Hydrostatic Pressure Procedure

PSL-2
PT. FRONTKEN INDONESIA
Owner: Technical Engineering Dated Last Revision: 02 Aug 2020
Revision: 0 Doc. No.: 01/PTFI/PTP/2021

1. Pre-Test Preparation

1.1. General

All personnel participating in this test shall fully familiarize themselves with this test procedure prior to
testing.

1.2. Test Fluid

Hydrostatic pressure cycling test: Water

1.3. Q.A. Requirements

All testing is to be witnessed by assembly personnel. Engineering shall be notified for all function and
interface testing. All pressure testing shall be performed with calibrated chart recorders, and

1.4. Safety

1.4.1. All personnel actually involved with testing must read this test procedure before starting
the test.

1.4.2. Prior to perform Hydro Test ensure all personnel use proper PPE as per Company Regulation and
Policy

1.4.3. Please contact PT. Pasundan Tiga Energi Representative and HSE Representative for external
personnel requirement.

1.5. Acceptance Criteria

1.5.1. Hydrostatic Test at room temperature

No visible leakage is allowed.

Page 1 of 15
01/PTFI/PTP/2021
Hydrostatic Pressure Procedure
PSL-2
PT. FRONTKEN INDONESIA
Owner: Technical Engineering Dated Last Revision: 02 Aug 2020
Revision: 0 Doc. No.: 01/PTFI/PTP/2021

Pressure shall be considered stabilized, when the change rate is no more than 5% of the testing pressure
per hour or 3.5 Mpa. (500 psi) per hour whichever is less.

Pressure shall remain within 5% of the testing pressure or 3.5 MPa (500 psi), whichever is less, during
the hold period.

1.5.2. Start of Hold Period

Hold periods shall start after pressure and temperature stabilization has occurred and the equipment
with pressure monitoring device has been isolated from the pressure source.

1.5.3. Pressure Stabilization

The pressure shall be considered stabilized, when the change rate is no more than 5% of the testing
pressure per hour or 3.5 MPa (500 psi)/hour whichever is less. Pressure shall remain within 5% of the
testing pressure or 3.5 MPa (500 psi), whichever is less, during the hold period.

2. Equipment Preparation

All Equipment should be at Hydro Test Room Area

All parts must be de-greased prior to assembly

All assembly work must be done in a clean, dry area.

Use short hoses to prevent unnecessary pressure drops during stabilization and hold periods.

Record the serial numbers of the assembly Part.

Page 2 of 15
01/PTFI/PTP/2021
Hydrostatic Pressure Procedure
PSL-2
PT. FRONTKEN INDONESIA
Owner: Technical Engineering Dated Last Revision: 02 Aug 2020
Revision: 0 Doc. No.: 01/PTFI/PTP/2021

3. Hydrostatic Pressure Test

3.1. Pressure Cycle Test for Casing Head Assembly

3.1.1. Body Test

Please refer to Drawing No.1 & Drawing No.2 Testing Configuration for detail

Ensure All Gate Valve in Fully Open Position

Fill up the Casing Head with water

Apply Low pressure 1,000 Psi and hold until 3 Minutes to the Casing Head through test port

Apply Hydro Static Pressure as per Table 1

Maintain the pressure for minimum period of 5 minutes.

Bleed off the pressure to the atmospheric level.

3.1.2. Seat test

Exercise Gate Valve to avoid pressure trap

Valve should be in fully close Position

Apply Low pressure 1,000 Psi and hold until 3 Minutes through

Apply Working Pressure as per Table 3

Maintain the pressure for minimum period of 5 minutes.

Bleed off the pressure to the atmospheric level.

