Component Scrap

 Component Scrap: scrap of a component that may break during production of an assembly.

-You can enter values for calculating component scrap in the material master or the BOM in the
BOM on the Item Detail Screen General Data (data block for quantity data). This component
scrap is only relevant for the individual BOM.
-In the material master (view MRP 4) in the Component scrap field. This component scrap is
relevant for all BOMs.
-The component scrap quantity maintained for a material component in the BOM has the higher
priority.

Note: Component scrap increases the dependent requirements quantity of the component.
In the BOM on the Item detail screen: basic data under Quantity data. This component scrap is
only relevant to the individual BOM.

In the material master record on the MRP 4 screen under Requirements explosion. If the same
component scrap applies to a material in a number of BOMs, then it can be maintained in the
material master record.
·          Component scrap is used in material requirements planning (MRP) to determine the
quantities of components required. When exploding the bill of material (BOM), the
system increases the required quantities of the components by the calculated scrap
quantity
Component Scrap - Dependencies
·          Component scrap maintained for a material component in a BOM overrides the
component scrap maintained in the material master record.
·          If there is also assembly scrap for a higher-level assembly, the system adds together the
two types of scrap
BOM Item detail screen: Basic data
 If the component scrap is only relevant to the      individual BOM, then it can be maintained in
the BOM Item detail screen