Professional Documents
Culture Documents
New Instruction To Bidders MKTG Ofc FHZ
New Instruction To Bidders MKTG Ofc FHZ
New Instruction To Bidders MKTG Ofc FHZ
1.0 INTRODUCTION
FILINVEST LAND INCORPORATED (FLI) desires to engage the services of a pre-qualified CONTRACTOR
with thorough experience in construction of the above-mentioned project based on parameters furnished by
Filinvest.
It shall be the sole responsibility of the Bidder, prior to submitting his Bid and before entering into contract with
FLI, to determine and to satisfy himself by such means as he considers necessary or desirable as to all
matters pertaining to the project such as: the nature and condition of the site; transportation and
communication; water and power supply facilities; availability of materials, manpower, equipment and other
resources in the vicinity; and other factors that may affect the cost; duration and method of construction of the
Project.
The cost of visiting the Site shall be at the Bidder’s own expense.
If any discrepancy or divergence is found between Drawing and Specification, the Specification shall take
precedence over the Drawing unless otherwise specifically stated to the contrary in the specification. Should a
conflict occur between Drawings, or between Specifications, or between Drawings and Specifications, the
contractor shall be deemed to have allowed in the Contract Price for the higher cost of undertaking the Work.
The Bids & Awards Department shall compile all queries and subsequently issue the responses to Bidders,
including minutes of the pre-bid conference prior to the bid submission. The Bids & Awards Dept. shall also
issue supplemental notices and/or bid bulletins for purposes of clarification and/or modification on the Bid
Documents. Oral Interpretations of the Bid Documents shall not be binding. Where the supplemental notice /
bid bulletin is on a matter of substance, the deadline for the submission of bids may be extended
appropriately.
4.0 PRICING
The unit rates “Total” for items in the bid breakdown shall be split into two sub-unit rates as follows:
4.1 Unit rate for “Materials” shall include for material cost (including all taxes and profit in connection with the
ordering of such materials) per unit of the items delivered to street level of site.
4.2 Unit rates for “Others” The rate inserted shall include for:
a. Labor and all costs in connection therewith;
b. Design to the extent required by the specification;
c. Taking delivery, unloading, storing, returning packing, handling, hoisting, lowering, etc of materials;
1
d. Fitting and fixing materials and goods in position including for all auxiliary materials for fixing, such as
mortar for bedding and jointing, adhesive and all similar items of a like nature, painting and finishing
as specified;
e. Use of plant and tools;
f. All cutting and waste;
g. Establishment charges, overhead and profit;
h. VAT and all other taxes in connection with the above.
Failure to submit the said requirements could mean bid proposal’s disqualification.
No Bid Bond is required for this project, however bids shall remain valid for a period of Sixty (60) calendar
days from date of submission.
FLI reserves the right to reject any or all bids, to waive any formality therein, and to accept such bid as it
considers most advantageous.
10.0 MATERIALS
a. All Contractor supplied materials shall be subject to FLI approval prior to installation.
3
b. All material tests will be shouldered by the Contractor and shall be conducted at independent testing
laboratories acceptable to the Owner.
c. Owner Supplied Materials will be delivered to jobsite and be directly issued to the Contractor.
d. Storage and security of construction materials shall be responsibility of the Contractor. All loses due to
pilferages, wastages etc. shall be borne by the Contractor.
e. All excess Owner Supplied Materials shall be returned to FLI.
The net total of such errors if net addition will be deemed to be interpreted as an overall discount against the
lump sum bid price. Subsequent clarified / revised bid submission for it to remain valid must not be higher than
the original bid offer except if covered by bid bulletin / bid addenda which revise the original scope of work.
JF DAWAL PP MUÑEZ
QS – BIDS & AWARDS LEAD QS - BIDS & AWARDS
PJ BALAJADIA RT BAUTISTA
CONTRACT ADMIN IN-CHARGE SVP - BIDS & AWARDS
- BIDS & AWARDS