DESIGN2 (FEED2)
(FEED
ONSHORE PIPELINE
SENIPAH - RU V BALIKPAPAN
NO part of this document may be reproduced, in any form or by any means, except as permitted by the
Author or PERTAGAS
REVISION SHEET
COMMENT SHEET
Reference /
No. Paragraph / PT. Pertamina Gas Comment BEI Response
Section
CLIENT
BY
POSITION
DATE
FRONT END ENGINEERING DESIGN 2
(FEED 2)
ONSHORE PIPELINE
SENIPAH - RU V BALIKPAPAN
TITLE DOCUMENT NUMBER REV PAGE
HOLD REGISTER
TABLE OF CONTENTS
CLIENT ................................................................
................................................................................................
................................. 3
BY................................................................
................................................................................................
......................................... 3
POSITION................................
.............................................................................................................................
............................. 3
DATE ................................................................
................................................................................................
.................................... 3
1. INTRODUCTION ................................
................................................................................................
....................................... 6
1.1 General ................................
................................................................................................
......................................... 6
1.2 SCOPE ................................
................................................................................................
.......................................... 7
1.3 Definitions ................................
................................................................................................
.................................... 7
1.4 Abbreviations ...............................................................................................
............................... 7
1.5 Units................................
................................................................................................
.............................................. 7
2. EQUIPMENT AND MATERI MATERIAL TO BE PURCHASED ..............................................
................................ 8
3. CONFLICTS ................................
................................................................................................
.............................................. 8
4. SCOPE OF WORK................................
................................................................................................
.................................... 8
4.1 General ................................
................................................................................................
......................................... 8
4.2 Schedule and Delivery ................................................................
................................................. 9
5. EXCEPTIONS / DEVIATI DEVIATIONS AND CLARIFICATION ..............................................
................................ 9
6. VENDOR DATA REQUIREM REQUIREMENT ................................................................
............................................. 9
6.1 General ................................
................................................................................................
......................................... 9
6.2 Size of Document ................................................................
....................................................... 10
6.3 No Of Copies ..............................................................................................
.............................. 10
7. SUPERVISION AT WORKS WORKSITE ................................................................
.............................................. 10
8. SPARE PARTS, SPECIAL TOOLS AND MANUAL BOOK K & CERTIFICATE ........ 11
8.1 Construction, Pre Pre-Commisioning,
Commisioning, and Commisioning Spare Parts ....... 11
8.2 Operating Spare Parts ................................................................
............................................... 11
8.3 Capital Spare Parts (if any requirement) ..................................................
................................ 11
8.4 Special Tools ..............................................................................................
.............................. 12
8.5 Manual Book & Certificate ................................................................
......................................... 12
9. QA/QC & REPORT REQUI REQUIREMENTS ................................................................
.................................... 12
9.1 General ................................
................................................................................................
....................................... 12
9.2 QA Audit ................................
................................................................................................
..................................... 12
9.3 Shop Inspection & Test Requirement .......................................................
................................ 12
9.4 Document & Report Requirement .............................................................
............................. 12
10. ADDITIONAL NOTES .............................................................................................
............................. 12
11. GUARANTEE................................
................................................................................................
.......................................... 13
11.1 Performance Guarantee ................................................................
............................................ 13
12. ATTACHMENTS ................................
................................................................................................
..................................... 13
FRONT END ENGINEERING DESIGN 2
(FEED 2)
ONSHORE PIPELINE
SENIPAH - RU V BALIKPAPAN
TITLE DOCUMENT NUMBER REV PAGE
1. INTRODUCTION
1.1 General
PT Pertamina Gas (Pertagas), hereafter known as COMPANY, plans to deliver
gas from Senipah KP 7.2 that is operated by Pertamina Hulu Mahakam to PT
PERTAMINA (Persero) Refinery Unit (RU V) Balikpapan, East Kalimantan, to fulfill
the gas demand at Refinery Unit (RU V) Balikp
Balikpapan
apan as part of the RDMP program.
