Subject: CUBES TEST FOR ESTABLISHMENT OF GCUF UNIVERSITY CINIOT CAMPUS REQUIRED
Dear Sir,
Enclosed herewith please find three (3) sample cubes of the following for fourteen days
(14) compressive strength test.
1:1.5:3 ratio three concrete cubes casted on 1-10-21 and mentioned on cubes. Test
results may kindly be sent to the undersigned and debit the testing charges to, M/S
Elcon Associates contractor for subject project.
Thanking you
Yours Truly
(Billal Mehmood)
Resident Engineer(Chiniot)