excess slurry head
within pile bore
DILATANCY EFFECTS IN A DENSE SOIL WITH A ROUGH
PILE/SOIL INTERFACE
CHANGES IN EFFECTIVE HORIZONTAL STRESSES DUE TO DILATANCY EFFECTS
DURING SHEARING
r E
h’ =
r 1+
1 – Crack fresh concrete cover using double packer and 2 – Carry out shaft grouting for each manchette from bottom to
water within 24 hours of casting concrete. top.
Water cracking must be carried out for all grouting pipes in Target Grout Intake used so far in Hong Kong is 35 l/m2 Area
the barrette (even the spare ones). covered by each manchette or refusal pressure (around 50 bars),
whichever occurs first. The overall minimum average intake of 25
l/m2 over the whole frictional area.
If intake cannot achieved on some manchettes, the target intake
Typical Grout Mix for 1 m3 for the manchette immediately above, below or on its side is
increased if necessary.
Cement: 1000kg Bentocryl 86: 1.5 litres
Grouting for all pipes to be used in one barrette can be carried out
Water: 666 litres Daracem 100: 4 litres simultaneously.
Bentonite: 15 kg
SHAFT GROUTING PROCEDURE
Local Instrumented Test Data for Bored Piles
=0.6 =0.5 =0.4
250
C3
Maximum Mobilised Average Shaft
= 0.3
200
Resistance, max (kPa)
B2 P14
150 = 0.2
P1 B3 P21‐2
B11
B7T
B10
B4
100 P23
B7C
B9
P20
P19
P9 P7 B5
P15
P2 = 0.1
P22 P4 P6
B6C C2 B1
50 P13
B8C P21‐1
P11 P18
C1 P5
P17 B8T
P10 P8 P12
B6T
0
0 100 200 300 400 500 600 700
Mean Vertical Effective Stress, 'v (kPa)
C3
/N =
1.0
Maximum Mobilised Average Shaft
200
Resistance,max (kPa)
P14 B11
B2
150
P21-2 B3
P1
B7T B10 /N =
B4 B7C
100 0.5
B5 P7
P20 P19
P23 B9 P9 P2
P15
P22 P6
C2 B1
P16 B6C
50 P4
B8C P21-1 P5
P11 P13
B8T P18
P17
C1 P12
P8 P10
B6T
0
0 50 100 150 200
values from load tests tend to be towards the lower bound of that
expected for bored piles in granular materials (possibly due to low
horizontal stresses in weathered rocks, i.e. low Ko value)
SOME OBSERVATIONS
The method and the SPT method for pile design are not necessarily
consistent in that they may give different predictions
As a pragmatic approach, it is probably best to use both methods to assist in
decision-making regarding pile design capacity
It is important to make reference to the results of previous instrumented pile
load tests in similar ground conditions for the respective pile construction
methods [role of precedents + design by load tests]