Page 3 of 15
01/PTFI/PTP/2021
Hydrostatic Pressure Procedure
PSL-2
PT. FRONTKEN INDONESIA
Owner: Technical Engineering Dated Last Revision: 02 Aug 2020
Revision: 0 Doc. No.: 01/PTFI/PTP/2021

Drawing No.1
Casing Head for Slip on Weld Configuration
Note :
1. Casing Head Assembly
2. Test Pin Assembly x 4 ½” IF thd Pin
3. Ring Gasket
4. Stud with Two Nuts
5. Flange 4 ½” IF Thd Box

Page 4 of 15
01/PTFI/PTP/2021
Hydrostatic Pressure Procedure
PSL-2
PT. FRONTKEN INDONESIA
Owner: Technical Engineering Dated Last Revision: 02 Aug 2020
Revision: 0 Doc. No.: 01/PTFI/PTP/2021

3.2. Pressure Cycle Test for Casing Spool Assembly

3.2.1. Body Test

Please refer to Drawing No.3 Testing Configuration for detail

Ensure All Gate Valve in Fully Open Position

Fill up the Casing Spool with water

Apply Low pressure 1,000 Psi and hold until 3 Minutes to the Casing Spool through test port

Apply Hydro Static Pressure as per Table 1

Maintain the pressure for minimum period of 5 minutes.

Bleed off the pressure to the atmospheric level.

3.2.2. Seat test

Exercise Gate Valve to avoid pressure trap

Valve should be in fully close Position

Apply Low pressure 1,000 Psi and hold until 3 Minutes through

Apply Working Pressure as per Table 3

Maintain the pressure for minimum period of 5 minutes.

Bleed off the pressure to the atmospheric level.

Page 5 of 15
01/PTFI/PTP/2021
Hydrostatic Pressure Procedure
PSL-2
PT. FRONTKEN INDONESIA
Owner: Technical Engineering Dated Last Revision: 02 Aug 2020
Revision: 0 Doc. No.: 01/PTFI/PTP/2021

Drawing No.3
Casing Spool Configuration

Note :
1. Casing/Tubing Spool Assembly
2. Test Flange
3. Test Flange
4. Ring Gasket
5. Stud with Two Nuts
6. Stud with Two Nuts

Page 6 of 15
01/PTFI/PTP/2021
Hydrostatic Pressure Procedure
PSL-2
PT. FRONTKEN INDONESIA
Owner: Technical Engineering Dated Last Revision: 02 Aug 2020
Revision: 0 Doc. No.: 01/PTFI/PTP/2021

3.3. Pressure Cycle Test for Casing/Tubing Spool Assembly

3.3.1. Body/Shell Test

Please refer to Drawing No.4 Testing Configuration for detail

Ensure All Gate Valve in Fully Open Position

Fill up the Tubing Spool with water

Apply Low pressure 1,000 Psi and hold until 3 Minutes to the Tubing Spool through test port

Apply Hydro Static Pressure as per Table 1

Maintain the pressure for minimum period of 5 minutes.

Bleed off the pressure to the atmospheric level.

3.3.2. Seat test

Exercise Gate Valve to avoid pressure trap

Valve should be in fully close Position

Apply Low pressure 1,000 Psi and hold until 3 Minutes through

Apply Working Pressure as per Table 3

Maintain the pressure for minimum period of 5 minutes.

Bleed off the pressure to the atmospheric level.

Page 7 of 15
01/PTFI/PTP/2021
Hydrostatic Pressure Procedure
PSL-2
PT. FRONTKEN INDONESIA
Owner: Technical Engineering Dated Last Revision: 02 Aug 2020
Revision: 0 Doc. No.: 01/PTFI/PTP/2021

3.4. Pressure Cycle Test for Assembly Single Stack-Up Tree Assembly

3.4.1. Body Test

Please refer to Drawing No.5 Testing Configuration for detail

Ensure All Gate Valve in Fully Open Position

Fill up the X-Tree with water thru Tree Cap Adapter

Apply Low pressure 1,000 Psi and hold until 3 Minutes to the Tubing Spool through test port

Apply Hydro Static Pressure as per Table 1

Maintain the pressure for minimum period of 5 minutes.

Bleed off the pressure to the atmospheric level.

3.4.2. Seat test

3.4.2.1. Lower Master Valve

Exercise Gate Valve to avoid Pressure Trap

Lower Master Valve should be in fully close

Apply Low pressure at upstream 1,000 Psi and hold until 3 Minutes and monitor at down stream

Apply Gate Valve working pressure through test port

Maintain the pressure of downstream for minimum period of 5 minutes.

Bleed off the pressure to the atmospheric level.