COMPANY has initiated the Onshore Pipeline Senipah – RU V Balikpapan Project
and awarded to PT Berca Engineering International (under service contract) to
execute the Front End Engineering Design 2 (FEED 2).
The Onshore Pipeline
ipeline Senipah – RU V Balikpapan scope will comprise of
development of mini facility in Senipah and RU V Balikpapan area consist of gas
metering, pigging facilities, utilities and an onshore gas pipeline.
1.2 SCOPE
This requisition covers the requirements for Design, Engineering, Manufacturing,
Fabrication, Assembly, Testing, Inspection and Delivery of AC Fire Fighting and
Safety Equipment to be performed and completed by VENDOR/Sub-VENDOR
VENDOR/Sub (or
SUBCONTRACTOR) for COMPANY at Senipah - RU V Balikpapan, East
Kalimantan.
1.3 Definitions
The following definitions shall apply to this document and all other referenced
documents.
1.4 Abbreviations
The following abbreviations will be used throughout this document:
Refer to attachment-1
1 section 1.
1.5 Units
SI units are used in this document unless noted otherwise.
FRONT END ENGINEERING DESIGN 2
(FEED 2)
ONSHORE PIPELINE
SENIPAH - RU V BALIKPAPAN
TITLE DOCUMENT NUMBER REV PAGE
The applicable documents are listed and attached in Attachment 2-“Fire Fighting
and Safety
ety Equipment
Equipment”.. These documents are part of this requisition and shall be
read and followed to understand the complete scope of work
work.
3. CONFLICTS
If there is any conflict between this requisition and the documents referred to in
Attachment 2-“Applicable
Applicable Documents for Fire Fighting and Safety
Equipment”thethe order of precedence shall be as follows:
Local Regulation
This Request for Quotation document
Accepted Deviation and Clarification
Data Sheet
Other Project Specifications / Documents
Reference Codes & Standards
VENDOR shall identify and state such conflict(s) in the course of bidding or in his
proposal to obtain CONTRACTOR’s / COMPANY’s resolution.
In event of conflict between these documents,, its attachments, drawings and codes/
standards listed
ed above, Vendor shall see Purchaser decision before proceeding with
the work.
4. SCOPE OF WORK
4.1 General
VENDOR’s scope of work shall include engineering, supply of material, fabrication
and assembly at VENDOR’s/MANUFACTURER’s shop, shop testing, inspection,
painting,
ainting, marking, preservation/protection, packing, and inland transportation, of the
equipment and material listed, but not limited to, in Section 3.0 and Attachment 1 -
”Scope of Work and Supply for Fire Fighting and Safety Equipment”.
Equipment
FRONT END ENGINEERING DESIGN 2
(FEED 2)
ONSHORE PIPELINE
SENIPAH - RU V BALIKPAPAN
TITLE DOCUMENT NUMBER REV PAGE
5. EXCEPTIONS / DEVIATI
DEVIATIONS AND CLARIFICATION
VENDOR’s Proposal shall be submitted in compliance with this Requisition and
Referenced Documents.
However, compliance wi
with
th the requisition and the referenced documents shall not
relieve the VENDOR from his responsibility. VENDOR may propose Deviations or
Exceptions if VENDOR has a justified reason to deviate from the requisition and the
referenced documents.
Exceptions and Deviations must be approved by COMPANY prior to placing order. In
general, deviations shall be avoided, unless they are technically better alternatives.
Any Deviation/Exception proposed by VENDOR after placing the order shall not be
accepted and consequen
consequential
tial cost/schedule impact shall be born / absorbed by the
VENDOR.
6.1 General
For Quotation purposes, V VENDOR shall supply the documents as stated in the list,
but not limited to the following:
Quotation, including best promised delivery time/date.
Company profile.
Past Experience of supplying the similar scope and service of equipment.
FRONT END ENGINEERING DESIGN 2
(FEED 2)
ONSHORE PIPELINE
SENIPAH - RU V BALIKPAPAN
TITLE DOCUMENT NUMBER REV PAGE
6.3 No Of Copies
At Bid stage : 3 copies of all drawings and documents
For Review / Approval : 2 copies of all drawings and
documents, 1 Original and 2 e-files.
e
VENDOR Data B
Book : 1 original, 3 copies and 2 softCopies
soft on
CD-ROM / DVD -ROM ROM
Manufacturer’s Data Reports : 1 original, 3 copies and 2 soft Copies
on CD-ROM/ DVD -ROM ROM
Operation
ration and Maintenance Manual : 1 original, 3 copies and 2 soft copies on
CD-ROM/ DVD – ROM
7. SUPERVISION AT WORKS
WORKSITE
VENDOR may be requested to ass assign
ign their supervisor or engineer to the work site
for installation, pre-commissioning,
commissioning, commissioning and start
start-up
up of the equipment
supplied by VENDOR. Such work should be in a separate contract on each
occasion.
For any such work, VENDOR shall provide item
itemized
ized quotation to cover the following:
Per-diem
diem Rate,
Period required based on VENDOR’s experience,
Mob/Demob
FRONT END ENGINEERING DESIGN 2
(FEED 2)
ONSHORE PIPELINE
SENIPAH - RU V BALIKPAPAN
TITLE DOCUMENT NUMBER REV PAGE
For Pre-commissioning:
commissioning:
Site Commissioning Assistance
NOTE: VENDOR shall supply all complete equipment and materials in VENDOR's
scope of work with proper instructions and detailed packing list so as to
carry out the site work needing neither VENDOR's supervisor or engineer.
8. SPARE
E PARTS, SPECIAL TOO
TOOLS AND MANUAL BOOK & CERTIFICATE
9.1 General
VENDOR shall establish and operate the quality system, which fully meets ISO
ISO-
9001. VENDOR shall submit the outline of Quality MaManagement
nagement Program and
procedure with his bid.
9.2 QA Audit
CONTRACTOR and/or COMPANY have the right to audit VENDOR’s or sub sub-
VENDOR’s shop whenever necessary without any costs, expenses and schedule
impact to CONTRACTOR and COMPANY.
c. The design life of Fire Fighting and Safety Equipment shall be 20 years
11. GUARANTEE
VENDOR shall guarantee the safe and satisfactory operation and flexibility of the
unit/equipment 18 month after delivery to the contr
contract
act delivery point or up to 12
month after successful startup and commissioning whichever earlier, and the
following performance:
12. ATTACHMENTS
Support equipment and commissioning procedure shall be submitted by the
VENDOR for approval before load out from VENDOR's site
Attachments shown below shall form a part of requirements of this requisition.
Attachment 1 : Scope of Work and Supply of Fire Fighting and Safety
Equipment
Attachment 2 : Applicable Documents of Fire Fighting and Safety Equipment
PERTAGAS SENIPAH-RU V BALIKPAPAN PIPELINE RFQ for Fire Fighting and Safety Equipment
ATTACHMENT – 1:
SCOPE OF WORK AND SUPPLY FOR Fire Fighting and Safety Equipment
Included
NO. ITEM Quantity Notes
(Required)
A Scope of Supply
Fire Fighting and Safety Equipment consist of 1 LOT Senipah and RU V
the following major equipment: Balikpapan
- Fire Extingusher X
- Fire Hydrant X
- Fire Monitor X
- First Aid Kit X
- Safety Sign X
B Scope of Work
SNBP2-00-HSE-RFQ-001 Page1of 1
PERTAGAS SENIPAH-RU V BALIKPAPAN PIPELINE RFQ for Fire Fighting and Safety Equipment
ATTACHMENT-2:
APPLICABLE DOCUMENT FOR FIRE FIGHTING AND SAFETY EQUIPMENT
2. Project Document