AL-Rakhees Contracting Company

QA Department
Monthly Progressive Report/ AL-Sweflah Bridge

Improvement
No: Category Situation Description Impact on Project Analysis or causes
Recommendation

Develop Communication and


The execution of plan were not
Communication plan were Miscommunication and delay of training plans and assign
-1 Communication Management co-ordinated with different
created late in project document ownership for development and
department of project
execution
strict dates were not set or
Set project update milestone
adhered to accommodate
-2 Time Management Project timeline were missed Delay in implementation and pre-set dates/time for
changes in scope or changes is
update
deliverable due dates
The technical department didn't Determine the correct amount of
Natural disaster were not considered the weather change time for project completion
-3 Time Management Delay in project schedule
taken in time schedule and raining season during maling taking in account the weather
of Time Schedule changes and rainy season

Prepared by: Eng. Sunil Deth Revised by: Eng. Awaz AL-Hakem
Date: 21/07/2022 Date: 24/07/2022

Signature: Signature: