Quality Walkthrough

Site: BS VI PROJECT, IOCL, PARADIP REFINERY


Prepared by: Sushil Dey & A.Waheedu.
Participates: Suvadip Bhattacharjee, Rajeev Kumar-Lead-QA/QC. Kaustav Samanta, TEL-QA/QC.

LocationFabrication Yard,KHDS & Pipe Rack.


Date: 22.12.2021
Time: 10:00 AM
Short Description Recommended corrective
Sl.No. Date & Time Area Action by/Target date Picture
observation action

Preservation of Valve shall


16 ‘’ Gate valve kept on
be done (to be cleaned
1 22.12.2021 Fab.Yard ground and found TEL-COMPO / 24.12.2021
from inside and flange to
derbies inside the valve.
be protected on both side).

All final painted spools to


Final painted spools
be kept on wooden
2 22.12.2021 Fab.Yard found on ground and TEL-COMPO / 27.12.2021
sleepers and flange to be
damaged paint.
protected.
Welding electrodes
Welding electrodes baking
baking control register
3 22.12.2021 Fab.Yard record shall be maintained TEL-COMPO / 24.12.2021
was found not in proper
in proper manner.
manner.

All welding m/c.


Few welding m/c. found
fitness/calibration reports to
4 22.12.2021 Fab.Yard fitness/calibration validity TEL-COMPO / 28.12.2021
be submitted for tkIS/IOCL
near to expiry.
review.

Unwanted tack-weld on
Pipe fixed with fixture by pipe surface not
5 22.12.2021 Fab.Yard TEL-COMPO / 24.12.2021
tack-weld. acceptable, to be removed
and DP tested.

Pipes kept direct on


All pipes to be kept on
6 22.12.2021 Fab.Yard ground and got paint TEL-COMPO / 27.12.2021
wooden plank.
damaged.
7 150-P-016-1203- Both spool Orifice flange TEL-COMPO / 24.12.2021
D1AP,Spl.01,Orifice flange inside ground flash to be
welded and erected. confirmed ( report to be
submitted).
KHDS
22.12.2021
Unit

All joints shall be dismantled


Near C-002,small bore
KHDS and cleaned and fit-up to be
8 22.12.2021 piping joints fit-up made TEL-COMPO / 31.12.2021
Unit done by GTAW welding
by SMAW process.
process only.

Fabricated spools got


paint damaged due to
KHDS All these spools shall be re-
9 22.12.2021 mishandling and kept on TEL-COMPO / 31.12.2021
Unit blast and repainting.
ground near KHDS road
side.