Project Pronet Surabaya

TIME LINE
No Keterangan ### Tuesday, December 13, 2022 ### Thursday, December 15, 2022
1 Koordinasi Ijin shellter
2 Tarikan BB Tower -+ 1500 m Masuk tower Team Pak mus & dimas Team Pak mus & dimas
3 Pasang ODP dan OTB Tower Team Pak mus & Dimas & Dani Dani & Dimas
4 install pondasi ODC Outdor Team Pak mus & Dimas & Dani Dani & Dimas
5 Interkoneksi indosat Dani & Dimas Dani & Dimas
6 Set up OLT Dani & Dimas
7 OLT live Dani
8 Pasang ke pelanggan 1 Dani & Dimas
9 Koordinasi SOP Pronet Rifki Rifki