Page 8 of 15
01/PTFI/PTP/2021
Hydrostatic Pressure Procedure
PSL-2
PT. FRONTKEN INDONESIA
Owner: Technical Engineering Dated Last Revision: 02 Aug 2020
Revision: 0 Doc. No.: 01/PTFI/PTP/2021

3.4.2.2. Upper Master Valve

Lower Master Valve should be in fully open

Upper Master Valve should be in fully close

Apply Low pressure in upstream 1,000 Psi and hold until 3 Minutes and monitor in down stream

Apply Gate Valve working pressure through test port

Maintain the pressure of downstream for minimum period of 5 minutes.

Bleed off the pressure to the atmospheric level.

3.4.2.3. Swab Master Valve

Upper Master Valve should be in fully open

Swab Valve should be in fully close

Apply Low pressure 1,000 Psi and hold until 3 Minutes

Apply Low pressure in upstream 1,000 Psi and hold until 3 Minutes and monitor in down stream

Apply Gate Valve working pressure through test port

Maintain the pressure of downstream for minimum period of 5 minutes.

Bleed off the pressure to the atmospheric level.

Page 9 of 15
01/PTFI/PTP/2021
Hydrostatic Pressure Procedure
PSL-2
PT. FRONTKEN INDONESIA
Owner: Technical Engineering Dated Last Revision: 02 Aug 2020
Revision: 0 Doc. No.: 01/PTFI/PTP/2021

3.4.2.4. Production Wing Valve

Lower Master Valve should be in fully open

Upper Master Valve should be in fully open

Swab Valve should be in fully open

Production Valve should be in fully close

Apply Low pressure in upstream 1,000 Psi and hold until 3 Minutes and monitor in down stream

Apply Gate Valve working pressure through test port

Maintain the pressure of downstream for minimum period of 5 minutes.

Bleed off the pressure to the atmospheric level

Page 10 of 15
01/PTFI/PTP/2021
Hydrostatic Pressure Procedure
PSL-2
PT. FRONTKEN INDONESIA
Owner: Technical Engineering Dated Last Revision: 02 Aug 2020
Revision: 0 Doc. No.: 01/PTFI/PTP/2021

Drawing No.3
X-Tree Configuration

Note :
1. Test Flange
2. Lower Master Valve
3. Upper Master Valve
4. Swab Master Valve
5. Prod. Wing Valve
6. Ring Gasket
7. Stud with Two Nuts
8. Plug

Page 11 of 15
01/PTFI/PTP/2021
Hydrostatic Pressure Procedure
PSL-2
PT. FRONTKEN INDONESIA
Owner: Technical Engineering Dated Last Revision: 02 Aug 2020
Revision: 0 Doc. No.: 01/PTFI/PTP/2021

4. Dismantle and Inspection

4.1. Dismantle the test equipment.

4.2. Visually inspect the Wellhead and X-Tree for any damage.

4.3. Record and report the damage, if any, to the engineering department.

6. Record

A chart recorder shall be used on all hydrostatic tests complete with identify of the Equipment, dated,
and signed.

5. Reference

Table 1 Hydro Static Body Test Pressure

Table 2 Recommended Torque for Flange Bolting (US Customary Units)

Table 3 Maximum Rate Working Pressure

Table 4 Hydrotest Chart List

API 6A Latest Edition

Page 12 of 15
01/PTFI/PTP/2021
Hydrostatic Pressure Procedure
PSL-2
PT. FRONTKEN INDONESIA
Owner: Technical Engineering Dated Last Revision: 02 Aug 2020
Revision: 0 Doc. No.: 01/PTFI/PTP/2021

Table 1
Hydro Static Body Test Pressure

Page 13 of 15
01/PTFI/PTP/2021
Hydrostatic Pressure Procedure
PSL-2
PT. FRONTKEN INDONESIA
Owner: Technical Engineering Dated Last Revision: 02 Aug 2020
Revision: 0 Doc. No.: 01/PTFI/PTP/2021

Table 2
Recommended Torque for Flange Bolting (US Customary Units)

Page 14 of 15
01/PTFI/PTP/2021
Hydrostatic Pressure Procedure
PSL-2
PT. FRONTKEN INDONESIA
Owner: Technical Engineering Dated Last Revision: 02 Aug 2020
Revision: 0 Doc. No.: 01/PTFI/PTP/2021

Table 3
Maximum Rate Working Pressure

Page 15 of 15
01/PTFI/PTP/2021