BECM 4203 - Lecture 4
BECM 4203 - Lecture 4
1.25
1.0
0.90
( 3 × 200) +(1 × 300) = 500 + 600 + 1050 + 500 + 600 + 300 = $ 3550
CT = LT + HT + DT + RT + ST
CT = Cycle Time
LT = Loading Time
HT = Hauling Time
DT = Dumping Time
RT = Returning Time
ST = Spotting Time
The returning haul unit may need to join a waiting line before it can be
loaded again, and it may have to wait for assistance to be spotted in a
position where it can be loaded. If this time is considered at all, it is
generally assumed to be a fixed time known as spotting time (ST).